2011 Supreme(Mad) 4064

High Court of Judicature at Madras
R. BANUMATHI & B. RAJENDRAN
Tirunelveli City Municipal Corporation rep. By its Commissioner
Versus
M/s. Sri Pathy Associates rep. By its Managing Director & Others
O.S.A. No. 215 of 2007
Decided On : 26-09-2011

Important Points

The main legal point established in the judgment is the court's authority to interfere with arbitral awards based on errors apparent on the face of the record and the interpretation of the agreement clauses.

Subject

Arbitration Law - Construction Contract

Act Referred

ARBITRATION AND CONCILIATION ACT : S.16(3), S.34
LETTERS PATENT : Cl.15
ORIGINAL SIDE RULES : O.37 R.1

Headnote

Arbitration - Construction Contract - Arbitration and Conciliation Act, 1996 - Section 34 - Claim Nos. 2, 5, 8 and 13 - Summary of Acts and Sections: The court discussed the applicability of Section 34 of the Arbitration and Conciliation Act, 1996, and the interpretation of the agreement clauses 24 and 25, and clause 40.2. The court also considered the legal principles of exhaustion of remedies and the scope of interference with arbitral awards.

Fact of the Case:

The Tirunelveli Municipal Corporation initiated a project for construction of a modern bus stand. A dispute arose between the Corporation and the contractor, leading to arbitration. The Corporation filed an appeal against the arbitral award.

Finding of the Court:

The court found that the contractor's claim for extra lead for filling earth was unsustainable due to a patent error in the arbitral award. The court also upheld the award for loss on supplying and laying Sand Gravel mix, and loss due to idle mobilisation of machinery. The interest awarded by the arbitral Tribunal was deemed reasonable and not interfered with.

Issues: The issues included the interpretation of the agreement clauses, the sustainability of the contractor's claims, and the reasonableness of the interest awarded.

Ratio Decidendi: The court held that the contractor's claim for extra lead for filling earth was unsustainable due to a patent error in the arbitral award. The court also upheld the award for loss on supplying and laying Sand Gravel mix, and loss due to idle mobilisation of machinery. The interest awarded by the arbitral Tribunal was deemed reasonable and not interfered with.

Final Decision: The appeal was partly allowed by modifying the award passed by the Arbitral Tribunal only in respect of claim No.2. In all other respects, the award passed by the Arbitral Tribunal was confirmed. The award amount was reduced from Rs.77,80,705/- to Rs.47,55,132.40 with interest at the rate of 12% per annum. No costs were awarded.

Advocates Appeared:
For the Appellant:R. Muthukumarasamy, Senior Counsel for S. Kandasamy, Advocate. For the Respondents:F1 - R. Murari, Advocate.

Judgment :-

B. RAJENDRAN, J

1. The Tirunelveli City Municipal Corporation, represented by its Commissioner, Tirunelveli, is the appellant in this appeal. The corporation/ appellant is aggrieved by the order dated 05.06.2007 passed by the learned single Judge, dismissing the O.P. No. 331 of 2004 filed by them.

2. According to the Appellant/Corporation, the Tirunelveli Municipal Corporation initiated a project for construction of a modern bus stand at Veinthakulam in Tirunelveli and the Government of Tamil Nadu had also accorded administrative sanction of Rs.628 lacs for this purpose. Subsequently, the Appellant/Corporation flouted tenders and out of the 19 tenders it received, the first respondent herein emerged as the successful bidder. Subsequently, the contract was awarded to the first respondent on 30.08.2000 for a cost of Rs.5,31,90,725/- and on the same date, an agreement was entered into between the Appellant/Corporation and the first respondent. The period for completion of the work stipulated in the agreement was 18 months and the work has to be completed by the first respondent on or before 28.02.2002. A work order was also issued by the corporation to the first respondent on 30.08.2000. According to the first respondent, since there was a delay attributable on the part of the Appellant/Corporation, the contract could not be completed in time. In this context, a dispute arose between the Appellant/Corporation and the first respondent. Therefore, as per the agreement, the first respondent nominated their arbitrator on 11.09.2002 and the appellant corporation in turn nominated their arbitrator on 10.10.2002. Both the arbitrators have chosen an umbire, the third arbitrator on 28.10.2002 and the arbitral tribunal commenced the arbitration proceedings. The arbitral Tribunal, after hearing both sides, passed an award, by majority, a sum of Rs.77,80,705/- as against the total claim made by the first respondent at Rs.2,12,48,646/-. Aggrieved by the award passed by the arbitral Tribunal, the Appellant/Corporation filed O.P. No. 331 of 2004 before the learned single Judge, which was also dismissed confirming the award passed by the arbitral Tribunal. As against the same, the present original side appeal is filed by the Appellant/Corporation.


3. The learned senior counsel appearing for the Appellant/Corporation would contend that though initially the entire amount awarded by the arbitral tribunal was questioned by the corporation in the Original Petition filed before the learned single Judge, the corporation is restricting their claim only in respect of claim Nos. 2, 5, 8 and 13 out of which claim No.13 pertains to rate of interest awarded by the arbitral Tribunal.

4. The learned counsel for the first respondent would only contend that normally, the Court will not interfere with the award passed by the arbitral Tribunal under Section 34 of the Arbitration and Conciliation Act, unless there are materials to show that there was a patent error or illegality or the arbitral Tribunal had relied on a material which is irrelevant for consideration. In this context, the learned counsel for the first respondent relied on the decision reported in (Pune Helium India Pvt Ltd., vs. Oil & Natural Gas Commission) 2003 8 SCC 593 to fortify his submission that the award passed by the Arbitral Tribunal, which are based on factual findings, shall not be disturbed, especially at the appellate stage. According to the learned counsel for the first respondent, even in respect of claim Nos. 2, 5, 8 and 13 which the Appellant/Corporation is restricting in this appeal, the learned counsel for the first respondent would contend that there is a variance in the contract. The contract itself provides that if there is any deviation or variance in the contract, then such item of work will be treated as a new item and the contractor is eligible to quote as if it is a new item. Admittedly, the first respondent made the claim under item Nos. 2, 5 and 8 as a new ite