(Rajasthan High Court)
Raj. State Mines & Minerals Vs. R.A.M. Earth Movers (Lodha, J.)
HON'BLE SANGEET LODHA, J.
Rajasthan State Mines and Minerals Ltd.
Versus
M/s. R.A.M. Earth Movers Pvt. Ltd. & Anr.
S.B. Civil Writ Petition No. 473 of 2005, decided on 05.01.2010

Advocates Appeared
M.R. Singhvi, for Petitioner;
B.C. Mehta, for Respondents.

Headnote:Arbitration and Conciliation Act, 1996, Sec. 16, 34, 37 — Jurisdiction of Arbitral Tribunal — Whether any order passed by the arbitral tribunal during the arbitration proceedings would be capable of being challenged before the High Court u/Art. 226 or 227 of the Constitution of India? — Held — Sec. 37 makes certain order of the Arbitral Tribunal appealable — u/S. 34, aggrieved party has an avenue for ventilating its grievances against the award including any in between orders that might have been passed by the Arbitral Tribunal acting u/S. 16 of the Act — The party aggrieved by any order of the Arbitral Tribunal, unless has a right of appeal u/S. 37 of the Act, has to wait until the award is passed by the tribunal — Warrants no interference u/Art. 226/227 of the Constitution. (Paras 18 to 22)

       Writ petition dismissed.

        ek/;LFke~ ,oa lqyg vf/kfu;e] 1996] /kkjk 16] 34] 37 & ek/;LFke~ vf/kdj.k dh vf/kdkfjrk & D;k ek/;LFke~ dk;Zokgh ds nkSjku ek/;LFke~ vf/kdj.k }kjk ikfjr dksbZ Hkh vknsk Hkkjr ds lafo/kku ds vuqPNsn 226 ;k 227 ds rgr mPp U;k;ky; ds le{k pqukSfr fn;s tkus ;ksX; gksxk\ & vfHkfu/kkZfjr & /kkjk 37 ek/;LFke~ vf/kdj.k ds dfri; vknskksa dks vihy ;ksX; cukrh gS & /kkjk 34 ds rgr O;fFkr i{kdkj ds ikl ,okMz ds fo:) viuh fkdk;r dks laokrkf;r djus gsrq ekxZ gS ftlesa lfEefyr gS vknskksa ds e/; ikfjr dksbZ Hkh ,okMZ tks vf/kfu;e dh /kkjk 16 ds rgr dk;Z djrs gq, ek/;LFke vf/kdj.k }kjk ikfjr fd;k x;k gks & ek/;LFke~ vf/kdj.k ds fdlh Hkh vksnk ls O;fFkr i{kdkj] tc rd mlds ikl vf/kfu;e dh /kkjk 37 ds rgr vihy dk vf/kdkj ugha] dks rc rd bartkj djuk gksxk tc rd fd vf/kdj.k }kjk ,okMZ ikfrj ugha dj fn;k tkrk & lafo/kku ds vuqPNsn 226@227 ds rgr gLr{ksi okaNuh; ughaA ¼in la- 18 ls 22½

       ;kfpdk [kkfjt dhA

Hon'ble LODHA, J.—This writ petition is directed against order dated 17.10.04 by the Sole arbitrator whereby an application preferred by the petitioner-non claimant u/S. 16 of the Arbitration & Conciliation Act, 1996 (in short "the Act") questioning the jurisdiction of Arbitral Tribunal to proceed with the arbitration proceedings, stands rejected.

2. The facts relevant in nutshell are that the petitioner, a Government company issued a Notice Inviting Tender (`NIT') dated 28.8.95 for the work "Transportation of Gypsum (ROM) from Ballar Gypsum Mines to Lalgarh Railway Siding and Anoopgarh Railway Siding." In pursuant thereto, the respondent No. 1 and some other persons submitted their tender. The rates quoted by the respondent No. 1 was the lowest, accordingly, its tender was accepted and the work order dated 9.2.96 was issued by the petitioner company in favour of the respondent No. 1 on the terms and conditions set out in the NIT as modified after negotiation. The term of the contract was three years from the date of start of the work. However, the work could not commence on account of alleged non creation of working conditions by the petitioner company and therefore, the respondent No. 1 vide letter dated 7.8.96 raised a claim against the petitioner company for a sum of Rs. 35,90,087.65 on account of the losses suffered by it and requested for payment thereof within a period of three weeks. After due deliberations, the matter was amicably settled between the parties and a fresh work order dated 4.3.99 was issued in favour of the respondent No. 2 and accordingly, the respondent No. 3 withdrew all its claim and agreed to work as per the rates agreed upon under the fresh work order dated 4.3.99.

3. In pursuance of the fresh work order, the respondent No. 1 started the work on 6.5.99, however, a contract was executed between the parties on 23.6.99. After commencement of the work as aforesaid, the petitioner company felt that contract is not viable and the rates agreed upon were excessive, prejudicial and against the interest of the petitioner company, therefore, the General Manager of the petitioner company terminated the contract granted in favour of the respondent No. 1 by giving 30 days notice invoking clause 17.3 of the contract which reads as under:-

"17.3."- Notwithstanding anything hereinabove, the Company in its absolute discretion, made at any time, terminate the contract without assigning any reason thereof by giving 30 days' notice in writing to the contractor at their last known notified address and in that event, the contractor shall not be entitled to raise any claim or demand for compensation and/or damages and/or loss by reason of such earlier termination on any ground whatsoever."

4. The notice was replied by the respondent No. 1 vide communication dated 19.11.99 alleging therein that the contract has been wrongly terminated and the action of the respondents in terminating the contract is outcome of male fide. The said communication was not responded therefore, the respondent No. 1 made an application to the Chairman of the petitioner company for appointment of an Arbitrator which was rejected by the Chairman vide communication dated 31.1.2000. In these circumstances, the respondent No. 1 preferred an application u/S. 11 of the Act before the District Judge, Bikaner for appointment of an Arbitrator and also preferred an application for grant of temporary injunction u/S. 9(e) of the Act read with Order XXIX Rule 1 & 2 of the Civil Procedure Code, 1908 praying therein that till the disposal of the application u/S. 11 of the Act by the Court, the petitioner company herein may be restrained from treating the work contract granted in favour of respondent No. 1 herein as cancelled. However, the application preferred by the respondent No. 1 for injunction as aforesaid, was disposed of by the District Judge holding that it will not be appropriate to restrain the respondents from issuing the fresh work order.

5. After termina