2015 Supreme(Mad) 1433
HIGH COURT OF JUDICATURE AT MADRAS
R. MALA, J.
N. Antony & Another - Petitioners
Versus
State rep. by Inspector of Police - Respondent
Criminal Appeal Nos. 176 & 302 of 2004
Decided On : 25-03-2015
Act Referred
INDIAN PENAL CODE : S.420, S.511, S.468, S.471, S.120(b)
PREVENTION OF CORRUPTION ACT : S.13(1)(d), S.13(2)
Headnote
Sanction - Criminal Appeals - 120B, 420, 511 IPC and Section 13(1)(d) of P.C.Act, 1988 - The judgment of conviction and sentence dated 04.02.2004 made in C.C.No.221 of 1997 on the file of the learned Principal Special Judge for CBI cases, Chennai - The prosecution has miserably failed to prove that the appellants/A1 and A2 are guilty for the offences beyond all reasonable doubt - The benefit of doubt is given in favour of the appellants/A1 and A2 and they are acquitted from the charges levelled against them - The judgment of conviction and sentence passed by the Special Court is hereby set aside.
Fact of the Case:
The case involved the conviction and sentencing of A1 and A2 for offences under Section 120B read with 420, 511 IPC and Section 13(1)(d) of P.C.Act, 1988. The prosecution alleged that A1 and A2 conspired to cheat the Madras Port Trust by submitting forged documents and accepting materials that were not in accordance with the specifications.
Finding of the Court:
The prosecution failed to prove the guilt of the appellants beyond all reasonable doubt. The benefit of doubt was given in favor of the appellants, and they were acquitted from the charges levelled against them. The judgment of conviction and sentence passed by the Special Court was set aside.
Issues: The issues revolved around the validity of the sanction accorded by the sanctioning authority, the evidence of forging signatures, and the failure of the prosecution to prove the guilt of the appellants beyond all reasonable doubt.
Ratio Decidendi: The sanctioning authority did not apply his mind while according sanction, which vitiates the entire case of prosecution. Additionally, there was no evidence to show that A1 forged the signatures of his higher officials. The prosecution failed to prove the guilt of the appellants beyond all reasonable doubt.
Final Decision: The Criminal Appeals were allowed, and the judgment of conviction and sentence was set aside. The appellants/A1 and A2 were acquitted from the charges levelled against them, and they were set free. The fine amounts paid by the appellants were ordered to be refunded to them, and the bail bond executed by the appellants/A1 and A2 was cancelled.
For the Appellants:R. Shanmugasundaram, Senior Counsel for S. Anbalagan, M. Nirmal Kunal, P.R. Gowthaman, Advocates.
For the Respondent: K. Srinivasn, Special Public Prosecutor (CBI cases).
1. The Criminal Appeals arise out of the judgment of conviction and sentence dated 04.02.2004 made in C.C.No.221 of 1997 on the file of the learned Principal Special Judge for CBI cases, Chennai, whereby the accused 1 and 2 were convicted and sentenced as follows:
| Accused | Conviction for Offence under Section | Sentence |
| A1 and A2 | 120B read with 420, 511 IPC and Section 13(1)(d) of P.C.Act, 1988 | To undergo one year rigorous imprisonment each and to pay a fine of Rs.1,000/- each in default to undergo three months rigorous imprisonment each. |
| A1 and A2 | 420 IPC | To undergo one year rigorous imprisonment each and to pay a fine of Rs.1,000/- each in default to undergo three months rigorous imprisonment each. |
| A1 and A2 | 420 read with 511 IPC | To undergo one year rigorous imprisonment each and to pay a fine of Rs.1,000/- each in default to undergo three months rigorous imprisonment each. |
| A1 | 468 IPC | To undergo one year rigorous imprisonment and to pay a fine of Rs.1,000/- in default to undergo three months rigorous imprisonment. |
| A1 | 468 IPC | To undergo one year rigorous imprisonment and to pay a fine of Rs.1,000/- in default to undergo three months rigorous imprisonment. |
| A1 | 471 (two counts) | To undergo one year rigorous imprisonment and to pay a fine of Rs.1,000/- in each count in default to undergo three months rigorous imprisonment in each count. |
| A1 | 13(2) read with 13(1)(d) of P.C.Act | To undergo one year rigorous imprisonment and to pay a fine of Rs.1,000/- in default to undergo three months rigorous imprisonment. |
The sentences are ordered to be run concurrently.
2. For the sake of convenience, the appellants herein are referred to as A1 and A2.
3. The case of the prosecution is as follows:
(i) P.W.1/Durai singh is working as Executive Engineer in the main office at Chennai Port Trust, Area 1, 2 and 3 are under his control. Area 1 and 2 are looked after A1/Assistant Engineer, Area 3 is looked after by P.W.3/Mathivanan/Assistant Engineer. A2 is the supplier to Madras Port Trust. P.W.3 and Area 3 Supervisor namely, P.W.12/Mohan Mani gave an indent for 15 numbers of slew motor couplings which was signed by him and sent to the stores for purchase along with drawings; After due compliance of the procedures involved in respect of materials to be purchased and on receipt of materials, the stores department sent Ex.P1 inspection note. As per Ex.P1, P.W.8/Samuel, P.W.12 and P.W.3 inspected the materials and made an endorsement stating that the materials are not as per indent and thus the materials were rejected and they were returned to R and C Section through internal gate pass prepared by P.W.12. But P.W.8/Mechanic informed him that the rejected materials were re-accepted by A1 by making an endorsement in Ex.P2 small acceptance memo book that the said items of materials were reinspected by him and found that they are as per Port Trust drawing. The endorsement is Ex.P3 and was signed by A1. According to P.W.1, after his personal inspection, he issued a fresh rejected memo Ex.P5 on 11.12.1995 itself as the materials were not as per the drawings of Port Trust and handed over Ex.P5 to one Aiyasamy, Assistant Controller of Stores and his signature is not available in Ex.P4.
(ii) P.W.1 further deposed that Ex.P6 is the indent dated 04.11.1994 prepared in Area 2 for 20 sets of upper guide rollers with shaft and 40 sets of bottom guide rollers and signed by him and A1. EX.P7 is the purchase order dated 03.08.1995 to their suppliers M/S.Sterling Engineering Enterprises and the concerned materials to his knowledge were not supplied by the supplier.
(iii) P.W.2/Arumuga Perumal, Supervisor, Grade-1 in Area 2, deposed that indent and purchase orders are meant for Area 2 and during that period, Area 1 and 2 were under the co