SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2024 Supreme(Ker) 732

IN THE HIGH COURT OF KERALA AT ERNAKULAM
THE HONOURABLE MRS. JUSTICE SHOBA ANNAMMA EAPEN
Assistant Executive Engineer Electrical Sub Division, Kse Board LTD. – Appellant
Versus
Arun R. Chandran – Respondent
WP(C) No. 21392 of 2017
Decided on : 22-07-2024

Advocates:
Advocate Appeared:
For the Appellant : SRI.P.A.AHAMED, SC, KERALA STATE ELECTRI NIRMAL.S
For the Respondent: SMT.ACHU SUBHA ABRAHAM, SMT.V.T.LITHA, SRI.PHILIP T.VARGHESE, SRI.RENI JOHN, SRI.THOMAS T.VARGHESE

IMPORTANT POINT
A short assessment bill for electricity charges is barred by limitation if not issued within two years from the date the amount became due, and procedural requirements for issuing such bills must be strictly followed.

Headnote:

LIMITATION - ELECTRICITY BILL ASSESSMENT - Electricity Act, 2003 - Section 56(2), Kerala Electricity Supply Code, 2014 - Section 134(1) - The court interpreted Section 56(2) of the Electricity Act, 2003, which prohibits recovery of sums due from consumers after two years unless shown as arrears. The court found that the KSEB's short assessment bill was issued after the limitation period, as the amount became due when the unauthorized load was regularized in March 2011, and not when the bill was issued in August 2015. The court emphasized the necessity of compliance with procedural requirements under Section 126 of the Act for issuing such bills, which were not followed in this case.

Fact of the Case:

The KSEB issued a short assessment bill for unauthorized electricity load used by the first respondent from April 2010 to March 2011, which was challenged on the grounds of being barred by limitation under Section 56(2) of the Electricity Act, 2003. The bill was issued in August 2015, after a delay attributed to administrative reasons.

Finding of the Court:

The court found that the KSEB's issuance of the short assessment bill was out of time as it was not issued within the two-year limitation period stipulated by Section 56(2) of the Electricity Act. The court noted that the KSEB failed to comply with the necessary procedural requirements for issuing such a bill.

Issues: Whether the short assessment bill issued by KSEB was barred by limitation under Section 56(2) of the Electricity Act, 2003, and whether the KSEB complied with the procedural requirements for issuing the bill.

Ratio Decidendi: The court held that the amount due for unauthorized load became first due when the load was regularized in March 2011, and since the bill was issued in August 2015, it was beyond the two-year limitation period. The court also emphasized the importance of following procedural requirements under Section 126 of the Act for issuing assessment bills.

Final Decision: The writ petition filed by KSEB was dismissed, affirming that the short assessment bill was out of time and KSEB was not entitled to recover the amount.

JUDGMENT :

THE HONOURABLE MRS. JUSTICE SHOBA ANNAMMA EAPEN

The short question to be decided in this writ petition is whether the impugned Ext.P5 order is correct in holding that Ext.P1 short assessment bill raised by the Kerala State Electricity Board (KSEB) for the period from April, 2010, to March, 2011 is barred by limitation under Section 56(2) of the Electricity Act, 2003 (for short, “the Act”).

2. The writ petition is filed by the KSEB challenging Ext.P5 order passed by the second respondent -the Consumer Grievance Redressal Forum. The case projected in the writ petition is that the premises of the first respondent, Sri.Arun R. Chandran (consumer), was inspected by the Anti Power Theft Squad (APTS) of the KSEB during March, 2010, and found that the first respondent consumer was using unauthorized additional load of 4 kw in addition to the registered connected load of 14 kw. The penal bill issued to the first respondent was paid without any objection. The unauthorized additional load was regularized by the first respondent only in March, 2011. Thereafter, Ext.P1 short assessment bill for penal charges for the subsequent months for the unauthorized additional load from April, 2010 to March, 2011, was issued to the first respondent on 17.08.2015 on the basis of an audit of the Electric Section, Kodakara, conducted on 03.09.2012. Though the first respondent filed an objection before the Assistant Engineer, it was rejected confirming Ext.P1. Challenging this, the first respondent filed a petition before the second respondent and as per Ext.P5 order, the second respondent cancelled Ext.P1 short assessment bill, holding that the said demand was raised after four years without showing the same as arrears recoverable in the subsequent bills. Aggrieved by Ext.P5, the KSEB has come up before this Court with the writ petition.

3. Heard the learned Standing Counsel for the petitioner/KSEB as well as the learned counsel for the first respondent.

4. According to the learned Standing Counsel appearing for the KSEB, the finding of the second respondent that the issuance of Ext.P1 short assessment bill for the period from April, 2010 to March, 2011 is not legally correct, is wrong and unsustainable. It is submitted that Ext.P1 bill for the unauthorized load was first time issued only on 17.08.2015 and therefore, the same is not hit by Section 56(2) of the Act. It is further pointed out that as per Section 134(1) of the Kerala Electricity Supply Code, 2014, if the licensee establishes either by review or otherwise, that it has undercharged the consumer, the licensee may recover the amount so undercharged from the consumer. Hence, according to the learned Standing Counsel, the KSEB is entitled to recover the said amount. To substantiate the arguments, the learned Standing Counsel relied on a decision of the Division Bench of this Court in Manager, Mar Athanasios College v. KSEB & others [2014:KER:27167]. It is submitted that the delay occurred in raising Ext.P1 short assessment bill is only due to administrative reasons, however, the first respondent is duty bound to pay the said charges since an unauthorized load was detected in the premises. Further, it was pointed out that the date on which the amount became first due is 17.08.2015, i.e., the date on which the bill was first time issued to the first respondent.

5. The learned counsel for the first respondent submitted that the APTS inspected the premises in March, 2010, and the said unauthorized additional load was regularized in March, 2011. It was further submitted that the penal charges demanded by the KSEB were paid by the first respondent without raising any objection and the first respondent was not aware of the fact that any further amount was due from him. According to the learned counsel, the demand is clearly out of time and the KSEB, while issuing Ext.P1 short assessment bill, did not comply with the procedures contemplated under Section 126 of the Act, which specify that before fin

    Click Here to Read the rest of this document
    1
    2
    3
    4
    5
    6
    7
    8
    9
    10
    11
    SupremeToday Portrait Ad
    supreme today icon
    logo-black

    An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

    Please visit our Training & Support
    Center or Contact Us for assistance

    qr

    Scan Me!

    India’s Legal research and Law Firm App, Download now!

    For Daily Legal Updates, Join us on :

    whatsapp-icon Back to top