1999 Supreme(Ker) 626
High Court of Kerala
S. Sankarasubban, J.
V P Kunhammed - Appellant
Versus
State of Kerala & Ors - Respondent
O.P. No. 6435 of 1996
Decided On : 07-09-1999
The State cannot unilaterally assess damages and recover the amount without an independent authority finding that the loss was occasioned to the Department.
Headnote:
Revenue Recovery Act - Breach of Contract - The court held that the State cannot unilaterally assess damages and recover the amount without an independent authority finding that the loss was occasioned to the Department. The court also emphasized that unless the claim is established through a court of law, no amount can be recovered. The court quashed the notice issued under the Revenue Recovery Act and directed the respondents to return the amount received as per the order.
Fact of the Case:
The petitioner challenged a notice issued under the Revenue Recovery Act and sought a declaration that no amount is due by him as compensation. The petitioner was awarded a contract for providing a water supply scheme but had to leave India before completing the work. The Department demanded compensation for the loss sustained due to the incomplete work.
Finding of the Court:
The court held that the State cannot recover the amount mentioned in the notice against the petitioner and directed the respondents to return the amount received as per the order.
Issues: Dispute over liability to pay compensation, unilateral assessment of damages by the State, belated notice under the Revenue Recovery Act.
Ratio Decidendi: The State cannot unilaterally assess damages and recover the amount without an independent authority finding that the loss was occasioned to the Department. Unless the claim is established through a court of law, no amount can be recovered.
Final Decision: The Original Petition is allowed, and the court quashed the notice issued under the Revenue Recovery Act and directed the respondents to return the amount received as per the order.
S. Sankarasubban, J.
1. In this Original Petition, Petitioner challenges Ext.P5 notice issued under the Revenue Recovery Act and also prays for a declaration that no amount is due by him by way of compensation.
2. The petitioner was awarded with a contract for providing water supply scheme to tribunal colonies at Puzhappathoor and Illiyambam in Wynad District as per work orders dated 18.8.1991 and 22.2.1981 by the third respondent, viz., the Executive Engineer, Kerala Water Authority, Sulthan Batherry, Wynad District. On completion of 90% of the said work, the petitioner had to leave India on getting an employment in Soudi Arabia in the year 1983. The work was thereupon entrusted with one Moosa as his agent with the concurrence of the third respondent. According to the petitioner, he returned to India in 1991 when he received Ext. P1 notice, it is stated that the aforesaid Moosa had not completed the work and the work was executed through some other contractor and the petitioner was liable to compensate the loss occurred to the Department. The third respondent demanded a sum of Rs.64,667/- by way of damages. The petitioner sent Ext.P2 reply. The petitioner disputed his liability to pay any amount by way of compensation. The third respondent again issued Ext.P3 demanding the amount and the petitioner sent Ext.P4 reply. Thereafter, the petitioner received Ext. P5 revenue recovery notice. It is challenging the above notice that this Original Petition is filed.
3. According to the petitioner, no amount can be recovered from him by way of damages, unless an independent authority founds that loss was occasioned to the Department. Counsel for the petitioner relied on the decision of the Supreme Court in State of Karnataka v. Rameshwara Rice Mills - A.I.R. 1987 S.C. 1359 - and contended that the third respondent cannot unilaterly assess the damages. He also raised the contention that Ext.P5 notice itself was belated.
4. Counter affidavits have been filed on behalf of respondents 1 and 3. It is stated in the counter affidavits that the Executive Engineer gave extension of time upto 15.2.1984 at the request of Moosa. He has also been informed that no further extension would be given. However, he had not come forward to start or to complete the work. It is further stated that as per the agreement, the Department is entitled to recover the loss sustained by it from the contractor.
5. I heard counsel for the petitioner, counsel for the Water Authority and the Government Pleader. It seems that the agreement between the petitioner and the third respondent was executed on 11.3.1981. The show cause notice was issued regarding the termination of the contract on 1.7.1985 and the contract was terminated on 12.9.1985. In Ext. P3, it is stated that the authority has suffered a loss of Rs. 29,964/-. It is further stated that a total amount of Rs. 70,819/-which includes an amount of Rs.31,427/- towards the value of certain movables has to be remitted by the petitioner. Under Ext.P5, the amount claimed is Rs. 1,35,485/-.
6. From the above, it is clear that the petitioner has denied that the breach of contract was committed by him or Moosa. He is also disputed the value of the materials and also contended that no claim is sustainable against him for the value of materials. It is now clear from the decision of the Supreme Court in State of Karnataka v. Rameshwara Rice Hills - A.I.R. 1987 S.C. 1359 - that the powers of the State Government under an agreement entered into by it with a private person providing for assessment of damage for breach of conditions of the agreement and recovery of the damages is confined only to those cases where the breach of conditions is admitted or it is not disputed. Here, the breach is not admitted. Unless the claim is established through a court of law, no amount can be recovered. In this case, admittedly, there has been no finding by any court that the petitioner committed breach of contract. The contention regarding l