IN THE HIGH COURT OF JHARKHAND AT RANCHI
Anil Kumar Choudhary, J.
Sanjay Kumar Singh and ors. - Petitioners
Versus
The State of Jharkhand and ors. - Respondents
W.P. (Cr.) No. 745 of 2023
Decided On : 12-02-2025
| Table of Content |
|---|
| 1. introduction of writ petition and factual background (Para 2 , 4) |
| 2. arguments regarding environmental clearance requirements (Para 5 , 6) |
| 3. court's observations on sufficient grounds for cognizance (Para 7 , 8 , 9) |
| 4. conclusion to quash criminal proceedings (Para 10 , 11) |
JUDGMENT :
Anil Kumar Choudhary, J.
1. Heard the parties.
2. This Writ Petition has been filed invoking the jurisdiction of this Court under Article 226 of the Constitution of India with a prayer to quash the entire criminal proceeding in connection with Complaint Case No. 918 of 2022 including the order taking cognizance dated 27.09.2022, passed in the said case by the learned Chief Judicial Magistrate, Seraikella.
3. Though notices were served upon the respondent nos. 2 & 3 but no one turns up on behalf of the respondent nos. 2 & 3 in-spite of repeated calls.
4. The brief fact of the case is that the respondent no.3 filed Complaint Case No. 918 of 2022 alleging therein that M/s Vidhi Developers Private Limited of which the petitioner nos. 1 & 2 are said to be directors and though the Environment Impact Assessment (EIA) Notification bearing No. S.O. 1533 (E) dated 14.09.2006 of the Ministry of Environment and Forests, Government of India requires that all new projects and activities listed in the Schedule to the said notification requires prior environmental clearance from the concerned regulatory authority but the petitioners as well their company, which has been arrayed as accused no.1 of the said complaint; have constructed residential project without obtaining Environmental Clearance as mandated through Environment Impact Assessment Notification, hence it is alleged that the petitioners have committed the offence punishable under Section 15 and 16 of the Environment (Protection) Act, 1986.
5. It is submitted by the learned counsel for the petitioners by drawing attention of this Court to serial no. 8(a) of the Schedule of the said Notification dated 14.09.2006 that prior environmental clearance is required for the project or activity relating to building and construction projects if the same is more than or equal to 20000 sq. metre and less than 1,50,000 sq. metre. Drawing attention of this Court to annexure-10 series at page no. 151, it is submitted by the learned counsel for the petitioners that the company of the petitioners have constructed three different buildings which are not contiguous to each other at any point; vide three different permits obtained from the Adityapur Area Notified Council (AANC) vide Permit No. 704, 1422 and 591 of built-up area 10,519 Sq. metre, 4,442 sq. metre and 14,587 sq. metre respectively. It is next submitted that there is no allegation against the petitioners or their company of having constructing any project of building and construction of area more than or equal to 20,000 sq. metre but less than 1,50,000 sq. metre. Hence, even if the entire allegations made in the complaint are considered to be true, still there being no requirement of obtaining Environmental Clearance by the petitioners and by not taking any such Environmental Clearance, no offence is made out against the petitioners. Therefore, it is submitted that the continuation of this criminal proceeding will amount to abuse of process of law more so when the cognizance has been taken only against the petitioners in capacity of their being directors of the company Vidhi Developers Private Limited but no cognizance has been taken against the Vidhi Developers Private Limited. Hence, it is submitted that the prayer as prayed for in this writ petition be allowed.
6. The learned counsel for the State fairly submits that there is no averment in the complaint as to, what was the area of the building said to be constructed by the petitioners or their company. It is also fairly submitted that as per serial no. 8(a) of the Schedule of the said Notification dated 14.09.2006, prior Environmental Clearance is required only if the area of the construction to be
AI
Criminal proceedings under the Environment (Protection) Act may be quashed if no requisite environmental clearance is mandated due to construction area being below the statutory threshold.
The main legal point established in the judgment is that prosecution under the Environment (Protection) Act, 1986 may be considered an abuse of process of law if environmental clearance is granted af....
The main legal point established in the judgment is the requirement for fresh appraisal and prior clearance for changes in the scope of construction projects, as well as the applicability of penal pr....
The court established that statutory exemptions for industrial sheds, along with undue delay in prosecution, render the charges unsustainable.
The complaint under the Environment (Protection) Act can be filed by authorized officers of the State Pollution Control Board, and the absence of explicit authorization resolution does not invalidate....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.