2025 Supreme(Ker) 2328
IN THE HIGH COURT OF KERALA AT ERNAKULAM
Nitin Jamdar, C.J., Basant Balaji, J.
Domestic On-Grid Solar Power Prosumers Forum – Kerala, Represented By Its President - Petitioner
Versus
Kerala State Electricity Regulatory Commission And Ors. – Respondents
WP(PIL) No. 79 of 2025
Decided On : 28-07-2025
Advocate Appeared:
For the Petitioner: Sri. Yeshwanth Shenoy, Smt. Aysha Abraham
For the Respondent: Nandagopal S. Kurup, Standing Counsel, Senior Government Pleader Sri. V. Tekchand
Public hearings are essential for stakeholder engagement in regulatory processes, and discontinuing established practices without valid reasons is subject to judicial review for arbitrariness.
Headnote:(A) Electricity Act, 2003 - Section 82 - Public Interest Litigation regarding the mode of public hearing for draft regulations on renewable energy - The Petitioner sought a hybrid public hearing; the Respondent opted for online-only hearings citing previous disruptions at physical hearings - The court emphasized the importance of public hearings as part of participatory democracy and directed the Respondent to conduct physical hearings at multiple locations, reaffirming established practices. (Paras 18, 26)
(B) Judicial Review - The court noted that while stakeholders may not have a statutory right to demand a physical hearing, the discontinuation of established practices without valid justification could be challenged for being arbitrary and disproportionate. (Paras 20, 23)
Facts of the case:
The Petitioner, representing solar energy users, contested the Respondent's decision for an online-only public hearing on draft regulations, arguing it would limit stakeholder participation.
Findings of Court:
The Respondent was directed to conduct public hearings physically at four locations to ensure wider participation and uphold democratic processes.
Issues: The main issues included the necessity of physical hearings and the Respondent's justification for opting only for online hearings.
Ratio Decidendi: The court ruled that public hearings are crucial for stakeholder engagement and should not be limited to online formats.
Result: The Respondent was directed to conduct physical hearings at four locations.
| Table of Content |
|---|
| 1. the legal framework governing public hearings under the electricity act. (Para 1 , 2 , 4 , 5 , 8) |
| 2. the importance of public hearings for stakeholder participation. (Para 10 , 12 , 19) |
| 3. judicial review of the respondent's decision-making process. (Para 15 , 20 , 21 , 22) |
| 4. the directive to conduct physical public hearings. (Para 26 , 28) |
JUDGMENT :
Nitin Jamdar, C. J.
The subject matter of this Public Interest Litigation is the decision of the Kerala State Electricity Regulatory Commission to conduct only an online public hearing, and not a physical hearing, in connection with the draft regulations pertaining to renewable energy.
2. The Petitioner – Domestic On-Grid Solar Power Prosumers Forum is a registered association formed with the object of ensuring the welfare and protection of the rights of all solar energy users in Kerala, particularly domestic on-grid solar power prosumers. The Respondent – Kerala State Electricity Regulatory Commission, is a statutory body constituted under Section 82 of the Electricity Act, 2003 .
3. The State Police Chief and Director General of Police, Police Headquarters, Thiruvananthapuram; and the City Police Commissioner, Office of the City Police Commissioner, Thiruvananthapuram, are impleaded as additional respondents.
4. The Electricity Act, 2003 (Act of 2003), under which the Respondent – Commission is constituted, is enacted to consolidate the laws relating to generation, transmission, distribution, trading, and use of electricity, and generally for taking measures conducive to the development of the electricity industry, protecting the interest of consumers and the supply of electricity to all areas, promoting efficient and environmentally benign policies, and establishing Regulatory Commissions, such as the Respondent. Part II of the Act of 2003 deals with the National Electricity Policy and Plan. Parts III to VI address the modalities, including generation, licensing, transmission, and distribution of electricity. In Part VII of the Act of 2003, tariffs are regulated under Section 61 . Under Section 62 , the procedure for tariff order is specified, and Section 66 deals with the development of the market, where the Appropriate Commission is enjoined to promote the development of a market in the manner specified in the National Electricity Policy. Part VIII deals with the works of licensees. Part IX deals with the constitution and functions of the Central Electricity Authority. Part X deals with the constitution, powers, and functions of the Regulatory Commissions.
5. Under Section 82 of Part X of the Act of 2003, the State Government is empowered to constitute a State Commission, known as the “State Electricity Regulatory Commission”, to discharge various functions as outlined in the scheme of Section 86. As per clause (a) of Section 86(1), the State Commission shall determine the tariff for generation, supply, transmission, and wheeling of electricity, whether wholesale, bulk, or retail. The State Commission, under clause (b) of Section 86(1), is empowered to regulate the electricity purchase and procurement process of distribution licensees and electricity traders, and under clause (e) of Section 86(1), the State Commission promotes cogeneration and generation of electricity from renewable sources of energy by providing suitable measures for connectivity with the grid. Section 181 empowers the State Commissions to make regulations. Such regulations can be made in particular and without prejudice to the generality of the powers specified therein, including any other matter which is to be, or may be, specified under clause (zp). As per sub-section (3) of Section 181 , all regulations made by the State Commission under the Act of 2003 shall be subject to the condition of previous publication.
6. On the aspect of previous publication referred to under Section 181 (3), the Ministry of Power, Government of India, in exercise of the powers conferred under sub-section (1) and cla