2011 Supreme(Mad) 4288
High Court Of Madras
V.Dhanapalan J.
K.Veerasamy - Appellant
Versus
Secretary To Government, Home (Police-Xix) Department, Fort St.George, Chennai – Respondent
W.P.NO.2402 OF 2008 and M.P.Nos.1 to 3 of 2008
Decided On : Oct 21,2011
Subject
ATTACHMENT - INTERIM ATTACHMENT
Act Referred
Headnote
Result : Writ Petition dismissed.
Kalyanasundaram, A.F.Diniz, L.P.Shanmughasundaram
( 1. ) THE petitioner has challenged the proceedings of the first respondent passed under Section 3 of the TNPID Act, 1997 in G.O.Ms.No.1469-Home Police-XIX, dated 17.10.2007 as well as the consequential proceedings of the Tahsildar, Palani, dated 21.01.2008 in Na.Ka.No.30247/07 in and by which, interim order of attachment was passed under Section 3 of the Tamil Nadu Protection of Interest of Depositors in Financial Establishment Act, 1997 (hereinafter referred to as 'TNPID Act') attaching the properties of the petitioner and others and possession of the said properties was taken over.
( 2. ) THE brief facts, necessary for disposal of the writ petition, can be stated as under:
2.1. THE petitioner along with his mother and friends, Thangaraj and Kanakaraj, started a partnership concern in the name and style, 'Sri Kandiamman Finance' at Coimbatore. THE business of the said financial establishment is, to receive money from the public and lend the same to the public for interest and earning a profit for the establishment. According to the petitioner, after establishment of the institution, they collected deposits from the public and paid interest upto 11 lakhs. While so, one B.Indrani, one of the depositors, lodged a complaint on 4.11.2004 against the petitioner and others before the Inspector of Police, Economic Offences-II/5th respondent herein, alleging that after having collected the deposits from her, the petitioner's institution had failed to return the same on maturity. After completion of the investigation, final report has been filed and it was taken on file as C.C.No.24 of 2005 by the Special Court for TNPID Act and the same is pending. Aggrieved by the same, the petitioner moved this Court by filing Crl.O.P.No.6690 of 2010 for quashing the criminal proceedings pending in C.C.No.24 of 2005 on the file of the Special Court for TNPID Act. By order, 3.7.2010, this Court granted interim stay of the proceedings. 2.2. Be that as it may, based on the above criminal case, the first respondent, invoking Section 3 of TNPID Act, 1997, passed Government Order in G.O.Ms.No.1469, Home (Police-XIX) Department, dated 17.10.2007 ordering interim attachment of the properties of the partnership firm and transferring the control over the said properties to the second respondent. Pursuant to the said G.O., the second respondent instructed the 3rd and 4th respondents to take possession of the properties.
THEreafter, the 4th respondent issued notice in Na.Ka.No.30247/2007, dated 21.1.2008, taking possession of the properties of the petitioner and others. Aggrieved by the same, the petitioner has come forward with the present writ petition.
( 3. ) THE respondents have filed a counter affidavit, inter alia, stating that on 4.11.2004, one Tmt.P.Indrani, W/o Bhaskaran, gave a complaint to the 5th respondent, alleging that a sum of Rs.16,00,000/- deposited in the names of her daughter and husband, was not repaid by the petitioner. Based on the said complaint, the 5th respondent registered a case in Crime No.9 of 2004 under Section 5 of TNPID Act.
3.1. According to the respondents, during the investigation, it was found that the partners of the defaulted financial establishment, had received a sum of Rs.25,30,000/- as deposits from the public and with accrued interest, they are liable to pay a total sum of Rs.38,57,700/-. After receipt of the deposits, in the year 2002, the said financial establishment was closed without repaying the deposited amounts to the depositors. THEreafter, the 5th respondent filed a charge sheet before the Special Court for TNPID Act, Chennai, which was taken on file as C.C.No.24 of 2005. THE concerned Investigating Officer identified the properties owned by the partners of the said defaulted financial establishment and sent proposals to the Government through the Inspector General of Police, Economic Offences Wing II, Chennai for issuing orders of ad-interim attachment of the said properties. On receipt of the said