IN THE HIGH COURT OF JHARKHAND AT RANCHI
D.N. PATEL, AMITAV K. GUPTA, JJ.
Workmen represented by Bokaro Progressive Front, Bokaro Steel City, Bokaro, Jharkhand - Appellant
Versus
Their Management of Bokaro Steel Plant of M/s. Steel Authority of India, Bokaro (Jharkhand) & Anr. - Respondents
L.P.A. No. 215 of 2010
Decided On : 01-12-2017
INDUSTRIAL DISPUTE - WORKMEN - Industrial Disputes Act, 1947 (Act, 1947) - Section 2(s), Section 10 - [Section 2(s), Section 10] - The court discussed the meaning of 'workmen' under Section 2(s) of the Act, 1947 and the relationship between the workers and the employer. The court also considered the nature of the contract and the engagement of workers by the contractor. The key legal provisions discussed were Section 2(s) and Section 10 of the Act, 1947, and the interpretation of the term 'workmen' and the relationship between the workers and the employer.
Fact of the Case:
The case involved a dispute between the management of Bokaro Steel Plant and the workers engaged by a contractor, M/s. Trinity Technology Group, regarding the termination of their services after the completion of a contract for the installation and operation of High Pressure Water Jet for cleaning of Goose Neck and Oven Doors.
Finding of the Court:
The court found that the workers engaged by the contractor could not be considered as 'workmen' of the Bokaro Steel Plant under Section 2(s) of the Act, 1947. The court emphasized that the workers were engaged for a specific and complex task, and their relationship with the Bokaro Steel Plant was not that of regular workmen. The court also highlighted that the completion of 240 days of work does not automatically confer the status of 'workmen' of the original employer.
Issues: The main issue was whether the workers engaged by the contractor could be considered as 'workmen' of the Bokaro Steel Plant under the Act, 1947.
Ratio Decidendi: The court held that the workers engaged by the contractor, M/s. Trinity Technology Group, were not 'workmen' of the Bokaro Steel Plant as their engagement was specific to the contract and did not establish an employer-employee relationship as per the provisions of the Act, 1947. The court also emphasized that the completion of 240 days of work does not automatically confer the status of 'workmen' of the original employer.
Final Decision: The court dismissed the Letters Patent Appeal, upholding the decision of the learned Single Judge to quash and set aside the award passed by the Industrial Tribunal, Ranchi in Reference Case No. 12 of 1994.
D.N. Patel, J.
This Letters Patent Appeal has been preferred by the original respondent No. 1 of a writ petition being W.P. (L) No. 1529 of 2004. This writ petition was preferred by the respondent-Management, challenging the award passed by the Industrial Tribunal, Ranchi, in Reference Case No. 12 of 1994, award dated 30.03.2003. This writ petition, preferred by the respondent-Management was allowed by the learned Single Judge vide judgment and order dated 23.04.2010, and the award passed by the Industrial Tribunal, Ranchi in Reference Case No. 12 of 1994 dated 30.3.2003 was quashed and set aside mainly on the ground that the workmen who raised industrial dispute were in fact not the workmen within the meaning of Section 2(s) of the Industrial Disputes Act, 1947 (for the sake of brevity here-in-after referred to as the 'Act, 1947') of the Management of the Bokaro Steel Plant. In fact they were the employees of M/s Trinity Technology Group (T.T.G.) to whom the contract was given by M/s. Bokaro Steel Plant. On this ground, writ petition preferred by the Management was allowed by the learned Single Judge, and hence, the present workmen has preferred the present Letters Patent Appeal.
2. Factual Matrix :
- It appears from the facts of the case that M/s Bokaro Steel Plant is a steel manufacturing company. The main object of this company was or the goal to achieve is to manufacture varieties of steels which are manufactured as per the requirement of the customer. There is a captive consumption plant which manufactures Coke. This Coke is produced from Coal. The Coke is required to be blast in the furnace so that from iron ore percentage of carbon can be reduced and steel can be manufactured. The reduction agent is a Coke. Thus, there is integrated plant of manufacturing of Coke.
- For the efficient manufacturing and blasting of Coal in the furnace or the production of the hot metal Coke, Oven Plant requires Coke Oven Battery and other ancillaries units. From similarly situated Bhilai Steel Plant-a comparatively older plant, from where, experiences was shared, for the efficient functioning or the working of Coke Oven Battery, Goose Neck and Oven Door which must be maintained properly. This is a very super technical and complex nature of work for which Workmen within the meaning of Section 2(s) of the Act, 1947, of Bokaro Steel Plant cannot be engaged for such type of highly complex nature of work as Bhilai Steel Plant has given a similar contract, to be given at the Bokaro Steel Plant.
- Thus, for partial modernization of efficient working of Coke Oven Plant, Coke Oven Battery has to work efficiently for which Goose Neck and cleaning of the Oven Door has to be done highly efficiently. Out of verities of methods to achieve this goal, for making the machinery more productive and more efficient, help of a contractor namely, M/s. Trinity Technology Group was taken by the Bokaro Steel Plant.
- It farther appears that M/s. Trinity Technology Group has to engage skilled workers for cleaning of the Goose Neck and for cleaning of the Oven Door with the help of the High Pressure Water Jet. This efficient work can be done by using High Pressure Water Jet, for such a technical work, contractor-M/s. Trinity Technology Group has to engage its own employees. This type of employees are technically known in the labour jurisprudence as "Contractor's Employees".
- The work of installation, operation, maintenance and testing was given to M/s. Trinity Technology Group. The work was over as alleged by the Management as on 30.9.1992. In paragraph-16 of the written statement, filed before the Industrial Tribunal, Ranchi in Reference Case No.12 of 1994, whereas as per the workers the said work was completed as on 16.3.1991.
- From 01.10.1992 the contract of installation and operation was over by M/s. Trinity Technology Group. As installation, operation and testing etc., was over, the work of the contractor was also over. Once there was end of the contract by M
M.P. Housing Board v. Manoj Shrivastava
M.P. State Agro Industries Development Corpn. Ltd. v. S.C. Pandey
Post Master General, Kolkata v. Tutu Das (Dutta)
Hindustan Aeronautics Ltd. v. Dan Babadur Singh
Chandra Shekhar Azad Krishi Evam Prodyogiki Vishwavidyalaya v. United Trades Congress
Uttaranchal Forest Hospital Trust v. Dinesh Kumar
SAIL v. National Union Waterfront Workers
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.