SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Ker) 204

IN THE HIGH COURT OF KERALA AT ERNAKULAM
HARISANKAR V. MENON, J.
Ganga Constructions, Represented By Its Managing Partner Smt. Meena Mamu – Petitioner 
Versus 
Assistant Executive Engineer, Local Self Government Department – Respondent
WP(C) No. 4911 of 2023
Decided On : 12-02-2026

Advocates Appeared:
For the Petitioner: Shri. M.R. Dhanil, Smt. Senitta P. Jojo
For the Respondent: Smt. S. Ambily, Sri. K.K. Chandran Pillai (Sr.), Shri. V. Renju, SC, Irinjalakuda Municipality, Sri Sunil Nath, GP.

A contractor is entitled to GST payments on completed works, as tender rates must be exclusive of GST per government circulars.

Headnote:(A) Goods and Services Tax Act, 2017 - Section 15 - Right to Information Act, 2005 - Tendering Process - The contractor's tender was awarded without including the GST component as required by the circulars issued by the Local Self Government Department. The court affirmed that the contractor is entitled to GST payments as the tender specified rates exclusive of GST, and the law permits reimbursement of GST upon provision of the requisite categories and documentation. (Paras 8, 10)

(B) Government Circulars - The stipulations in various government circulars clarified that GST should not be included in the quoted tender amounts but should be separately computed when making periodic payments for completed works. (Paras 4, 6, 10)

Facts of the case:
The petitioner was awarded a contract by the Municipality for an amount exclusive of GST. Disputes arose regarding the recoupment of already paid GST following an audit report claiming improper payment. The petitioner sought clarification regarding the Municipality's obligation to pay GST on billed amounts.

Findings of Court:
The petitioner is entitled to be paid the GST component along with the value of completed works, and the communication attempting to recoup this GST payment was set aside.

Issues: The primary question was whether the Municipality was required to include GST in the payments made to the contractor based on the bills presented.

Ratio Decidendi: The court concluded that the GST must be treated separately from the base payment, using the circulars as the guiding principle for payment obligations while confirming the contractor's justification for including GST in billed amounts.

Result: Writ petition allowed, setting aside the recoupment order.

Table of Content
1. contractor awarded work; gst included in payments (Para 1)
2. dispute over gst payment requirement in tender (Para 2 , 3 , 8)
3. clarifications on payment processes regarding gst (Para 4 , 5 , 6 , 7 , 9 , 10)
4. petitioner entitled to gst payment as per law (Para 11)

JUDGMENT :

HARISANKAR V. MENON, J.

The petitioner is stated to be a contractor and pursuant to a notice inviting tender dated 23.02.2019, floated by the respondent – Municipality, placed the tender, and the petitioner was also awarded the work as evidenced by Ext.P1 work order dated 18.06.2019. An agreement was also entered into between the petitioner and the respondent – Municipality, as evidenced by Ext.P2, as per which the total estimate for the work is a sum of Rs.2,53,82,519.35. The petitioner contends that the amount quoted above and forming part of the agreement is exclusive of GST with reference to the provisions of the CGST/SGST Act, 2017. Therefore, with reference to various circulars issued by the Government, the petitioner state that while making periodical payments to the petitioner, GST was also paid to it. Later, pursuant to an audit report at Ext.P15, wherein it was recorded that the GST is included in the quote placed by the petitioner, the payment of GST effected to the petitioner till that date was found to be inappropriate. On that basis, steps for recouping GST already paid were also taken. The petitioner, in such circumstances, sought for certain clarifications under the provisions of the Right to Information Act, 2005 , in response to which, Ext.P17 communication dated 25.11.2022 has also been issued by the respondent – Municipality, seeking to clarify the position with reference to the liability of the Municipality to satisfy GST while making payments to the petitioner as above. It is in such circumstances that the petitioner is before this Court seeking to challenge the audit report at Ext.P15 as well as the communication at Ext.P13, issued by the Assistant Engineer attached to the Municipality, concluding that the payments towards GST already effected to the petitioner requires to be recouped.

2. I have heard Sri.M.R. Dhanil, the learned counsel for the petitioner, as well as Smt. V. Renju, the learned Standing Counsel for the respondent – Municipality.

3. The short issue arising for consideration in this writ petition is as to whether the respondent – Municipality, is required to satisfy the GST component while making periodical payments to the petitioner as against the bills raised by it. The petitioner seeks to rely on Ext.P4 circular dated 14.12.2017, issued by the Finance (Industries & Public Works) Department, which clarified that while obtaining administrative sanction, the total amount submitted for approval should separately indicate the estimated cost and the applicable GST. However, the aforementioned requirement is with reference to the mandate for the Municipality while obtaining the administrative sanction. Clause 2 of Ext.P4 states that in the tender documents, the rate quoted should be “exclusive of GST” but “inclusive of all other taxes”, etc. At the same time, it further states that the contractor is required to indicate separately the applicable GST in the tender document. According to Smt. V. Renju, the petitioner having not separately shown the GST in the tender document, the benefit cannot be extended to it. Even on the face of the afore, this Court notices that the tender documents, as noted earlier, should only show the rates quoted by the contractor without including the “GST”. Therefore, in my opinion, the tender placed by the petitioner has to be understood as one filed without disclosing the GST component.

4. In the light of the afore, clauses 3, 4, and 5 of the Ext.P4 circular requires to be noticed as under:-

“3) For the purpose of determining L1, the rates quoted by contractors exclusive of GST should be taken into consideration.

4) When the bills for any Goods, Services or Works procured by any Gove

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top