A. P. SEN, V. D. TULZAPURKAR, Y. V. CHANDRACHUD
Hind Construction Contractors By Its Sole Proprietor Bhikam Chand Mulchand Jain (Dead) By Lrs – Appellant
Versus
State Of Maharashtra – Respondent
Key Points:- The court analyzes whether time was of the essence of the contract and how extensions or waivers affect that status. (!) (!) (!) - It considers that if time is not of the essence or has been waived, the employer may fix a reasonable time and rescind for breach; otherwise rescission may be unjustified. (!) (!) - The presence of extension provisions (Clause 6) and penalty provisions (Clause 2) influence whether time is fundamental and whether forfeiture is permissible. (!) (!) - The decision holds that rescission was wrongful and demands refund of security deposits and unpaid amounts plus interest, given time was not essential and extension could have been granted. (!) (!) - The contractor sought extension prior to expiry; the lack of timely extension contributed to the breach analysis. (!) (!) - The High Court’s approach differed from the trial court by assuming non-essence of time; the Supreme Court restored the trial court’s view and allowed recovery. (!) (!) - The contract included differential treatment for progress and penalties that bear on the time-essence analysis. (!) (!) (!) - The court notes that waivers or extensions can render time non-essential, altering the remedy from forfeiture to breach with damages. (!) (!) - The judgment emphasizes evaluating intent from contract terms and surrounding correspondence, including rescission letters. (!) (!)
Judgment
TULZAPURKAR, J.:- These appeals by certificate of fitness granted by the High Court of Judicature at Bombay are directed against that Courts common judgement and decree dated September 9/10, 1968, passed in two cross appeals being First Appeals Nos. 245 of 1962 and 844 of 1961.
2. A contract for the construction of an aqueduct across the Alandi River at Mile No. 2 of the Nasik Left Bank Canal of the total value of Rs.1,07,000 was granted to the appellant-plaintiff (originally a partnership but later a proprietary firm of contractors) by the respondent-defendant (the State of Maharashtra) after the formers tender was accepted on June 17, 1955. On July 2, 1955 the Executive Engineer issued the work order to the appellant-plaintiff directing him to commence the work by July 5,1955 intimating in clear terms that the stipulated date for starting the work would be reckoned from July 5, 1955. The formal regular contract in prescribed Form B-2/1 of 1955-56 (EX.34)containing the terms and conditions as well as the Schedules, Specifications etc. was executed by the parties on July 12, 1955. A security deposit of Rs.4,936 was kept by the appellant-plaintiff with the respondent-defendan
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.