SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Ker) 632

IN THE HIGH COURT OF KERALA AT ERNAKULAM
RAJA VIJAYARAGHAVAN V., K.V. JAYAKUMAR, JJ.
Prasanth B. – Appellant
Versus
Hoysala Projects Private Limited – Respondent
WA Nos. 1058, 1059, 1060, 1063, 1064, 1076 of 2026
Decided On : 02-06-2026

Advocates Appeared:
For the Appellants : K. Shaj, Beena N. Kartha, Arun Chand, Kevin James, Gopika Gopal, Bharat Vijay P.
For the Respondents: E.K. Nandakumar, Saijo Hassan, Nandagopal S. Kurup

The mandatory pre-deposit requirement of the real estate legislation is a jurisdictional condition precedent. Courts cannot, through interim orders, substitute statutory interest benchmarks or dilute pre-deposit conditions, as doing so constitutes impermissible judicial legislation and violates the principle of separation of powers.

Headnote:(A) Real Estate (Regulation and Development) Act, 2016 - Sections 43(5) and 58 - Kerala Real Estate (Regulation and Development) Rules, 2018 - Rule 18 - Pre-deposit requirement for filing appeal - Promoters/builders must deposit interest as per statutory rules - Substitution of interest benchmark through judicial intervention during interim stage is impermissible. (Paras 12, 13, 19, 24)

(B) Judicial Review - Scope of interference - Courts should not interfere with discretionary orders unless they are perverse, contrary to law, or without jurisdiction - Power under Article 226 cannot be used to rewrite statutory rules or substitute legislative policy choices. (Paras 8, 19, 24, 25, 26)

Facts of the case:
Allottees/buyers filed complaints against a developer for failure to deliver possession of housing units within the agreed timeframe. Regulatory authorities ordered the developer to pay interest at a rate prescribed by state rules, calculated using a specific bank benchmark plus two percent. The developer approached the appellate tribunal seeking exemption from the mandatory pre-deposit requirement or a reduction in the rate, which was rejected. Writ petitions were subsequently filed, and a single judge passed an interim order permitting the developer to calculate interest for pre-deposit purposes using a different lending benchmark.

Findings of Court:
The court held that the requirement of pre-deposit under the specific statutory provision is mandatory and cannot be diluted. The use of a specific bank benchmark in the rules was a conscious policy choice by the legislature to deter defaults and protect consumers. Judicial intervention that effectively substitutes this benchmark during an interim stage is an overreach of the doctrine of separation of powers and undermines the statutory mandate.

Issues: Whether a court can, via an interim order, substitute the statutory interest benchmark prescribed under state rules for the purpose of calculating pre-deposit, and whether such an order is appealable.

Ratio Decidendi: Legislative policy choices concerning sectoral regulation and consumer protection must be respected; courts cannot rewrite statutory instruments. The mandatory pre-deposit requirement of the governing legislation serves as a jurisdictional condition precedent that cannot be diluted by interim judicial modifications, especially when the legislative intent behind the specified interest rate is to ensure deterrence against developers.

Result: Appeals allowed; interim orders set aside with a direction to comply strictly with statutory pre-deposit requirements within the stipulated time.

Table of Content
1. nature of the dispute involving project delays and pre-deposit requirements under rera. (Para 2)

JUDGMENT :

1. These Writ Appeals have been preferred challenging the common order dated 24.03.2026 passed by the learned Single Judge of this Court in W.P.(C) Nos. 35451, 36421, 36488, 36492, 36503 and 36658 of 2024. By the said order, as an interim measure, the learned Single Judge permitted the writ petitioner who is a promoter/builder, to make payment of the pre-deposit as mandated under the proviso to sub-section (5) of Section 43 of the Real Estate (Regulation and Development) Act, 2016 (Act 16 of 2016), calculated on the basis of the Marginal Cost of Funds based Lending Rate (MCLR) prevailing as on the date of passing of the order. The said order is under challenge in these intra-court appeals filed under Section 5 of the Kerala High Court Act, 1958.

2. Before dealing with the contentions, it would be profitable to refer to the facts which led the writ petitioner to approach this Court.

3. As identical issues are involved, for the sake of clarity, W.A. No. 1063 of 2026 shall be taken as the lead case. The parties shall hereinafter be referred to as "allottee/buyer" and "promoter/builder" as the case may be.

4. The allottees/buyers of a housing project by name “Hoysala EVM” apartments approached RERA and filed separate complaints. The gist of the allegations in the complaint are as under:

a) M/s. Hoysala Projects Pvt. Ltd. is the promoter/builder who entered into a Joint Venture Agreement with the other respondents for the development of a housing project by name “Hoysala EVM”. The allottees/buyers agreed to purchase apartments in the said project each measuring approximately 962 sq.ft. An agreement for sale and construction was entered into on 28.10.2013, as per which the project was to be completed and handed over within a period of 36 months, i.e., by October, 2016. The total sale consideration of Rs. 38,24,396/- was transferred to the builder. The allottees/buyers contended that the construction was not carried out as per specifications, and the project was not completed. In the said circumstances, legal notice was issued on 14.07.2021. Thereafter, separate complaints were lodged seeking issuance of directions to the builder to complete and hand over the apartment with covered car parking, after completing the common areas and amenities, and to execute the conveyance deed.

b) The RERA, after evaluation of the materials, came to the conclusion that the allottees/buyers had remitted a total amount of Rs.34,02,496/- before the assured date of completion, i.e., on 28.10.2016, and that thereafter, the balance amount, thus totalling Rs.38,24,396/-. Taking note of the above, it was held that the promoter/builder is liable to pay interest to the allottees/buyers as per the proviso to Section 18 (1) of Real Estate (Regulation and Development) Act, 2016. The authority took note that as per Rule 18 of the Kerala Real Estate (Regulation and Development) Rules, 2018, the rate of interest payable by the promoter/builder shall be State Bank of India's Benchmark Prime Lending Rate (BMPLR) plus 2% and shall be computed as simple interest. Holding so, the authority directed the promoter/builder to pay simple interest at 16.85% per annum on the amounts paid, calculated from the dates of payment. The authority also directed that if the amounts were not paid, the allottees/buyers were at liberty to recover the amount from the promoter/builder and its assets by initiating execution.

c) Being aggrieved, separate appeals were preferred by the promoter/builder before the Real Estate Appellate Tribunal, Ernakulam. Along with the appeal, an application was filed purportedly under the proviso to Section 43 (5) of Act 16 of 2016, seeking exemption from depositing 30% of the penalty/compensation and to hear the appeal on its merits.

d) The Tribunal considered the request for exemption and also the objection filed by the allottees/buyers and d

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top