IN THE HIGH COURT OF GAUHATI, ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH
SANDEEP MEHTA, ARUN DEV CHOUDHURY, JJ.
The General Manager (Cons), N.F. Railway, Maligaon, Guwahati & Ors. - Petitioners
Versus
M/s. AR-Allied Subhadra (JV) & Ors. - Respondents
WA No. 239 of 2021
Decided On : 04-07-2023
Contract - Tender Process - NIT - Regulations for Guidance of Tenderers - [Indian Contract Act, 1872, Section 7, 19, 36] - The court discussed the concept of concluded contract, the obligation to execute formal contract documents, and the forfeiture of earnest money. The judgment emphasized the importance of inspecting the site conditions before quoting rates and upheld the tendering authority's decision to cancel the bid and forfeit the EMD.
Fact of the Case:
The appellants cancelled a contract with the respondents and forfeited their Earnest Money Deposit (EMD) after the respondents' bid was accepted but they failed to execute the formal contract agreement. The respondents challenged this action in a writ petition, which was accepted by the learned Single Judge. The appellants appealed this decision.
Finding of the Court:
The court found that the contract stood concluded when the bid was accepted, and the subsequent signing of documents was only for formal documentation. The court upheld the tendering authority's decision to cancel the bid and forfeit the EMD, emphasizing the importance of inspecting the site conditions before quoting rates.
Issues: The issues revolved around the conclusion of the contract, the obligation to execute formal contract documents, and the forfeiture of the EMD.
Ratio Decidendi: The court held that the contract stood concluded upon acceptance of the bid, and the subsequent signing of documents was only for formal documentation. The court emphasized the importance of inspecting the site conditions before quoting rates and upheld the tendering authority's decision to cancel the bid and forfeit the EMD.
Final Decision: The appeal was allowed, and the impugned judgment and order were reversed. No order as to cost.
JUDGMENT :
S. Mehta, J.
The instant intra-Court writ appeal takes exception to the judgment and final order dated 25.03.2021 passed by the learned Single Judge whereby the writ petition, being, WP(C) 155/2020 preferred by the respondents herein was accepted and the order dated 02.05.2019 issued by the appellants, cancelling the contract entered into with the respondents (writ petitioners) and forfeiting their Earnest Money Deposit (EMD) to the tune of Rs.51,51,870/-, was interfered with and reversed.
2. The brief facts relevant and essential for disposal of the appeal are noted hereinbelow.
A Tender Notice dated 17.09.2018 was floated by the appellant Northeast Frontier Railway (hereinafter referred to as the Tendering Authority) for carrying out the task of earthwork in forming embankment including Pawakhali station yard, construction of minor bridges including RUB/LHS [Total 44 Nos.], including other miscellaneous ancillary works from Chainage 83.50 Km. to 106.837 Km. between station Pawakhali to Thakurganj in connection with construction of New BG line from Arariya to Galgalia of NF Railway (Construction). The approximate value of work was Rs.1000373270.52 and the earnest money deposit was quantified at Rs.51,51,870/-. The respondents/writ petitioners claim that pursuant to the publication of the tender notice, they formed a joint venture and participated in the tender process by depositing the earnest money as quantified (supra). While the bidders (respondents herein) were waiting for acceptance of their bids and completion of the formalities to conclude the contract in question, to the utter shock and surprise of the joint venture bidders, i.e. the respondents/writ petitioners, a communication dated 02.05.2019 was issued by the tendering authority conveying that not only the contract in question purportedly entered into with the writ petitioners had been cancelled but in addition thereto the EMD had also been forfeited. The said communication/order was challenged by the joint venture bidders/respondents by filing the captioned writ petition, which has been accepted by the learned Single Judge vide order dated 25.03.2021, which is assailed in this writ appeal.
3. We have heard learned counsel appearing for the parties and perused the material available on record.
4. On a perusal of the impugned judgment, it transpires that the reasons which persuaded the learned Single Judge to interfere with the impugned action were that:-
(ii) the endorsement of the postal department that the premises were found closed could not be equated to a refusal which would have a different connotation.
(iii) non-delivery of the communication dated 18.01.2019 on account of the remark of “closed” could not lead to presumption of service and delivery of the letter dated 18.01.2019.
(iv) As per the stipulation in the letter of acceptance dated 18.01.2019, the bidders were required to return the duly signed duplicate copy in all pages so as to constitute a binding contract. Since hardcopy of the letter of acceptance along with the annexures was never served upon the bidders, the parties could not be said to have arrived at a concluded contract. Since there was no contract between the parties, the question of termination could not arise and the EMD could not be forfeited.
5. Having held so, the learned Single Judge proceeded to interfere with and reverse the order dated 02.05.2019 whereby termination of the contract and forfeiture of EMD were directed.
6. Mr. G. Goswami, learned counsel representing the appellants urged that the NIT by itself indicated that the process was being invited as an e-Tender. The joint venture bid of the respondents herein was accepted by the Tendering Authority, i.e. the appellants herein and the letter of acceptance was iss
National Highways Authority of India Vs. Ganga Enterprises & Anr.
Kailash Nath Associates Vs. Delhi Development Authority & Anr.
Central Coal Fields Limited & Anr. Vs. SLL-SML (Joint Venture Consortium) & Ors.
The main legal point established in the judgment is that the contract stood concluded upon acceptance of the bid, and the subsequent signing of documents was only for formal documentation. The court ....
The NIT stipulated that tenderers who resile before the validity period shall be liable for forfeiture of EMD. The action of the respondents in seeking change of the rate offered bid amounted to resi....
Forfeiture of Earnest Money requires intent to mislead; accidental clerical errors should not disqualify bidders nor invoke punitive measures, affirming principles of natural justice.
A successful bidder cannot be penalized for inadvertent documentation errors, and forfeiture of earnest money requires proof of intent to mislead, reflecting principles of natural justice.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.