IN THE HIGH COURT OF JHARKHAND AT RANCHI
Rajesh Shankar, J.
M/s. Ram Lal Agarwalla, through its Proprietor, Manoj Kumar Agarwalla. -Petitioner
Versus
The Central Coalfields Limited and ors. – Respondents
W.P.(C) No.2607 of 2020
Decided On : 07-12-2021
Constitution of India, 1950 – Article 226 – Power of high court to issue certain writs – Quashing the letter – Cancellation of contract – Prayed for grant of interim relief – Petitioner filed intra court appeal being L.P.A before learned Division Bench and same was disposed of – Held, It thus appears that there was no violation of the principles of natural justice in passing impugned order as alleged by petitioner – Petitioner had sufficient knowledge of consequence of non-compliance – Under aforesaid facts and circumstances of case, Court do not find sufficient ground to interfere with impugned letter issued by respondent no.6 under extraordinary writ jurisdiction – It is, however, observed that there has been no adjudication of rival factual pleas raised by parties in present order – Thus, petitioner will be at liberty to seek adjudication of dispute through arbitration as has been provided under GTC of contract or to work out any other legal remedy as available under law – Writ petition dismissed.
JUDGMENT :
Rajesh Shankar, J.
1. The present writ petition has been filed for quashing the letter under Ref. No. PO/TTK/Ramlal Agarwalla/NIT-11/Cancellation of contract/2020-21/1278 dated 11.09.2020 (Annexure-49 to the writ petition) issued under the signature of the Project Officer/Engineer-incharge, Tetariakhar OCP, Rajhara Area- respondent no.6, whereby the management of the respondent-Central Coalfields Limited has taken decision to take penal actions against the petitioner, namely, (i) Termination/cancellation of contract awarded to the petitioner in terms of Clause 9(a) of the GTC; (ii) Forfeiture of EMD of Rs.27.78 lakh in terms with Clause 6.1 of the GTC; (iii) debarring it from participating in future bids for a period of three years in terms with Clause 6.1 of the GTC; (iv) as per Clause 9.2(c), recovery is to be made from the petitioner to the extent of 20% of the contract value (20% of Rs.93,43,08,500/-) i.e. Rs.18,68,61,700/- being higher than the performance security and additional performance security deposited by the petitioner; (v) recovery is to be done by encashment of B.G. amounting to Rs.1,95,52,050/- submitted against performance security for Rs.93,43,100/- and additional performance security for Rs.1,02,08,950/-; and (vi) balance amount i.e. Rs.16,73,09,650/- (18,68,61,700-1,95,52,050) is to be recovered from any other contract of the petitioner-company or by institution of recovery suit in terms of Clause 9.2(c)(ii) of the GTC.
2. During pendency of the present writ petition, the petitioner prayed for grant of interim relief which was declined by this Court vide order dated 22.09.2020. Aggrieved thereby, the petitioner filed intra court appeal being L.P.A No. 298 of 2020 before learned Division Bench and the same was disposed of on 21.10.2020, observing as under:-
The parties are at liberty to make a motion before the learned Single Judge for listing of the writ petition.
So, far as passing of the interim order is concerned in view of the undertaking furnished by Mr. Das, on instruction of the competent authority of the respondents-CCL to the effect that no further recovery would be made till the disposal of the writ petition, this Court orders accordingly. Let no further recovery be made till the disposal of the writ petition.”
3. The factual background of the case as stated in the writ petition is that the respondent-CCL issued e-tender notice dated 24.05.2019 being NIT No.:CCL/GM(CMC)/Rajhara/2019/11 for hiring of HEMM for OB removal, extraction and transportation of coal at Tetariakhar OCP of Rajhara Area for a period of five years (hereinafter referred as ‘the said work’). The petitioner submitted its bid document and was found L-1 and the General Manager (CMC) issued letter of acceptance vide letter no.520 dated 25.10.2019, specifying that the term of completion of the work would be 1825 days which would be deemed to have commenced on the expiry of 30 days from the date of issuance of letter of acceptance or one week from the date of handing over the site of work, whichever is later, however, preparatory works would be started from 10th day of issue of LoA. Thereafter, the respondent no.8 issued letter of award vide letter no.347 dated 07.11.2019 for the aforesaid work. In compliance of the aforesaid letters, the petitioner submitted performance security through bank guarantee dated 19.11.2019 for Rs.93,43,100/-
Erusian Equipment & Chemicals Ltd. Vs. State of W.B. & Another
Gorkha Security Services Vs. Govt. (NCT of Delhi)
Harbanslal Sahnia & Another Vs. Indian Oil Corpn. Ltd. & Others
Joshi Technologies International Inc. & Others Vs. Union of India
Mohinder Singh Gill Vs. the Chief Election Commissioner
UMC Technologies Private Limited Vs. Food Corporation of India & Another
Union of India & Others Vs. Tantia Construction Private Limited
Uttar Pradesh & Others Vs. Ashok Kumar Nigam
Whirlpool Corpn. v. Registrar of Trade Marks [(1998) 8 SCC 1
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.