IN THE HIGH COURT OF JUDICATURE AT MADRAS
M.M. SUNDRESH, N. ANAND VENKATESH, JJ.
M/s SEI Adhavan Power Private Limited & Anr. - Appellants
Vs.
M/s Jinneng Clean Energy Technology Limited & Ors. - Respondents
Original Side Appeal Nos. 170 to 175, 206 to 210 of 2018; C.M.P. Nos. 9048 to 9053 & 10304 to 10308 of 2018
Decided On : 23-07-2018
Arbitration and Conciliation Act, 1996 - Section 45, 9 - International Chamber of Commerce - Pending payment - Contracts executed - Sake of brevity - appellants and respondent No.2 constitute a single Economic Entity namely Sun Edison Group of Companies along with Edison Energy Holding (Singapore) Private Limited (Respondent No.2) - Appellant No.1 is an Indian Company involving itself process of constructing a 50 MW AC power plant referred as project . M/s Sun Edison Energy Holding (Singapore) Private Limited (Respondent No.2) was holding 99.99% of the aggregate equity capital in the appellant No.1. The appellant No.1 had engaged the appellant No.2 as the contractor to provide certain construction related services qua the Project. The appellant No.2, in turn, entered into a sub contract qua supply of modules to the respondent No.1 in pursuant to the mutually agreed contracts executed vide purchase orders issued by respondent No.2 - M/s Sun Edison Energy Holding (Singapore) Private Limited in favour of respondent No.1. – Held, Court do not propose to go into the same for the reason that even assuming the same can sustain in the eye of law, the appeals as against the other applications are certainly maintainable. Secondly, invoking Section 45 of the Act 26 of 1996 and the order passed therein are consequential. To be noted, the respondent No.1 has already initiated the process by invoking Clause 9 of the undertaking before the respondent No.3 - There is nothing wrong in directing appellants to participate in the proceedings before the Respondent No.3. This is, even assuming that the application under 45 is not maintainable. The learned single Judge has rightly took into consideration of the undertaking given and its effect on the appellants - Appeals is dismissed.
M.M. Sundresh, J.
As all these original side appeals filed by the appellant No.2 were disposed of by the learned single Judge through a common order involving same fact and law, we propose to do the same. For the sake of brevity, the appellant in O.S.A. Nos.170 to 175 of 2018 is taken as appellant No.1 and the appellant in O.S.A. Nos.206 to 210 of 2018 is taken as appellant No.2. The respondents are accordingly arrayed as such.
2. Heard Mr. R. Venkatavaradan for Mr. V. Srikanth, learned counsel appearing for the appellant in OSA. Nos.170 to 175 of 2018 and Mr. Vijay Narayan, learned Advocate General, Assisted by M/s Shubharanjani Ananth, learned counsel appearing for the appellant in OSA. Nos. 206 to 210 of 2018 and Mr. Sathish parasaran, learned Senior Counsel assisted by M/s Priyanka Shetty for Mr. P. Giridharan, Mr. Dominic David, Mr. S. Santhosh and Mr. H. Siddarth, learned counsel appearing for the first respondent in all the appeals and perused the written submissions filed on 12.07.2018.
3. Facts in brief
3.1. The appellants and respondent No.2 constitute a single Economic Entity namely Sun Edison Group of Companies along with M/s Sun Edison Energy Holding (Singapore) Private Limited (Respondent No.2). The appellant No.1 is an Indian Company involving itself in the process of constructing a 50 MW AC power plant at Virudhunagar Village, Tamil Nadu referred as project . M/s Sun Edison Energy Holding (Singapore) Private Limited (Respondent No.2) was holding 99.99% of the aggregate equity capital in the appellant No.1. The appellant No.1 had engaged the appellant No.2 as the contractor to provide certain construction related services qua the Project. The appellant No.2, in turn, entered into a sub contract qua supply of modules to the respondent No.1 in pursuant to the mutually agreed contracts executed vide purchase orders issued by respondent No.2 - M/s Sun Edison Energy Holding (Singapore) Private Limited in favour of respondent No.1. The respondent No.1 raised certain invoices which were pending payment from the respondent No.2 with the appellant No.2. Thus, the appellants and the respondent No.2 are intrinsically connected to each other.
3.2. Under those circumstances, the respondent No.2 executed a Non Disposal Undertaking in favour of the respondent No.1. The facts narrated above were reiterated in the aforesaid document executed on 17.03.2016. This Non Disposal Undertaking was with respect to the shares held by the respondent No.2 with the appellant No.1. This document was prepared by one Mr. Pasupathy Gopalan being the President of respondent No.2. Incidentally, he controlled all the operations of the appellant No.1 as well.
3.3. In the aforesaid document, the respondent No.1 was referred as “Sun Edison”, the respondent No.2 as the “Contractor”, the appellant No.1 as the “company” and the appellant No.2 as the “client”.
3.4. While defining invoices, it was made clear that they mean, the invoices issued pursuant to the sub contract agreements and others added to the Annexure by mutual agreement by appellant No.2 and respondents 1 and 2. The payment obligation was defined as that of the appellant No.2 to the respondent No.1 qua the invoices raised.
3.5. Accordingly, the respondent No.2 gave an undertaking, which shall stand valid until the complete discharge of the Payment Obligations by the appellant No.2, to hold and retain atleast 24% of the equity in the appellant No.1 company. Thus, without prior approval of the respondent No.1 and until the complete and full discharge of the payment obligations, there shall not be any encumbrance by way of a transfer etc. This undertaking was meant to be terminated automatically upon receipt of the complete payment of the invoices by appellant No.2 or the respondent No.2 to the respondent No.1.
3.6. The appellants are functioning from the same office. All the group of companies belonging to the Sun Edison correspond through the same E-mail ID. The respondent No.2 as per the un
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.