2018 Supreme(Gau) 211
IN THE GAUHATI HIGH COURT (HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH)
A.K.GOSWAMI, J.
UNION OF INDIA – Appellant
VERSUS
DAMODAR ROPEWAY AND INFRA LIMITED – Respondent
RFA 12 of 2017
Decided on : 06-03-2018
Subject
Civil Law - Necessary Party
Act Referred
RAILWAYS ACT : S.3(6), S.4(1), S.4(2)
Headnote
Civil Procedure Code - Rule 1 and 2 - Order 41 – Admission – Institution - Plaintiff opted for closure of agreement by letter recording there in that such closure of contract could not be without any financial liability/claim and relying upon Clause 61 of General Conditions of Contract demanded price for value of approved materials at site – Held, Decision cited by in case of is not applicable to facts and circumstances of this case - In said case a local authority for whose benefit land was sought to be acquired was held to be proper party in a land acquisition proceeding - In suit Union of India was made a defendant through General Manager NF Railway - In light of the pronouncement of Supreme Court – Appeal dismissed
Advocate Appeared:
For the Petitioner: MRS.U. CHAKRABORTY
For the Respondent: MR. S. BANERJEE
Heard Ms U. Chakraborty, learned Special Senior counsel, NF Railway, appearing for the appellants. Also heard Mr. S. Banerjee, learned counsel for the respondent.
2. On 5.2.2018, the learned counsel for the parties had submitted that having regard to the issues involved in the appeal, instead of formally admitting the appeal, the appeal can be disposed of at the admission stage itself and it was also contended that the records need not be called for.
3. It is in the light of the above order, the appeal was heard at the admission stage and is being disposed of by this order today.
4. In IA(C) No. 1433/2017, this Court had passed the following order on 5.3.2018:-
“Heard Ms U. Chakraborty, learned Special Senior counsel, NF Railways appearing for the applicants. Also heard Mr. S. Banerjee, learned counsel, appearing for the respondent. This is an application under Section 151 CPC praying for grant of leave to prefer appeal under Section 96 read with Order 41 Rule 1 and 2 CPC against the ex parte judgment and order dated 12.8.2016 passed by the learned Civil Judge No. 2, Kamrup(M) in MS No. 372/2015. The applicant is the Union of India, represented by the General Manager (Construction), NF Railways and in the appeal filed it is already arrayed as appellant No. 1.
The appellant No. 2 in the appeal is the Union of India represented by the General Manager, NF Railways, Maligaon.
The applicant had filed a civil revision petition numbered as CRP No. 379/2015 against the order dated 17.5.2016 passed by the Civil Judge, No. 2, Kamrup (M) whereby the petition filed under the provision of Order 1 Rule 10(1) CPC for adding it as a party in MS No. 372/2015 was rejected.
The above civil revision petition was dismissed as infructuous by order dated 11.11.2016 but at the same time liberty was granted to the applicant to challenge the judgment and decree passed in MS No. 372/2015.
In view of the above order dated 11.11.2016 passed in CRP No. 379/2016, leave is granted to the applicant to prefer appeal.
The application is allowed and disposed of.”
5. Though in the appeal a number of grounds are taken to assail the ex parte judgment and decree dated 12.8.2016 passed by the learned Civil Judge No. 2, Kamrup(M) in MS No. 372/2015, Ms Chakraborty has submitted that she will be addressing the Court only on the ground that the ex parte decree dated 12.8.2016 is liable to be interfered with as the General Manager (Construction), who is a necessary party, was not arrayed as a defendant in the suit and that the application filed on 8.3.2016 for impleading the General Manager (Construction), NF Railway was also erroneously rejected by the order dated 17.5.2016.
6. With the above preface, it will be appropriate to briefly take note of the case of the respondent in the trial court.
7. The respondent, who is the plaintiff, is engaged in the business of construction of ropeway, bridges and other civil and mechanical construction works and deals with government as well as non-governmental private organizations on contractual basis. A letter of intent was issued in favour of the plaintiff on 29.11.2011 for construction of three bridges on three rivers: Sankosh, Tipkai and Gadadhar in Assam. A formal agreement was entered into on 29.8.2012. A letter dated 13.6.2013 was issued directing the plaintiff to stop the execution of the works due to shortage of funds till further orders/instruction. The plaintiff was informed that it would be at liberty to opt for closure of the said contract, if it so desired without any financial liabilities or claim on either side. The plaintiff opted for closure of the agreement by letter dated 1.7.2013, recording there in that such closure of the contract could not be without any financial liability/claim and relying upon Clause 61 of the General Conditions of Contract, demanded the price for value of approved materials at site, the price of construction work done by the plaintiff till the date of such closure and other misce