2019 Supreme(Mad) 2177
IN THE HIGH COURT OF JUDICATURE AT MADRAS
SENTHILKUMAR RAMAMOORTHY, J.
M/s. Indian Oil Corporation Ltd, Rep. by its Deputy General Manager (LPG), Tamil Nadu State Office, Chennai - Petitioner
Versus
M/s. Fabtech Works & Constructions & Another - Respondents
O.P. No. 485 of 2014
Decided On : 08-11-2019
Subject
Contract Disputes - PRICE ADJUSTMENT
Act Referred
CONTRACT ACT : S.74
Headnote
Arbitration and Conciliation Act, 1996 - Section 34 – Claim of compensation - Evidences that the Contract - It is also admitted position that Petitioner made deductions from running account bills of first Respondent - Such deductions were made from amounts due and payable towards making said deductions, an aggregate sum which constitutes total lump sum contract price, was deducted - Therefore a dispute arose between the parties and the said dispute was referred to arbitration - In Arbitration Proceedings first Respondent herein claimed deducted sum of a further sum towards expenses incurred for commissioning work along with interest thereon - Other claims, such as a sum of towards loss of reputation and goodwill were also made and in aggregate, a sum of was claimed – Held, From the above, it is clear that the price adjustment clause is intended to provide compensation for loss of business due to delay in completion of work - In effect, it is stipulated compensation for delay that is attributable to the contractor - In this connection, it may be further noted that this is not an incentive-based clause whereby contractor could receive additional payment for accelerated completion and in converse situation should provide a discount in the event of delay - On other hand it is clearly a breach-based compensation clause - Once there is a contractual stipulation by way of compensation for delay notwithstanding terminology or label used to describe it and the stipulation in clause contract that it is not by way of liquidated damages or penalty, it amounts to a stipulation by way of compensation as per Section 74 of Contract Act - In this regard, in Dunlop Pneumatic Company Limited New Garage and Motor Company Limited Dunlop Pneumatic case - House of Lords held, in speech of Lord Dunedin, at page 86 of the Report, that "though the parties to a contract who use the words penalty or liquidated damages may prima facie be supposed to mean what they say yet expression used is not conclusive - Court must find out whether the payment stipulated is in truth a penalty or liquidated damages law in India, is the same on this subject - As stated earlier Section 74 of the Contract Act does not refer specifically to liquidated damages. On the other hand, it refers to a stipulation by way of compensation - Therefore Clause 4.4 of GCC would qualify as a stipulation by way of compensation - Once it qualifies as a stipulation by way of compensation, it became necessary for the Petitioner to prove that loss was incurred as a result of breach, although it may not be necessary to prove the exact quantum of loss, if it is difficult or impossible to prove the same - Petitioner cannot circumvent legal regime governing the imposition of liquidated damages merely by using label price adjustment - Therefore, in admitted absence of proof of factum of loss, it would be an sine scenario and the Petitioner is not entitled to compensation by way of price adjustment – Therefore Court do not find any reason to interfere with Arbitral Award – Petition dismissed
For the Petitioner:M/s. Mohammed Fayaz Ali, Advocates
For the Respondents:M/s. Gowtham Kumar, Advocates
JUDGMENT :
(Prayer: Original Petition is filed under Section 34 of the Arbitration and Conciliation Act, 1996 to set aside the Award dated 15.05.2014 passed by the 2nd Respondent herein in the un-numbered Arbitration Case.)
1. The respondent in the Arbitration is the Petitioner herein. The dispute between the parties arises out of a contract for the supply of steel plates, fabrication, erection and commissioning of 3X150 T capacity mounded type pressure vessels for LPG storage with cathodic protection at the LPG Bottling plant of the Petitioner at Illayangudi, Tamil Nadu. A letter of intent dated 27.11.2007 was issued in favour of the first Respondent in relation to the above mentioned work at the lump sum price of Rs.4,68,45,000/- inclusive of all taxes and duties. The entire work was required to be completed within a period of 12 months from the date of handing over of the site. Pursuant to the letter of intent, a detailed work order was issued to the first Respondent. The admitted position is that the site was handed over on 10.12.2007. Thereafter, the execution of work is stated to have been delayed by various factors such as delay in approval of designs and drawings by the Third Party Inspection Agency, namely Projects and Development India Limited(PDIL), changes in the orientation of the mounds which necessitated revision in the designs and drawings, heavy rainfall, delay in supply of steel, etc. According to the first Respondent, the work was completed on 26.12.2009, as certified by PDIL, whereas, according to the Petitioner, the work was completed on 30.04.2010.
2. It is also the admitted position that the Petitioner made deductions from the running account bills of the first Respondent. Such deductions were made from amounts due and payable towards RA Bill No.3 dated 28.03.2009, RA Bill No.4 dated 02.05.2009, RA Bill No.5 dated 29.10.2009, RA Bill No.6 dated 15.11.2009, RA Bill No.7 dated 04.02.2010, RA Bill No.8 dated 23.06.2010 and RA Bill No.9 dated 28.09.2010. By making the said deductions, an aggregate sum of Rs.46,84,500/-, which constitutes 10% of the total lump sum contract price, was deducted. Therefore, a dispute arose between the parties and the said dispute was referred to arbitration. In the Arbitration Proceedings, the first Respondent herein claimed the deducted sum of Rs.46,84,500/- and a further sum of Rs.5,00,000/- towards expenses incurred for commissioning the work along with interest thereon. Other claims, such as a sum of Rs.93,69,000/- towards loss of reputation and goodwill, were also made and, in the aggregate, a sum of Rs.2,55,33,436/- was claimed. In the said Proceeding, the Petitioner filed an application under Section 16 of the Arbitration and Conciliation Act, 1996 (the Arbitration Act) challenging the jurisdiction of the Arbitral Tribunal and the said application was rejected by Order dated 04.07.2013. Thereafter, the Petitioner filed its reply statement before the Arbitral Tribunal, wherein it refuted the claims of the first Respondent herein and prayed that the said claims be rejected. The learned Arbitrator framed three issues by considering the pleadings of the parties. In substance, these issues are: 1) Whether the invocation of the price adjustment clause by the Petitioner herein is justifiable? 2) Whether the first Respondent herein committed a breach of Contract by delaying the completion of the project? and 3) Whether the first Respondent herein is entitled to the relief as claimed? Both parties adduced oral and documentary evidence: the first Respondent herein exhibited 18 documents as Exs.C-1 to C-18 and the Petitioner herein exhibited 13 documents as Exs.R1 to R-13. Upon consideration of the above, the learned Arbitrator by Arbitral Award dated 15.05.2014 (the Award) directed the Petitioner herein to pay a sum of Rs.46,84,500/- to the first Respondent herein immediately. The said Award is impugned in this Petition.
3. I heard the learned counsel for the Petitioner and the learned