IN THE HIGH COURT OF HIMACHAL PRADESH AT SHIMLA
Tarlok Singh Chauhan, Stayen Vaidya, JJ.
M/S Bharat Construction (I) Private Limited Through Its Authorised Signatory Sh. Jai Pal Singh, 9-Ppcl Conoy, Uday Vihar, Opposite Radha Swami Satsang, Haridwar Vy Pass, Dehradun, Uttarakhand – Petitioner
Versus
M/S Himachal Pradesh Road Infrastructure Development Corporation Limited (Hpridcl) And Ors. – Respondents
Civil Writ Petition No.6434 of 2021
Decided On : 16-11-2021
Constitution of India,1950 - Article 226 and 14 - rectify its mistake/omission by confirming that bid price - Award - RFP/NIB for the bidders to submit their financial quotes by including GST - Whether failure of respondent No.2 to submit financial bid strictly as per Appendix 1B and more particularly with “corrigendum-1” would render said respondent disqualified from contest - Whether subsequent clarification by the employer from respondent No.1 was not warranted by RFP/NIB and also such conduct of employer was reflective of its bias towards respondent No.1 - Alleged that terms of RFP/NIB specifically prohibited any correspondence between employer and bidders violation of such prohibition was evident from fact that respondent No.1 after having received written objections petitioner had ventured into seeking clarification on material aspect of tender from respondent No.2. According to petitioner, it was this conduct of respondent No.1 that gave undue advantage to respondent No.2 to make good deficiencies in financial bid - Respondent by way of two-bid system invited offers through Request for Proposal/Notice Inviting Bid for construction of “2 Lane Road Tunnel” parallel to existing Dhalli Tunnel under the Shimla Smart City Mission on EPC mode with estimated cost – Held, Allegations of respondents that petitioner has not approached this Court with clean hands - It did not intentionally disclose at the time of filing of the petition that work had already been awarded and EPC contract had been executed besides investments already incurred by respondent No.2. This definitely allowed petitioner to succeed in obtaining interim directions from this Court - Non disclosure of material facts by the petitioner may not be fatal to its case at the stage of final adjudication, but it definitely can be taken to be a factor for determining that the motive of the petitioner in filing the petition was sheer act of vengeance and definitely not bonafide – petition dismissed.
JUDGMENT :
Satyen Vaidya, J.
By way of instant petition, the petitioner has prayed for following substantive reliefs:-
ii. Issue writ of certiorari to quash and set aside the said award issued in favour of respondent No.2 by respondent No.1; and/or
iii. Issue a writ of certiorari to quash and set aside the financial bid of respondent No.2 declared vide notification dated 02.08.2021 (Annexure P-6); and/or
iv. Issue a writ of mandamus directing the respondent No.1 to issue the letter of award in favour of petitioner; and/or
v. Issue a writ of certiorari to quash and set aside the entire tender process; and/or
vi. Issue a writ of mandamus directing the respondent No.1 to re advertise the tender in question;”
2. Respondent by way of two-bid system invited offers through Request for Proposal/Notice Inviting Bid (for short “RFP/NIB”), dated 15.06.2021 for construction of “2 Lane Road Tunnel” parallel to the existing Dhalli Tunnel under the Shimla Smart City Mission on EPC mode with estimated cost of Rs.53 crores. Petitioner and respondent No.2, in response to RFP/NIB dated 15.06.2021, submitted their respective bids. Both the bidders were declared technically responsive, their financial bids were evaluated on 2.8.2021 and Respondent No.2 was found “L-1”. Letter of acceptance (for short “LOA”) favouring respondent No.2 was issued on 12.08.2021.
3. On 3.8.2021, petitioner addressed respondent No.1, inter alia, taking exception to the financial bid of respondent No.2 being not in the format prescribed by RFP/NIB. Petitioner further extended certain clarification with respect to its own financial bid vis-a-vis the GST component. Respondent No.1 did not agree to the objections raised by the petitioner, and, replied to this effect vide correspondence dated 5.8.2021. Some further correspondence was exchanged inter se the petitioner and respondent No.1, but respondent No.1 adhered to its decision and issued LOA in favour respondent No.2, as noticed above.
4. The entire edifice of the case of the petitioner has been built on the premise that RFP/NIB specifically provided for a format in which the bidders were required to submit their respective bids. As per petitioner, the condition of RFP/NIB to the effect that the bids were to be submitted in a specified format was imminent and admitted of no exception. The petitioner has also contended that initially there was no requirement in RFP/NIB for the bidders to submit their financial quotes by including GST and other applicable taxes, cess etc., and it was only by way of “Corrigendum-1” incorporated in RFP/NIB through amendment dated 6.7.2021, that bidders were mandated to quote their financial bids by including GST and its incidence. The petitioner has taken exception to the fact that respondent No.2 did not submit its financial bid in the manner required by Corrigendum-1, dated 6.07.2021 and it was only after the petitioner raised objections, that respondent No.1 afforded opportunity to respondent No.2 to rectify its mistake/omission by confirming that bid price quoted by it, included component of GST at the rate of 12%.
5. Petitioner has further alleged that the terms of RFP/NIB specifically prohibited any correspondence between the employer and the bidders, whereas, the violation of such prohibition was evident from the fact that respondent No.1 after having received written objections dated 3.08.2021 from the petitioner had ventured into seeking clarification on material aspect of the tender from respondent No.2. According to the petitioner, it was this conduct of respondent No.1 that gave undue advantage to respondent No.2 to make good the deficiencies in the financial bid.
6. Respondent No.1 in its reply has contested the stand of th
Afcons Infrastructure Limited vs. Nagpur Metro Rail Corporation Limited and another
Bharat Cooking Coal Limited and others vs. Amar Dev Prabha and others
Central Coalfileds Limited and another vs. SLL SML (Joint Venture Consortium) and others
Michigan Rubber v. State of Karnataka (2012) 8 SCC 216
Raunaq Internation Ltd. vs. I.V.R. Construction Ltd. And others
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.