IN THE HIGH COURT OF JAMMU AND KASHMIR AT JAMMU
PANKAJ MITHAL, RAJNESH OSWAL, JJ.
M/s Vijeta Projects and Infrastructure Ltd - Appellant
Versus
Union of India and others - Respondents
LPA No. 59 of 2021
Decided on : 30-04-2021
Constitution of India, 1950 - Article 14 and 226 - Contract and Agreement - Non-payment of dues - Work remained uncompleted - Whether termination of contract vide order is illegal or unjustified - Appellant started construction work of hospital and during course of execution of the work, due to number of changes in scope of work as well as in goods to be consumed by appellant, pace of execution of work was severely effected - Appellant mentioned the following deviations sought for by the respondents, in his writ petition:
Finding of the court: On perusal of record reveals that there are allegations and counter allegations on the part of both parties against each other and neither we nor the learned Single Judge has returned any finding qua genuineness of claims of either of parties. The work of utility in question being of vital importance cannot be allowed to remain in suspended animation just because of slow pace of work or on account of payments due, if any. Appellant would have been right in contending that action of respondents was arbitrary, had respondents furnished no reason for purpose of terminating contract or had terminated contact on basis of reasons contrary to record, but there is nothing on record to demonstrate either of above.
Result: Appeal dismissed
JUDGMENT :
RAJNESH OSWAL, J
1. This intra court appeal has been preferred against the judgment dated 14.01.2020 (hereinafter to the referred as the judgment impugned) passed by the learned Single Judge by virtue of which, two writ petitions bearing Nos. OWP No. 168 of 2019 and OWP No. 485 of 2019 were dismissed.
2. The judgment impugned has been challenged on the following grounds:
(ii) that the learned Single Judge should have considered the fact that the respondents could not have issued the impugned order of cancellation, particularly when they had agreed with the appellant that the deadline for completion of the work would be 31.12.2019. The work had been substantially completed by the appellant and the work remained uncompleted due to the non-payment of dues of the appellant by the respondents and also delay in the execution/completion of project was occasioned because of frequent deviations made by the respondents in the original plan.
(iii) that the learned Single Judge ought to have held that the termination letter was bad in law due to legal mala fides and the writ petition was maintainable as the State is under a constitutional obligation to act fairly and that the State cannot practice discrimination or arbitrariness.
(iv) that the impugned judgment prejudges the contractual claims and observes on merits instead of limiting the jurisdiction within the bounds of Article 14 of the Constitution thereby violating the scope of Article 226 of the Constitution.
3. Briefly stated, the facts necessary for the disposal of the instant appeal are that the appellant was awarded a contract for the construction of a 650 bed hospital along with OTM ACCN In. Lift, Central AC Plant, Hot Water Supply, Fire Hydrant, Sprinkler System, Fire Alarm System and External Service for a Command Hospital, Northern Command, at Udhampur in the Union Territory of Jammu and Kashmir and Contract Agreement No. CEUZ/UDH/09/2010-11 dated 27.01.2011 was executed. Time period for the execution of the work was 27 months commencing from 10.02.2011. It is the case of the appellant that after the site was handed over to the appellant on 10.02.2011, the appellant started the construction work of the hospital and during the course of execution of the work, due to number of changes in the scope of work as well as in the goods to be consumed by the appellant, the pace of the execution of the work was severely effected. The appellant mentioned the following deviations sought for by the respondents, in his writ petition:
b. The respondents demanded change in the size of the lifts from 20 passengers to 26 passengers.
c. Change was made from glass wool insulation for chilled water as provided in original contract to the expanded Polystyrene insulation
d. Change in G F Plan due to relocation of various areas with in the Hospital building (35% of the G.F area and 10% of Hospital area).
e. Abnormal variation in quantities ranging up to more than 1000% for Air conditioning, Fire Fighting, Medical Gases etc.
f. Change in the specifications in the basement crumples, three times.
4. It is also stated in the petition that the appellant time and again requested the respondents that they should allow the appellant to adhere to the original contract and should refrain from making unnecessary changes in the executed agreement and allow the appellant to co
ABL International Limited vs. Export Credit Guarantee Corporation of India Limited
Union of India vs Tantia Constructions (P) Ltd (2011) 5 SCC 697
Joshi Technologies International Inc. vs. Union of India and Others
K.K.Sakesena vs. International Commission on Irrigation & Drainage
Tata Cellular Vs. Union of India” reported in 1994 (6) SCC 651
SupremeToday
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.