2023 Supreme(J&K) 235

IN THE HIGH COURT OF JAMMU & KASHMIR AND LADAKH AT JAMMU
M.A. CHOWDHARY, J.
Farooq Hussain, S/o. Talib Hussain - Petitioner
Versus
UT of Jammu & Kashmir through Principal Secy. PWD (R&B), Civil Secretariat, Jammu & Ors. - Respondents
WP (C) No. 2301 of 2023, CM No. 5358 of 2023, CAVEAT No. 1602 of 2023
Decided On : 22-09-2023

Advocates Appeared:
For the Petitioner:Mr. Sunil Sethi, Sr. Advocate with Mr. Navyug Sethi.
For the Respondents: Mr. Ravinder Gupta, AAG, Mr. F.A. Natnoo.

The court highlighted the importance of adhering to the Standard Bidding Document (SBD) and Notice Inviting Tender (NIT) requirements, including the provision of accurate information, and emphasized the need for judicial restraint in administrative actions, considering public interest in contract matters.

Headnote:

Tendering Process - Technical Bid Evaluation - E-NIT No. 14 of 2023-24 - [TENDERING PROCESS] - [E-NIT No. 14 of 2023-24] - [17.08.2023, 25.08.2023, 26.08.2023] - The court discussed the technical bid evaluation process for the construction of a road and the subsequent challenges raised by the petitioner. The court considered the compliance with the Standard Bidding Document (SBD) and the Notice Inviting Tender (NIT) and emphasized the significance of providing accurate information, including litigation history, as per the SBD. The court cited legal principles from previous cases to support its decision not to interfere with the tender process, highlighting the need for judicial restraint in administrative actions and the importance of public interest in contract matters.

Fact of the Case:

The petitioner challenged the technical bid evaluation process for a road construction project, alleging non-compliance with the Standard Bidding Document (SBD) and favoritism towards the successful bidder.

Finding of the Court:

The court found that the petitioner's technical bid was rightly declared non-responsive due to non-compliance with the SBD, particularly regarding the submission of accurate information, including litigation history. The court also noted that the tender process had culminated in the allotment of work to the successful bidder and the commencement of work execution.

Issues: The issues involved the compliance with the SBD and NIT, the significance of accurate information in the bidding process, and the timing of the petitioner's challenge to the technical bid evaluation.

Ratio Decidendi: The court emphasized the need for adherence to the SBD and NIT requirements, including the provision of accurate information, and cited legal principles to support its decision not to interfere with the tender process, considering the public interest and the advanced stage of work execution.

Final Decision: The petition was dismissed in limini, along with interim application(s), as the court found no merit to warrant interference at that stage of the tender process.

JUDGMENT :

CAVEAT No. 1602/2023

With appearance of Mr. F. A. Natnoo, Advocate, as counsel for the caveator/respondent No.5, the caveat is discharged.

WP (C) No. 2301/2023

1. Petitioner through the medium of this petition has sought the following reliefs :

    (a) An appropriate writ, order or direction in the nature of writ of certiorari quashing result of Technical Evaluation dated 17.08.2023 as well as revised result of Technical Evaluation dated 25.08.2023 issued by respondent no.3 whereby technical bid submitted by the petitioner in reference to E-NIT No. 14 of 2023-24 dated 12.07.2023 with respect to works indicated at serial no.4 i.e. “Construction of road from Main National Poonch Highway road to Mohalla Dramna Kindo Potha Lower, Tehsil surankote District Poonch” has been declared non-responsive and technical bid submitted by respondent no.5 has been declared responsive notwithstanding non compliance of various clauses of NIT/Standard Bidding Document by respondent no.5 i.e. non-uploading of mandatory documents by him.

(b) An appropriate writ, order or direction in the nature of writ certiorari quashing result of the financial bid dated 26.08.2023 together with all subsequent actions taken by the respondents 2 to 4 whereby respondent no.5 has been declared lowest for the aforesaid work/contract and the said contract is or likely to be awarded to respondent no.5 without considering and deciding the objections dated 19.08.2023 filed by the petitioner to the result of technical evolution summary dated 17.08.2023.

(c) An appropriate writ in the nature of mandamus commanding the respondents to declare the technical bid of the petitioner as "responsive" for the aforesaid contract/work and consider his financial bid on its merits and if the same is found to be lowest than respondent no.5 then allot the aforesaid contract in reference to E-NIT no. 14 of 2023-24 dated 12.07.2023, in favour of the petitioner.

(d) An appropriate writ in the nature of prohibition restraining the respondents from issuing allotment order with respect to aforesaid contract in favour of respondent no.5 in any manner.

2. It has been asserted in the petition that the tenders were invited by official respondents, for construction of different roads in Poonch District in terms of e-NIT No. 14 of 2022-23 dated 12.07.2023 and seven bidders including respondent no.5 filed their tenders in response to the aforesaid e-NIT for “Construction of road from Main National Poonch Highway road to Mohalla Dramna Kindo Potha Lower, Tehsil surankote District Poonch” (Under NABARD), to be completed in a period of two years for an estimated costs of Rs. 319.62 lacs.

3. Petitioner contends that soon after issuance of e-NIT in question, the respondent no.3 issued a Corrigendum dated 19.07.2023 whereby the contractors were directed either to upload their consent from J&K Pollution Control Board duly renewed for the current financial year or upload an undertaking from a Hot Mix Plant Holder for the peripheral distance 60 kms for construction of road works for complete job/black topping works for all class of contractors and subsequently, another corrigendum dated 27.07.2023 came to be issued by the respondent No.3 whereby it was directed that the bidders, are required to upload the consent from a Hot Mix Plant duly renewed from the current financial year or upload an undertaking from a Hot Mix Plant Holder with the renewed certificate from J&K Pollution Control Board for the peripheral distance 40 kms instead of 60 kms, for construction of road works in question.

4. It is being pleaded that the petitioner being eligible in all respects competed in the tendering process for aforesaid two works and in this behalf besides submitting his financial bid, also submitted his technical bid, on the web-portal of the respondents; that the petitioner besides uploading various mandatory documents, also uploaded two certificates dated 23.07.2023 and 31.07.2023 in reference to corrigendums dated 19.07.2023

        Click Here to Read the rest of this document
        1
        2
        3
        4
        5
        6
        7
        8
        9
        10
        11
        SupremeToday Portrait Ad
        supreme today icon
        logo-black

        An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

        Please visit our Training & Support