1996 Supreme(Raj) 21

Supreme Court
Honble A.M. AHMADI C.J. & S.C. SEN, J.
State of Maharashtra and Another - Appellant
Versus
M/s. National Construction Company, Bombay and Another - Respondents
Civil Appeal No. 1497 of 1996
Decided On : January 09, 1996

Act Referred

CIVIL PROCEDURE CODE : S.11, O.2 R.2

Headnote

C.P.C., Sec. 11 and Order 2, Rule 2 – The principle of res-judicata and Rule 2 of order 2 (Relinquishment of part of claim) are based on the rule of law a man shall not be twice vexed for one and the same cause – Scope of the principle – Where the cause of action on the basis of which the previous suit was brought, does not form the foundation of the subsequent suit – The relief claimed in the subsequent suit should not be sought in the earlier suit – The subsequent suit is not barred by order 2 Rule 2. (Para 14, 15 & 17)

       

Honble AHMADI, CJ. – The appellants are the State of Maharashtra and its Executive Engineer who was posted at the Masonry Dam Division, Nathnagar, during the relevant period. In 1967, the appellant invited tenders for perfoming work on the masonry portion of the Paithan Dam on Godavari River, as part of the Jayakwadi Project, Stage-I (hereinafter called ``the work ) , the first respondent, M/s. National Construction Company, Bombay (hereinafter called ``the contractor) submitted its tender offer for the work which was conditionally accepted by the appellants on 30.3.1967.

(2). On 6.1.1968, the second respondent, the Central Bank of India (hereinafter called ``the Bank), executed performance guarantee No. 57/22 whereby it guaran- teed that the contractor would faithfully conform to the terms and conditions of the contract to be entered into between the appellants and the contractor. Under the terms of the guarantee, the Bank was jointly and severally liable with the contractor for the latters default in perfomance, the liability of the Bank being limited to Rs. 14,12,836/-, i.e. 5% of the contract price. The guarantee was to remain in force till 3.7.1972. Soon thereafter, on 8.1.1968, the contract for commencing construction was executed. However, no work was initiated for almost two years. On 11.12.1969, the appellants gave an ultimatum to the contractor to begin work. It is alleged that instead of commencing work, the contractor abandoned the work on 19.12.1969. The appellants alleged that the contractor did not respond to their repeated reques- ts for recommencing work, forcing them to emply other agencies for completing the work. In the process, by 31.5.1972, they claim they had incurred expenses totalling Rs. 1,44,18,970.24.

(3). At this stage on 21.6.1972, the appellants filed Short Cause Suit No. 491/72 only against the Bank on the original side of the Bombay High Court praying for the recovery of Rs. 14,12,836/-, which was the amount stipulated in performance guarantee No. 57/22, with interest. It would be pertinent to note that the suit was filed before the guarantee lapsed on 3.7.1972. On 17.1.1983, the Bombay High Court dismissed the suit for non-joinder of parties, holding that the contractor was a necessary party for deciding the issue of default and the banks consequent liability. In appeal against this order, Appeal No. 303/83, the appellants included the contractor as a party in the cause title of the memo of appeal but the appeal was dismissed on 7.4.1983 on the very same ground. It may, however, be clarified that the contractor was not impleaded a party by the Courts order.

(4). On the same day, 7.4.1983, the appellants filed Spl. Civil Suit No. 29/83 against both the contractor and the bank in the Court of the Civil Judge (Senior Division) at Aurangabad. In this suit, the appellants claimed Rs. 1,13,27,298.16, with interest from the contractor by way of damages for breach of contract. This was inclusive of their claim for Rs. 14,12,836/- against the bank under the perfomance guarantee.

(5). On 28.7.1992, the learned Civil Judge dismissed the Suit holding that as the cause of action was identical to the one in the former suit, it was barred by res judicata under Explanation IV to Section 11 as also Order 2 Rule 2 of the Civil Procedure Code, 1908 (hereinafter called ``the Code). The appellants appealed against this order on the ground that the two suits were based on separate causes of action and the dismissal of the former on a technical ground could not act as a bar against the latter. On 9.7.1993, a Division Bench of the Bombay High Court by the decision impugned herein dismissed the appeal. Feeling aggrieved, the appellants have approached this Court by way of special leave.

(6). We may first dispute of the plea based on Section 11, Explanation IV, of the Code. That section deals with the doctrine of res Judicata and provide that any matter which might or ought to have been made a ground for defence or attack i