SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2007 Supreme(Mad) 3144

Madurai Bench of Madras High Court
THE HONOURABLE MR. JUSTICE A.C. ARUMUGAPERUMAL ADITYAN
The Executive Engineer, Wind Farm Project, Tamilnadu Electricity Board, Maharaja Nagar, Tirunelveli & Another
Versus
S. Jegatheesan & Others
Second Appeal (MD) Nos.453 of 2007 and 513 of 2007 and M.P.Nos.1 and 1 of 2007
Decided On :Decided On : 27-09-2007

Advocates Appeared:
For the Appellants:R. Murali, Advocate. For the Respondents:P. Jeyapal, Advocate.

There should not be erection of pales in the land of any owner without his permission.

Headnote:Indian Electricity Act, 1910 (as amended by Central Amendment Act, 2003)-Section 12(2) and proviso-for erecting pales it is mandatory on the electricity board to get prior permission from the owner-Owner may claim compensation-Owner can file suit and also may obtain mandatory injunction for removing the poles.

       

Judgment :-

The defendants 4 and 5 in O.S.No.384 of 2004 who had lost their defence before the Courts below are the appellants herein. The Plaintiff had filed the suit in O.S.No.384 of 2004 before the Court of Principal District Munsif, Valliyoor for mandatory injunction against the defendants/the appellants herein, the Electricity Board represented by its Executive Engineer and the Superintendent Engineer and for a direction to remove the Electricity poles installed in his land in S.No.2/2A measuring 6.52.08 hectares and also in S.No.2/2C measuring 0.09.08 hectares at Kudankulam village. According to the plaintiff, the defendants 4 and 5 /the appellants herein without the knowledge of the plaintiff had erected the electricity poles in his land i.e., in the above said Survey Number Property at Kudangulam which was objected to by the plaintiff through his notice dated 23.04.2004 and 28.04.2004 to the defendants 1, 2 and 3 respectively. Since the plaintiff is a practicing advocate at Tirunelveli which is about 60 kms away from the place of occurrence, he came to know about the installation of the electrical post in Survey Number property at Kudankulam only in the month of April 2004. On enquiry, he came to know that the electrical poles were installed in the month of February 2004 itself. Since the representations made by the Plaintiff to the defendants proved futile, he had approached the Court.

2. The defendants 1 to 3 in the joint written statement in O.S.No.384 of 2004 would contend that the third defendant after purchasing the land, had handed over the same to the first and the second defendants. The first defendant purchased the property in which the Wind Mill was erected by the third defendant under a valid sale deed. The first defendant got no objection certificate for installation of wind mill and electric genearation on application to the defendants 4 and 5. The defendants 4 and 5 after perusing the records making a spot inspection and have accorded sanction and accordingly, the electric poles were erected and electric wires are drawn as per the Departmental norms. The electric poles and the stay wires were erected by the defendants 4 and 5 and they are in exclusive possession and control. The defendants 1 to 3 are unnecessary parties to the suit and they have no control over the defendants 4 and 5.

3. The defendants 4 and 5 have filed a joint written statement contending that the electric poles were erected during the month of February 2004 but the suit was filed belatedly. The plaintiff was allowed to erect the poles at the first instance and it is shown from the plaintiffs act of approach to the defendants 1 to 3 several times even after the completion of erection of poles. The plaintiff has filed the suit with a huge delay after the misunderstanding developed in due course between them. The erection of poles and wires are the part and parcel of the sanctioned project of the Tamilnadu Electricity Board as per Section 42 of Electric Supply Act r/w 12 of the Indian Electricity Act. As per the act, the Department need not obtain previous permission from the owner of the land in erecting the electric poles. The defendants act is approved by the Madras High Courts decision reported in 2001 LW 556 and AIR 1999 MAD 365. The action of the Boards is in their interest of public to have undisturbed power supply, and hence the Board cannot be prevented by injunction. There is no cause of action. Hence, the suit is liable to be dismissed.

4. The sixth defendant in his written statement would contend that as per the partition deed, the plaintiff is the owner of the plaint schedule property.

S.A.No.513 of 2007:-

5. The defendants 4 and 5 in O.S.No.406 of 2004 who had lost their defence before the Courts below are the appellants herein. According to the plaintiff, he is the owner of the Survey Number 2/2 along with his son sixth defendant measuring 6.52.08 acres in Survey No.2/2A and 0.09.08 hectares in Survey No.2/2C. The plaintiff is


































Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top