2026 Supreme(Gau) 1979

THE GAUHATI HIGH COURT (HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH)
Manish Choudhury, J.
Shri Babul Ali, S/o- Late Kashim Ali – Petitioner 
Versus
Guwahati Municipal Corporation And Ors. – Respondents 
Wp(C)/3220 of 2026
Decided On : 06-10-2026

Important Points

Unauthorized constructions cannot be legitimized by the passage of time, payment of taxes, or authority inaction; they must be demolished to uphold the rule of law and prevent a culture of impunity.

Subject

Municipal Law - Unauthorized Construction

Act Referred

GUWAHATI MUNICIPAL CORPORATION ACT: S.337(3), S.438
Assam Unified Building Construction Regulation Bye-laws: S.5
Assam Building Construction Regulation Act: S.4
Guwahati Municipal Corporation Act, 1971: S.337[3], S.438
Assam Unified Building Construction Regulation Bye-laws, 2022: Reg.5
Assam Building Construction [Regulation] Act, 2022: S.4

Headnote

(A) Municipal Act - Section 337(3) and Section 438 - Unauthorized construction - Demolition order - Passage of time or payment of taxes does not legitimize illegal construction - Construction made in contravention of Acts/Rules must be demolished and cannot be protected by citing inaction of authorities or expenditure of money. (Para 10)

(B) Judicial Regularization - Courts must adopt a strict approach toward illegal constructions and should not readily engage in judicial regularization of buildings erected without requisite permissions to uphold the rule of law and prevent a culture of impunity. (Para 11)

Facts of the case:
A complaint was filed alleging unauthorized permanent construction without a No Objection Certificate or valid building permit on a plot of land. The municipal authority issued a notice and subsequently passed an order for the removal of the unauthorized structures. The petitioner claimed the structures were old, had been in possession since the time of the father, and that property taxes were being paid regularly. During the pendency of the writ petition, the petitioner obtained a planning permit for a new residential building and submitted an affidavit promising to demolish the existing temporary structures.

Findings of Court:
The constructions were admitted to be without the necessary No Objection Certificate and were therefore unauthorized. The subsequent procurement of a planning permit for a new building does not legitimize the existing unauthorized structures.

Issues: Whether unauthorized constructions can be protected from demolition on the grounds of long-term possession, payment of property taxes, or the subsequent grant of a building permit for a new structure.

Ratio Decidendi: Illegality in unauthorized construction cannot be perpetuated by the passage of time or inaction of authorities. Courts must maintain a firm stance against illegal constructions to ensure the rule of law and avoid creating a culture of impunity.

Result: Writ petition disposed of; demolition of unauthorized constructions upheld, granting the petitioner three months to carry out the demolition, failing which the municipal authority shall proceed to demolish the same at the petitioner's cost.

Legal Category Hierarchy

  • administrative law
    • municipal law
      • building regulations
        • unauthorized construction (Para 2, 4, 9, 10, 11, 12)
        • demolition (Para 4, 12, 13)
        • building permits (Para 2, 3, 5, 8)

Advocates Appeared:
For the Petitioner: Mr S R A Naser, Mr. P D Nair,Mr. F Ahmed,Mr G Alam
For the Respondent: Sc, Gmc, For Caveator,Ms. M Baruah,Mr A Kakoti

Table of Contents

1. Complaint regarding unauthorized construction without NOC or building permit — Order for demolition under Section 337(3) of the Guwahati Municipal Corporation Act, 1971. (Para 2 , 3 , 4 , 5 )

2. Petitioner claims long-term possession and tax payments; GMC asserts due process was followed and constructions lack requisite permits. (Para 6 , 7 , 8 )

3. Unauthorized constructions cannot be legitimized by the passage of time, inaction of authorities, or subsequent applications for new building permits. (Para 9 , 10 , 11 )

4. Illegal constructions in contravention of Acts or Rules must be demolished and cannot be judicially regularized or protected by the passage of time. (Para 10 , 11 )

5. Writ petition dismissed — Demolition of unauthorized constructions upheld — Three-month grace period granted for self-demolition. (Para 12 , 13 , 14 )

6. Can unauthorized construction be legitimized by the passage of time or payment of property taxes?

No. Illegality in unauthorized construction cannot be perpetuated or legitimized solely by the passage of time, inaction of authorities, or the amount of money spent on the construction. (Para 10 )

7. Should courts regularize buildings erected without requisite permissions from competent authorities?

No. Courts must adopt a strict approach and should not readily engage in judicial regularization of buildings erected without requisite permissions to uphold the rule of law and maintain a deterrent effect. (Para 11 )

8. Does obtaining a new building permit for a future structure excuse existing unauthorized constructions on the same plot?

No. Existing constructions without a No Objection Certificate are held to be unauthorized and subject to demolition, regardless of subsequent applications or permits for new constructions. (Para 9 , 12 )

JUDGMENT :

Manish Choudhury, J.

Heard Mr. G. Alam, learned counsel for the petitioner and Mr. S. Bora, learned Standing Counsel, GMC & GMDA for the respondent nos. 1, 2, 3, 4 & 6.

2. From the statements and averments made in the writ petition and the documents annexed thereto, it transpires that the respondent no. 5, as a power of attorney holder of one Begum Raunak Akhtar Huda, filed a complaint before the Guwahati Municipal Corporation [GMC] alleging illegal and unauthorized permanent construction without a No Objection Certificate [NOC] or valid building permit on a plot of land measuring 1 Katha 5 Lessas, covered by Dag no. 384 of Patta no. 34, at Revenue Village – Sahar Ulubari Part-I, Mouza –Ulubari, District – Kamrup [M] [‘the subject-plot’, for short].

3. On receipt of the complaint, a notice was issued on 17.12.2025 to the present petitioner and four other noticees asking from them documents including NOC, approved plan, up-to-date property tax receipt, etc. within three days time as regards such constructions. In response, the petitioner submitted a Reply before the respondent no. 3 on 19.12.2025 stating inter alia that he was in possession of an old tinned-roof Assam Type House over an area of land measuring 9 Lessas within the subject-plot since the time of his father and he had been paying regularly property taxes to the GMC and land revenue, and had not undertaken construction of any RCC Building.

4. After receipt of the Reply and site inspection, an Order under Section 337[3] of the Guwahati Municipal Corporation [GMC] Act, 1971 came to be passed by the respondent no. 2 on 18.03.2026 ordering for removal or pulling down the set-back deviation noted therein with a further observation that the constructions of RCC and Assam Type House were unauthorized. The Order dated 18.03.2026 was issued in respect of five persons including the petitioner.

5. Aggrieved by the Order dated 18.03.2026, the petitioner filed an appeal before the respondent no. 4. By an Order dated 15.06.2026, the appeal of the petitioner was disposed of granting liberty to the competent authority in the GMC to bring the proceeding initiated by the Order dated 18.03.2026 issued under Section 337[3] of the GMC Act to its logical conclusion by following due process of law. The appellate authority has observed that the petitioner had not produced any valid NOC, technical blueprint, or approved permit from the GMC for construction of permanent structure over the subject-plot.

6. It is the case of the petitioner that the tinned-roof Assam Type House with two rooms was constructed over an area of land measuring 320 sq. ft. and there is also another separate one ekchali tinned-roof Assam Type House measuring 190 sq. ft. within 9 Lessas. The construction of the said houses started in the year 1980 and since then, the family of the petitioner is in occupation of the said houses. In the year 1996, the houses were assessed by the GMC for property tax and after assessment, the family of the petitioner had been paying property taxes regularly till date.

7. Mr. Bora, learned Standing Counsel, GMC & GMDA has submitted that in the entire process leading to the Order dated 18.03.2026, the petitioner was provided an adequate opportunity of being heard and it was after spot verification and hearing the petitioner only, the Order dated 18.03.2026 was passed and thereafter, the Order dated 15.06.2026 was passed.

8. Mr. Alam, learned counsel for the petitioner has submitted that during the pendency of the writ petition, the petitioner has applied for building permission for construction of an RCC [G+2] Building under the Mukhya Mantrir Sohoj Griha Nirman Achoni before the GMDA on 30.07.2026. Along with the application, the petitioner and his brother submitted an affidavit to the effect that in the event building permission is granted for construction in the concerned part within the subject-plot, covered by Dag no. 385 [new] and Patta no. 187 [new] at Village – Sahar Ulubari-I, Mo