SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2024 Supreme(Raj) 536

IN THE HIGH COURT OF JUDICATURE FOR RAJASTHAN AT JODHPUR
DINESH MEHTA, RAJENDRA PRAKASH SONI, JJ.
Riddhi Siddhi Infraproject Pvt. Ltd., Through Its Authorized Representative Om Prakash Kumawat S/o. Bhanwar Lal Kumawat - Appellant
Versus
M/s Anil Industries, Through Its Owner Proprietor/Authorized Reprsentative Anil Dangi and Ors. – Respondents
D.B. Civil Misc. Appeal No. 873 Of 2024
Decided On : 29-05-2024

Advocates Appeared:
For the Appellant : Mr. Pushkar Taimini, Mr. Sanjay Nahar.
For the Respondents: Mr. Sandeep Saruparia, Mr. Nikhil Ajmera.

IMPORTANT POINT
The court clarified that the initiation of arbitral proceedings is marked by the notice of appointment of an arbitrator, and the court retains the discretion to extend interim measures beyond the statutory 90-day limit.

Headnote:

INTERIM MEASURES - ARBITRATION AND CONCILIATION - Commercial Courts Act, 2015; Arbitration and Conciliation Act, 1996, Sections 9, 11, 21 - The court discussed the provisions of the Commercial Courts Act, 2015 and the Arbitration and Conciliation Act, 1996, particularly focusing on Sections 9 and 11. It interpreted Section 9(2) as allowing the court to extend interim measures beyond 90 days, contrary to the Commercial Court's ruling. The court emphasized that arbitral proceedings commenced upon notice of appointment of an arbitrator under Section 21, which influenced its decision to overturn the lower court's order.

Fact of the Case:

The appellant sought an interim order under Section 9 of the Arbitration and Conciliation Act, 1996 to maintain status quo on disputed land pending arbitration. The Commercial Court initially granted this order but later rejected the appellant's request to extend it, citing a failure to initiate arbitral proceedings within 90 days.

Finding of the Court:

The court found that the Commercial Court erred in its interpretation of the statutory timeline for initiating arbitral proceedings. It held that the arbitral proceedings had commenced upon the notice of appointment of the arbitrator, thus allowing for the extension of the interim order.

Issues: Whether the Commercial Court correctly interpreted the timelines for initiating arbitral proceedings and the extension of interim measures under the Arbitration and Conciliation Act, 1996.

Ratio Decidendi: The court established that the commencement of arbitral proceedings is determined by the notice of appointment of an arbitrator, and that the court has the authority to extend interim measures beyond the 90-day period specified in Section 9(2) of the Arbitration and Conciliation Act, 1996.

Final Decision: The appeal was allowed, the order of the Commercial Court was set aside, and the respondent was directed to furnish a solvent surety to maintain the balance of equity pending arbitration.

JUDGMENT :

(Dinesh Mehta, J.) :

1. Instant appeal which has been preferred under Section 13 of the Commercial Courts Act, 2015, calls in question, the order dated 24.01.2024, passed by the learned Commercial Court, Bhilwara, whereby the appellant’s request for extending the interim order dated 10.10.2023 was refused.

2. The facts precisely narrated are that the appellant had moved an application dated 19.09.2023 under section 9 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as “the Act of 1996”) with assertion that in relation to an agreement dated 10.12.2009, a dispute has arisen between the parties and as per clause 31 of the said agreement which was to be resolved by way of arbitration. And accordingly, invoking clause 31, the appellant appointed Mr. Satyanarayan Derashri as an Arbitrator and initiated the proceedings as required. But as the respondent is not taking any interest, the proceedings in terms of clause 31 and decision by way of Arbitration is likely to take some time. It was thus, prayed that until the dispute is resolved by the Arbitrator and award is passed, by way of interim measure the respondent be restrained from alienating the property or from raising construction on the disputed land and also be directed to maintain status quo.

3. Pursuant to the application aforesaid, the Commercial Court passed an order dated 10.10.2023 and directed the parties to maintain status quo in relation to the land (Khasra Nos.3021, 3022, 3023 of Tehsil Bhilwara) in dispute.

4. Thereafter, on 18.01.2024, the appellant moved this Court by way of filing an application under section 11 of the Act of 1996, for securing appointment of Arbitrator.

5. During the pendency of above referred application viz. Civil Misc. Case No.15/2023, pending before the Commercial Court, it was contended by the respondent that the order dated 10.10.2023 had a life of 90 days only, per force provision of section 9(2) of the Act of 1996. Faced with such stand, the present appellant filed an application dated 11.12.2023 with a prayer to pass further orders under section 9 of the Act of 1996 or to extend the interim order dated 10.10.2023.

6. The appellant’s said application was rejected and the application (Civil Misc. Case No.15/2023) filed under section 9 of the Act itself was disposed of by the Commercial Court on 24.01.2024. While rejecting the application (Civil Misc. Case No.15/2023), the Commercial Court observed that the appellant was required to take up the arbitral proceedings within a period of 90 days i.e. on or before 10.01.2024, whereas the application under section 11 of the Act of 1996 came to be filed before Hon’ble High Court belatedly, on 18.01.2024. According to the Commercial Court as the appellant had failed to take up the proceeding for securing appointment of Arbitrator within the statutory timeline of 90 days, no indulgence can be granted.

7. Mr. Taimini, learned counsel for the appellant argued that Commercial Court has erred in non-suiting the appellant on the ground that it has not taken up the arbitral proceedings under section 11 of the Act of 1996, within a stipulated period (upto 10.01.2024).

8. He invited Court’s attention towards section 21 of the Act of 1996 and submitted that arbitral proceedings should be deemed to have commenced on 12.07.2023-when the notice of appointment of Arbitrator was received by the respondent. He argued that as a matter of fact and law, the arbitral proceedings had already commenced and the mandate of section 9(2) of the Act of 1996 had been met.

9. Learned counsel for the appellant submitted that when the appellant has already filed an application under section 11 of the Act of 1996 before the High Court, it was upon the learned Commercial Court to have either passed a fresh order under section 9 of the Act of 1996 or to have extended the interim order dated 10.10.2023 for a further period.

10. Mr. Saruparia, learned counsel for the respondent vehemently opposed the app

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
Judicial Analysis

AI

SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top