SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Gau) 820

IN THE GAUHATI HIGH COURT (HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH)
MARLI VANKUNG, J.
Mary V. Zoenpuii and Others - Appellants 
Versus
State of Mizoram  - Respondent 
WP(C)/165/2019
Decided on : 24-06-2025


Advocates:
Advocate Appeared:
For the Appellant : Mr Zoramchhana
For the Respondent: Addl. AG/GA, Mizoram

Interest on delayed compensation under the Land Acquisition Act is calculated based on the effective date of possession as per the signed agreement, not earlier notifications.

Headnote:(A) Land Acquisition Act, 1894 - Sections 4 and 34 - Writ petition concerning compensation for land acquisition for public works - Petitioners claimed interest on delayed compensation from the date of possession, asserting that the date mentioned in RTI was incorrect - Court found no clarity on possession date and treated the signing of the agreement on 31.05.2016 as the relevant date for payment, thus dismissing the claim for interest from an earlier date. (Paras 2, 5, 11)

(B) Interest calculation - The determination of the date of taking possession of land for interest calculation can only be based on the terms of the agreement signed by both parties, which explicitly stated the land was handed over on the date payment was made. (Paras 3, 10, 11)

Facts of the case:
The petitioners are owners of land subjected to acquisition for road construction under the Mizoram State Road-II Project. The state acquired the land following notifications in accordance with the Land Acquisition Act, yet disputes arose over the date of possession and subsequent interest on payments.

Findings of Court:
The court determined that the date of signing the agreement (31.05.2016) was the correct date of possession, dismissing claims regarding earlier dates mentioned in the RTI reply as errors without malice.

Issues: Whether the petitioners were entitled to interest on compensation based on the date of possession claimed.

Ratio Decidendi: The court ruled that without clarity on possession dates, the signed agreement dictated the terms of compensation and interest calculation, affirming that the date of possession is critical.

Result: Writ petition dismissed.

Table of Content
1. notification of land acquisition process. (Para 2 , 3)
2. contention regarding interest calculation. (Para 4 , 5)
3. defense on correct date of possession. (Para 6 , 7)
4. court's reasoning on notice validity. (Para 8 , 9 , 10)
5. decision on interest claim. (Para 11)
6. dismissal of writ petition. (Para 12)

JUDGMENT :

MARLI VANKUNG, J.

Heard Mr. Zoramchhana, learned counsel for the petitioners, also heard Mrs. Mary L. Khiangte, learned Govt. Advocate for the State respondents.

2. The case of the petitioners in the writ petition filed under Article 226 of the Constitution of India, is that they are the owners or the landed property at Tlabung-Kawrpuichhuah, and the respondents, for the purpose of improvement and upgradation of the Tlabung-Kawrpuichhuah Road 0.00 to 11.850 kms. to 2 Lane NH Standard under the Mizoram State Road-II Project (MSRP-II), to be funded by the World Bank, issued notification dated 13.08.2013 u/s 4(i) of the LAND ACQUISITION ACT , 1894, which was issued by the Principal Secretary to the Government of Mizoram, Revenue Department.

3. Accordingly, declaration u/s 6 of the Act, 1894 was issued on 04.02.2014 and thereafter, the respondent No. 4 passed the Draft Award No. 3 of 2014- 2015. Since, no date was indicated in the draft award, the petitioners in an application under RTI Act, was informed that the Draft Award No. 3 of 2014- 2015 was passed on 08.05.2015. The approval of the award was conveyed on 08.05.2015 and payment of the compensation to the petitioners was made on 31.05.2016. Thereafter, the petitioners sought for information through RTI, regarding the date of taking possession of the land for construction of Tlabung- Kawrpuichhuah Road, under the Mizoram State Road Project-II wherein as per the RTI reply dated 05.10.2018, it was stated that the date was on 13.08.2013.

4. The learned counsel for the petitioners thus submitted that, since the petitioners received payment of the acquisition of the land on 31.05.2016, the interest of the delayed payment should be calculated from the date of taking possession of the land, i.e., 13.08.2013, in terms of Section 34 of the LAND ACQUISITION ACT , 1894. The learned counsel also submitted that after the issuance of notice u/s 4 of the LAND ACQUISITION ACT , the petitioners could no longer utilise their landed property.

The learned counsel for the petitioners further submits that the corrigendum made by the State respondents in the letter dated 11.12.2019, to the effect that the date of taking possession of the land was mistakenly replied in the information given under the RTI Act dated 13.08.2013, which is the date of issuance of notice u/s 4 of the LAND ACQUISITION ACT , 1894 and that the correct date of taking possession of the land of the petitioners for construction of Tlabung- Kawrpuichhuah Road is the date in which an agreement was signed with the landowners, was made after the filing of the writ petition on 07.11.2019, and thus the corrigendum was made as an afterthought.

5. The learned counsel further submitted that, if there is no clarity on the date of possession of the landed property, the date of taking possession should be considered as the date on the date the Draft Award No. 3 of 2014-2015 was made, and approved on 08.05.2015. In support of this submission, the learned counsel has cited the Judgment of the Apex Court in the case of Lila Ghosh Vs. State of West Bengal reported in (2004) 9 SCC 337 (Para 19) and State of Madras Vs. K.N. Shanmugha Mudaliar and others reported in (1976) 2 SCC 406 (Para 4).

The learned counsel thus submitted that in the event of no clarity on the date of possession, the interest u/s 34 of the LAND ACQUISITION ACT , 1894 can be calculated from 08.05.2015 till the date of payment on 31.05.2016.

6. Mrs. Mary L. Khiangte, learned Govt. Advocate, on the other hand, submitted that the information furnished to the petitioners by the SPIO, PIU, PWD vide letter No. MSRP-17/PIU/RTI/2017/36 dated 05.10.2018, s

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top