SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2021 Supreme(Ker) 538

IN THE HIGH COURT OF KERALA AT ERNAKULAM
MARY JOSEPH, J.
SIDHIQUE, S/O PANIKKAVEETIL SYED MUHAMMED, THOOVANNOOR DESOM, CHUNDAL VILLAGE – Appellant
Vs.
CLEAMISS, S/O MANDUMBAL MATHEW, ALOOR VILLAGE DESOM, THALAPPILLY TALUK.
R.F.A. No. 556 of 2005
Decided On : 03-06-2021

Advocates Appeared:
For The Appellant : SRI.SREEKUMAR G.(CHELUR)
For The Respondent: SRI.AVM.SALAHUDDEEN

Point of Law: Suit for recovery of amount - Suit to include whole claim - Since defendant in case on hand failed to raise plea of bar of suit under Order II Rule 2 C.P.C before the trial court, it is a matter of leave being obtained from Appellate Court under Order XLI Rule 2 CPC to raise it at this juncture.

Headnote:

Civil Procedure Code, 1908 - Order II Rule 2 - Evidence Act - Section 45 - Seeking realisation of money - Agreement - Construction work - Opinions of experts - He had raised a case that he was a Building Contractor, that he was engaged by the defendant to construct a house and allied structures as per the building plan and agreement executed by them on 07.06.1995 incorporating the terms settled among them after negotiations about the manner of constructions and it’s costs, that Rs.5,000/- was given as advance towards the costs, that the construction work was to commence from the already constructed basement, that Rs.75,000/- each was agreed to be paid towards costs of construction works of the foundation as well as the terrace of the Kayyalapura, that the time fixed for completion of the work was till 30.01.1996

2. Finding of the court: In appeal filed against, appellate court found that procedure adopted is wrong and thus remanded case to the trial court after setting aside the impugned judgment with permission to raise plea as an additional one and direction issued to court to adjudicate case afresh - Factual scenario in the case on hand is not akin to that in Sardar Satpal Singh supra - there cannot be any doubt on the power of the court to compare the signature of one person stands disputed by another. Evidence Act by the provision extracted supra permits the court to apply it’s own judgment and perception, by a mutual comparison and application of mind to arrive at an opinion on the affixture of the disowned signature with those admittedly affixed by the said party and made available to it - This Court is able to take a view based on discussions made above that the plaintiff's claim is defeated for failure to discharge his burden to establish execution of Ext.A1.

Result: Appeal allowed.

JUDGMENT :

The judgment and decree passed by I Additional Sub Court, Thrissur (for brevity, 'the court below') on 18.03.2005 in O.S No.128 of 1998 is assailed in the appeal on hand by the defendant in the said suit. For the sake of clarity, the parties to this appeal are referred to hereinafter as the defendant and the plaintiff in accordance with their status in the suit.

2. The suit above was filed by the plaintiff seeking realisation of money. He had raised a case that he was a Building Contractor, that he was engaged by the defendant to construct a house and allied structures as per the building plan and agreement executed by them on 07.06.1995 incorporating the terms settled among them after negotiations about the manner of constructions and it's costs, that Rs.5,000/- was given as advance towards the costs, that the construction work was to commence from the already constructed basement, that Rs.75,000/- each was agreed to be paid towards costs of construction works of the foundation as well as the terrace of the Kayyalapura, that the time fixed for completion of the work was till 30.01.1996, that the construction work commenced as per the agreed schedule could not be continued for failure of the defendant to supply the required materials as agreed, that the defendant being abroad at the relevant time, letter was sent to intimate him about the situation, that the work was assigned by the defendant to another party without settling the accounts with the plaintiff, and that as per the agreement executed, the defendant is liable to pay a sum of Rs.1,45,000/- (Rs.75,000x2)- 5000) for the work already completed by the plaintiff and a sum of Rs.1,05,000/- as compensation towards the loss sustained by him. Raising claims as above, the Original Suit was filed for realisation of Rs.2.5 lakhs with interest at the rate of 12% per annum.

3. The defendant in his written statement has taken a categoric stand of denial of execution of the agreement and entrustment of the construction work of the house and Kayyalapura. The signature in the agreement allegedly executed by the plaintiff with him was disowned by him. The construction work was admitted as done under the supervision of his father and younger brother. According to him it was orally agreed that the plaintiff would supply the workers for the construction and supervise the work, that wages would be paid to the workers by his father directly, that Rs.5,000/- was paid to the plaintiff for the work, that the materials for the construction work were supplied by the father of the defendant, that suit filed by the plaintiff as O.S No.1041/1995 was already dismissed by the Munsiff's Court, that in the absence of an agreement executed among them, question of breach of any terms will not arise and that the suit for realisation of money is only to be dismissed.

4. Based on the above rival contentions, specific issues had been framed by the trial court as follows:

    “1. Whether the plaintiff has executed the construction work as per agreement dated 07.06.1995?

2. Whether the defendant is liable to pay the cost of the work by plaintiff?

3. Whether the plaintiff is entitled to realise any compensation as claimed?

4. Reliefs and costs?”

5. To facilitate the process of adjudication of the issues, both parties adduced oral as well as documentary evidence. The plaintiff's evidence consists of the oral evidence tendered by himself and his witnesses as PWs 1 to 4 and documentary evidence of Ext.A1 to A7(c). The defendant's evidence is confined to the solitary oral evidence of his father and Power of Attorney holder as DW1 and documentary evidence of Ext.B1. Ext.X1 was also marked as court Exhibit.

6. The trial court found the issues except issue No.3 in favour of the plaintiff and accordingly decreed the suit as follows:

    “21. Issue No.4:- In the result the suit is partly decreed with cost and partly dismissed without cost. Plaintiff is entitled to realise Rs.1,45,000/- with 12% interest from the date of the

                          Click Here to Read the rest of this document
                          1
                          2
                          3
                          4
                          5
                          6
                          7
                          8
                          9
                          10
                          11
                          SupremeToday Portrait Ad
                          supreme today icon
                          logo-black

                          An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

                          Please visit our Training & Support
                          Center or Contact Us for assistance

                          qr

                          Scan Me!

                          India’s Legal research and Law Firm App, Download now!

                          For Daily Legal Updates, Join us on :

                          whatsapp-icon Back to top