SupremeToday Landscape Ad
Back
Next
Headnote Court Copy Facts Arguments Court observation Judicial Analysis Case Map Category Hierarchy Table of Content
Listen Article Pause Article
judgment-img

2009 Supreme(Gau) 503

IN THE HIGH COURT OF GAUHATI
C.R. Sarma, J.
Raj Narayan Paul – Appellants
Vs.
State of Assam and other – Respondent
Writ Petition (C) No. 5650 of 2006
Decided On: 30.07.2009

Subject

Public Procurement - Tendering Process

Headnote

Writ Petition - Tax assessment - Bidders were asked not to tender on percentage based rate - Order communicated by the Chairman, Respondent No. 4 accepting the offer of the Respondent No. 5 for construction of the Market for Group B work Ward No. 5 and the allotment of the said construction work in favour of Respondent No. 5 on the basis of tender notice is under challenge in this writ petition - Held, issuance of copy to the Chairman, Development Authority, who happened to be the father of the Respondent No. 5 is not sufficient to draw inference that the said father of the Respondent No. 5 had played any role in the said allotment of work - Therefore, Court find no substance in the contention of the Petitioner that undue favour was shown to the Respondent No. 5 - Petition dismissed.

Advocates appeared:
For Appellant/Petitioner/Plaintiff:J.P. Sarma, Advocate
For Respondents/Defendant:B. Chetry, Advocate

JUDGMENT

C.R. Sarma, J.

1. The order dated 27.06.07 communicated by the Chairman, Dhubri Municipal Board. Dhubri Respondent No. 4 accepting the offer of the Respondent No. 5 for construction of the Lainey Market (Ground floor) for Group B work at Dhubri Town, Ward No. 5 and the allotment of the said construction work in favour of Respondent No. 5 on the basis of tender notice is under challenge in this writ petition.

2. The Chairman, Municipal Board, Dhubri i.e. Respondent No. 4 by notice dated 24.2.06 invited sealed tender in prescribed form for construction of Lainey Market (Ground Floor) under IDSMT, at Ward No. 5, Dhubri, Assam Group A and Group B, from Govt. registered contractors of Class-I (A, B, C) category. The bidders were asked not to tender on percentage based rate. They were further asked to submit current Sales Tax, Income Tax certificates, details of past experience of works of similar nature for last three years, tools and machinery etc. The total value of the Group B work was Rs. 22,06,856/-. The writ Petitioner being an eligible Govt. registered Class-I (B) Contractor belonging to the O.B.C. category submitted a tender as per terms of the notice aforesaid. On 24.05.06 tenders were opened and out of three bidders including the Petitioner and the private Respondent No. 5, the amount quoted by the Petitioner was found to be Rs. 21,52,717/- while the rate quoted by Respondent No. 5 stood at Rs. 22,06,833/-

The Petitioner also annexed two works experience certificates dated 01.10.2003 and 15.03.2005 issued by the Executive Engineer. R.W.D. Roads, Dhubri, Road Division.

3. Though the Petitioner, being the lowest eligible bidder was confident to get the offer, to his utter surprise, he was served with a caveat dated 26.6.06, issued by the Respondent No. 5. In the said caveat it was mentioned that the Respondent No. 4 had accepted the bid of the Respondent No. 5 for construction of the Group B works of the Lainey Market at Rs. 22,06,833/-. Subsequently, the Petitioner came to know that the Respondent No. 4 had accepted the offer of the Respondent No. 5 depriving the Petitioner. According to the Petitioner the Respondent No. 5 was an inexperience person and that the work aforesaid was allotted to a person without experience causing serious injuries to the Petitioner. It was further alleged that the tender of the Respondent No. 5 was accepted only on the ground that he was the son of the Chairman of Dhubri-Gauripur Development Authority. The Petitioner being, deprived in the alleged way causing loss to the State Exchequer, has come up with this writ petition, invoking the writ jurisdiction under Article 226 of the Constitution of India, seeking a direction/order for setting aside the order dated 27.06.07 communicated by the Respondent No. 4, thereby by accepting the offer of the Respondent No. 5 for construction of the work Lainey Market and for further direction to reconsider the offer made by the bidders afresh.

4. Notice being issued, the Respondent No. 4 refuted the Petitioner's claim. By filing an affidavit-in-opposition, he stated that the Tender Committee upon scrutiny and consideration of all the relevant documents, along with technical report, found the Respondent No. 5 suitable for the work and accordingly awarded the contract to the Respondent No. 5. A copy of the Minute of the Meeting of the Tender Committee, held on 17.06.06 has also been annexed as Annexure-A to the affidavit-in-opposition. The Deponent further stated that the Petitioner, while submitting tender application, did not fill up all the columns of the tender papers and that he failed to submit the necessary papers/certificates regarding experience in respect of construction of buildings. The Deponent further denied the Petitioner's contention that he had submitted certificates dated 1.10.03 and 15.3.03 as mentioned in the writ petition. It was further contended that the Petitioner did not comply with all the essential terms and conditions of the ten