2017 Supreme(Ker) 1513
IN THE HIGH COURT OF KERALA
Shaji P. Chaly, J.
Sakthidharan – Petitioner
Versus
Special Tahsildar (LA) – Respondent
W.P.(C) No.33708 of 2016
Decided On : 12-07-2017
Subject
Land Acquisition - Negotiated Purchase
Act Referred
LAND ACQUISITION ACT : S.4(1)
Headnote
Constitution of India - Article 300A - Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act 2013 - Land Acquisition Act 1894 - Section 4( 1) - Acquisition of Land by Government - Compensation - Negotiation of purchase - Power of State Government - Conflict of legislation - Maxim "generalia specialibus non derogant" Held, general provisions contained under the Transfer of Property Act, 1882 is controlled by the special provisions of Act, 2013. If at all there is any conflict by and between the aforesaid legislations, the provisions of latter legislation will prevail - Absence of such a provision under the new Act and absence of power for the appropriate Government to make rules in that regard makes it clear that, there is no enabling power for the State Government to resort to eminent domain and go ahead with negotiated purchase disadvantageous to the land owner
For the Petitioner: K. Balachandran (Mangalath), Rajesh Nair, T.R.S. Kumar, Sobin Soman & U.B. Siras
For the Respondent:K. Jaju Babu (Sr. Advocate), Y. Jafar Khan (Sr. Government Pleader) & M.U. Vijayalakshmi
The captioned Writ Petitions arose in the premise of Section 4(1) notification issued under the Land Acquisition Act, 1894, vis-a-vis introduction of Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, (hereinafter called “Act, 2013”), and consequential agreements entered into by and between the petitioner land owners and respondent State Government in some cases, and securing consent letters from the petitioners in some cases, paying part consideration, and refuse to pay compensation under the Act, 2013, in view of the agreements executed to sell off the lands in accordance with the negotiated purchase value. The fact circumstances and the documents put forth in W.P.(C) 33708/2016 and the counter affidavit filed by the State Government in the said Writ Petition are referred to, in order to dispose of the Writ Petitions.
2. An extent of 0.09 Ares situate in Sy.No.575/7. Pt of Ernakulam Village and the building owned by the petitioner is under acquisition for the Kochi Metro Rail Project. Act 30 of 2013 has come into force w.e.f. 1.1.2014. However, unreasonable delay was caused by the State Government in framing rules under the said Act. As no rules were framed, the Land Acquisition Authorities did not proceed under the provisions of the new Act and instead, forced the petitioners and others to deliver the property in advance. Taking into account the larger public interest, petitioner decided to co-operate with the acquisition subject to the right to get due compensation and other benefits under the law governing land acquisition. Basically petitioner is claiming the benefits under the Act, 2013, which has come into force w.e.f. 1.1.2014, evident from Ext.P1 notification. According to the petitioner, as projected in the very preamble itself, the Act is introduced to ensure a humane, participative, informed and transparent process for land acquisition with the least disturbance to the owners of the land and other affected families and provide just and fair compensation and make adequate provisions for such affected persons for their rehabilitation and resettlement, and for ensuring that the cumulative outcome of compulsory acquisition should be, affected persons become partners in development leading to an improvement in their post acquisition social and economic status and for matters connected therewith and incidental thereto. It is submitted S.11 of Act, 2013 mandates publication of a preliminary notification to the effect that land in the area is required or likely to be required in connection with any public purpose, along with details of the land to be acquired in the official gazette, in two daily newspapers circulating in the locality of which one shall be in the regional language and in the local language in the Panchayat, Municipality or Municipal Corporation as the case may be, in the offices of the District Collector, the Sub Divisional Magistrate and the Tahsil and uploaded in the website of the appropriate Government, in the affected area etc.etc. The first proviso to S.12 provides that even the survey of the land cannot be conducted in the absence of any person authorized in writing by the owner. S.15 deals with ‘Hearing of objections’ and Ss.16 to 18 deal with rehabilitation scheme. S.19 makes strict provisions for publication of declaration and summary of rehabilitation and resettlement. S.21 of the Act provides for ‘notice to persons interested’ and the enquiry and land acquisition award by the Collector is contemplated under S.23 of the Act. Therefore, the Act deals with determination of compensation, award of solatium, rehabilitation and resettlement award etc. etc.
3. Therefore, according to the petitioner, even though the petitioner is not against the acquisition of the property, if it is inevitable for a public purpose, that does not mean that, petitioner can be deprived of his property in gross disregard of the law of land. Therefore, petitio