SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2013 Supreme(Mad) 4189

High Court of Judicature at Madras
M. VENUGOPAL, J.
M. Prabharan & Others
Versus
The Superintending Engineer Salem & Another
W.P. No. 22851 of 2012
Decided On : 20-12-2013

Advocates:
Advocate Appeared:
For the Petitioners:S. Doraisamy, Advocate.
For the Respondents: P.R. Dhilip Kumar, Standing counsel for TNEB.

The main legal point established is that the orders of the Inspector of Labour under the Tamil Nadu Establishments Act must be followed by the Respondents, and failure to do so can lead to interference by the Court.

Headnote:

Writ of Certiorarified Mandamus - Workmen's Permanent Status - Tamil Nadu Establishments (Conferment of Permanent Status to Workmen) Act (46 of 1981) - Section 3, Section 12(3) of Industrial Disputes Act, 1947 - Section 3, Section 4, Section 5 of Tamil Nadu Industrial Establishments (Conferment of Permanent Status to Workmen) Act, 1981

Fact of the Case:

The Petitioners sought permanent status as they had worked for more than 480 days in 24 months. The Inspector of Labour, Salem, directed the First Respondent to confer permanent status, but no action was taken. The Second Respondent rejected the Petitioners' request citing Section 12(3) settlement under the Industrial Disputes Act, 1947.

Finding of the Court:

The Court found that the Second Respondent did not consider the order of the Inspector of Labour, Salem, leading to a miscarriage of justice. The impugned order was set aside, and the Respondents were directed to consider and pass appropriate orders in line with the Inspector's order.

Issues: The issues revolved around the Petitioners' entitlement to permanent status under the Tamil Nadu Establishments Act and the failure of the Second Respondent to consider the Inspector's order.

Ratio Decidendi: The Court held that the Respondents were bound to follow the orders of the Inspector of Labour, Salem, and set aside the impugned order due to legal infirmities.

Final Decision: The Writ Petition was allowed, and the impugned order was set aside. The Respondents were directed to consider and pass appropriate orders in line with the Inspector's order within six weeks.

JUDGMENT

1. The Petitioners have preferred the instant Writ of Certiorarified Mandamus praying for an issuance of an order by this Court, in calling for the records relating to the proceedings of the Respondents passed in Letter No.064770/361/G.65/G.651/2012-3 dated 25.06.2012 on the file of the Second Respondent/Chief Engineer (Personnel), Tamil Nadu Electricity Board, Chennai and to quash the same. Further, the Petitioners have sought for passing of an order by this Court in directing the Respondents to implement the orders of the Inspector of Labour, Salem dated 22.10.2010 in Na.Ka.Aa.3665/2008 by confirming them as regular employees of the Respondents.

2. The Writ Petition Facts:-

According to the Petitioners, they are working as Field Helpers in the Respondent/Board. They are engaged by the First Respondent/ Superintending Engineer, General Construction Circle, Tamil Nadu Electricity Board, Udayapatti, Salem-16 for executing cable laying, concrete laying, digging and erection of polls and allied works. The First Respondent is an Industrial Establishment as defined by the Tamil Nadu Establishments (Conferment of Permanent Status to Workmen) Act (46 of 1981) which is applicable to the First Respondent.

3. The Petitioners have not been made permanent and since they have been working for more than 480 days in a period of 24 calendar months they are entitled to be made permanent. By applying Section 3 of the Tamil Nadu Establishments (Conferment of Permanent Status to Workmen) Act (46 of 1981), they preferred an application to the Inspector of Labour, Salem praying for passing of an order in directing the First Respondent to absorb them as regular employees of the Respondent/Electricity Board. After contest, the Inspector of Labour, Salem by means of an order dated 22.10.2010 in Na.Ka.Aa.3665/2008 directed the First Respondent to confer the permanent status to the Petitioners, inasmuch as they have been working for more than 480 days in a period of two years.

4. It is the stand of the Petitioners that the order of the Inspector of Labour, Salem dated 22.10.2010 was communicated to the First Respondent. However, no orders were passed and the Petitioners made a request to the Second Respondent on 15.11.2010 praying for issuance of direction to the First Respondent to absorb them as regular employees on the basis of the order of the Inspector of Labour, Salem dated 22.10.2010. However, no steps were taken by the Second Respondent.

5. Consequently, the Petitioners were perforced to project the Writ Petition in W.P.No.25290 of 2011 praying for passing of an order by this Court in directing the First Respondent to implement the order of the Inspector of Labour, Salem dated 22.10.2010 in Na.Ka.Aa.3665/2008 based on their Representations dated 15.11.2010 by confirming them as regular employees of the Board. This Court passed an order on 01.11.2011 directing the Second Respondent/Chief Engineer (Personnel), Tamil Nadu Electricity Board, Chennai to consider and pass orders on their Representation dated 15.11.2010 within a period of eight weeks.

6. Meanwhile, the First Respondent/ Superintending Engineer, General Construction Circle, Tamil Nadu Electricity Board, Udayapatti, Salem-16 challenged the order of Inspector of Labour, Salem dated 22.10.2010 in W.P.No.27785 of 2010 and this Court on 31.03.2011 dismissed the said Writ Petition.

7. The Petitioners' contentions:-

The Learned counsel for the Petitioners urges before this Court that the impugned order dated 25.06.2012 (signed on 26.06.2012) passed by the Second Respondent is illegal and arbitrary one. Moreover, it is against the spirit of the order passed by this Court in the decision reported in 2009 (4) MLJ 472 [The Superintending Engineer, Nagapattinam & Others Vs. The Inspector of Labour & Others].

8. The forceful argument of the Petitioners is that they are seeking regularisation only on the basis that they are continuously working in the Respondent/Electricity Board for more than 480 day





































Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top