SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2016 Supreme(Raj) 996

IN THE HIGH COURT OF JUDICATURE FOR RAJASTHAN BENCH AT JAIPUR
MOHAMMAD RAFIQ, J.
Singhal Construction Company Registered Partnership firm B Narain Gate, Bharatpur through its partner Shri Gopal Chand Singhal son of Late Shri Goverdhan Singhal - Petitioner
Versus
Rajasthan State Agriculture Marketing Board through Administrator, Pant Krishi Bhawan, Janpath, Jaipur – Respondent
S.B. ARBITRATION APPLICATION NO. 3 of 2010
Decided On : 07-10-2016

Advocates Appeared:
For the Petitioner: Mr. R.P. Garg with Mr. D.D. Sharma
For the Respondent: Mr. R.A. Katta

Headnote:

Constitution of India – Article 226 – Arbitration and Conciliation Act, 1996 – Sections 10, 34 and 11 – Arbitration Act, 1940 – Section 8 – Amendment Act of 2015 – Section 12 – Appointed Resolution – Public Works Department – Respondents Awarded – Commencement and Completion – Learned counsel applicant submitted that respondents did not provide lay out plan in time, changed the specifications time and again and also failed to provide clear site to the applicant for construction – Respondent-department failed to acquire land give compensation to the land holders reluctantly who knocked door of courts of law and stay order were granted – Respondents also failed to settle agitation and protest of villagers in constructing roads because their crops were standing on site and site was still in their possession and cultivation these reasons work could not be completed. After lapse of stipulated date of completion of work respondents department without consent of applicant extended interim time period – Held, Clauses both Schedule Fifth and Seventh are similarly worded which provide that if arbitrator is an employee consultant advisor or has other past or present business relationship with a party it would give rise to justifiable doubts as to his independence or impartiality – Clauses 5 of both Schedule Fifth and Seventh also provide that for a similar consequence if any arbitrator happens to be manager director or part of management or has a similar controlling influence in an affiliate of one of parties if affiliate is directly involved in matters in dispute in arbitration. Sub-section (5) of Section 12 of Amendment Act of 2015 has been given overriding effect over any prior agreement to contrary – Appeal dismissed.

ORDER :

1. This application under Sections 10 and 11 of the Arbitration and Conciliation Act, 1996 (for short 'the Act of 1996') has been filed by the applicant Singhal Construction Company, which is a partnership firm, through its partner Gopal Chand Singhal, with the prayer that an independent arbitral tribunal may be appointed for resolution of its disputes with the respondents.

2. Factual matrix of the case as averred in the application is that the applicant is a partnership firm registered as 'A' class contractor with the Public Works Department. The respondents invited tender for construction of 5 Links Roads under MDFF Packages. Offer of the applicant being found lowest, the respondents accepted the same and awarded contract for aforesaid construction to the applicant vide order dated 17.10.1998. Estimated cost of the work was Rs. 69,92,335.00 and stipulated time for completion of work was 15 months from 11.10.1998. Thus, date of commencement and completion of work were fixed respectively as 11.10.1998 and 10.01.2000. The applicant deposited a sum of Rs. 3,49,000/- as performance guarantee/bank guarantee in favour of the respondents. In order to execute the work an Agreement 10/98-99 was executed and signed between the parties.

3. Learned counsel for the applicant submitted that the respondents did not provide lay out plan in time, changed the specifications time and again and also failed to provide clear site to the applicant for construction. The respondent-department failed to acquire the land, give compensation to the land holders reluctantly, who knocked the door of the courts of law and stay order were granted in their favour. The respondents also failed to settle the agitation and protest of the villagers in constructing the roads because their crops were standing on the site and the site was still in their possession and cultivation. For all these reasons, the work could not be completed. After lapse of stipulated date of completion of the work, the respondents department without consent of the applicant extended interim time period up to 30.06.2000. It is argued that the respondents were fully responsible for non-execution of the work in time, even then without affording an opportunity of hearing and notice to show cause, the respondents unilaterally imposed deducted liquidated damages @ 0.03% of Rs. 1,84,342/- on the applicant. Yet, despite request of the applicant to finalize the work at that particular stage, the respondents failed to finalize the bill. There was delay in execution of the work, which was beyond control of the applicant and the applicant was not liable for such delay.

4. It is argued that in the circumstances so narrated, the applicant exercised arbitration clause 23 of the agreement signed between the parties and requested the respondents to refer the dispute to Empowered Standing Committee. When no action was taken, the applicant moved application for appointment of arbitrator before this Court. However, during pendency of the application, the respondents referred the dispute to the Empowered Standing Committee. The applicant filed objections with regard to constitution of the Standing Empowered Committee. Even then, the Standing Committee passed the award. The applicant challenged the award by filing objections under Section 34 of the Act of 1996 before the District and Sessions Judge, Alwar which vide judgment dated 16.05.2009 set aside the award. Learned counsel for the applicant, therefore, submitted that independent arbitrator may now be appointed so as to resolve the disputes between the parties. It is argued that Division Bench judgment of this Court in State of Rajasthan & Others Vs. SPML INFRA Ltd. & Another, 2015 (4) WLC (Raj.) 375 and Single Bench Judgment of this Court in M/s. Mohammed Arif Contractor Vs. State of Rajasthan & Another, 2015 (4) WLC (Raj.) 32 holding that Clause 23 in the format of agreement in Public Works Department of State Government is not a arbitration clause, h



































Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
Judicial Analysis

SupremeToday

SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top