2019 Supreme(Mad) 2342

IN THE HIGH COURT OF JUDICATURE AT MADRAS
SENTHILKUMAR RAMAMOORTHY, J.
M/s. Hindustan Steel Works Construction Limited – Petitioner
Versus
Government of Tamil Nadu, Rep. by its Project Director, Tamil Nadu Road Sector Project, Chennai & Others – Respondents
O.P. No. 309 of 2014
Decided On : 04-12-2019

Important Points

Court upheld rejection of claims based on interpretation of contractual clauses and factual findings, emphasizing limited scope for interference with Arbitral Award.

Subject

Arbitration Law - Contractual Interpretation and Award Enforcement

Act Referred

ARBITRATION AND CONCILIATION ACT : S.34

Headnote

Arbitration - Enhanced Periodical Maintenance of Government Roads - Arbitration and Conciliation Act, 1996, Section 34 - 10/2004-05 Agreement - Claim for escalation, loss of profits, compensation for idle men and machinery, interest, arbitration costs, and delay compensation - Award challenged - Court upheld rejection of claims based on interpretation of contractual clauses and factual findings

Fact of the Case:

Dispute arises from a contract for Enhanced Periodical Maintenance of Government Roads in Tuticorin District. Petitioner made 6 claims in Arbitration, but only claim No.4 was awarded. Petitioner challenged the Award.

Finding of the Court:

Court upheld rejection of most claims based on interpretation of contractual clauses and factual findings. Petitioner failed to establish entitlement to escalation, loss of profits, and compensation for idle men and machinery. Court found no grounds for interference with the Arbitral Award.

Issues: Interpretation of contractual clauses, entitlement to escalation, loss of profits, compensation for idle men and machinery, interest, arbitration costs, and delay compensation

Ratio Decidendi: Court's decision based on reasonable interpretation of relevant contractual clauses and factual findings. No grounds for interference with the Arbitral Award.

Final Decision: Petition to set aside the Award is dismissed. No costs.

Advocates Appeared:
For the Petitioner:N.C. Ramesh, Senior Counsel for M/s. C. Ramesh, Advocate.
For the Respondent: M. Sricharan Rangarajan, Spl. GP(CS).

JUDGMENT :

(Prayer: Original Petition is filed under Section 34 of the Arbitration and Conciliation Act, 1996 to set aside the Award dated 28.08.2009 passed by the Arbitrator.)

1. The claimant in the Arbitration is the Petitioner herein. The dispute arises out of a contract for the Enhanced Periodical Maintenance of Government Roads in Tuticorin District. Pursuant to the tender floated by the first Respondent, the work was awarded to the Petitioner. The Agreement No.10/2004-05 was executed on 21.07.2004 (the Agreement) and the scheduled date of completion of work was 23.09.2005. However, the admitted position is that the work was actually completed on 30.10.2006. In these facts and circumstances, claims were made with regard to escalation, idling etc. and the said dispute was referred to Arbitration. In the Arbitration, the Petitioner made 6 claims. The said claims were in respect of the following: a sum of Rs.2,17,23,456/- towards escalation in costs of materials and labour; a sum of Rs.1,86,38,923/- towards loss of profits and overheads; a sum of Rs.70,28,640 towards compensation for costs incurred on idle men and machinery; interest on overdue payments; costs of the Arbitration Proceedings; and compensation due to delay in issuance of the Project Authority Certificate. Based on the pleadings and documentary evidence, the Arbitral Tribunal pronounced the Arbitral Award dated 28.08.2009 (the Award) and rejected all the claims except claim No.4. With regard to claim No.4, a sum of Rs.13,25,994/- was awarded with interest thereon at 8% per annum from the date of the Award till the date of payment. The said Award is challenged by the Petitioner.

2. I heard the learned counsel for the Petitioner and the learned counsel for the Respondents. The learned counsel for the Petitioner submitted that the delay in completion of work was on account of delay in approving revised proposals and that this delayed the performance of work from 09.04.2005 to 09.01.2006. The other reasons for delay were the monsoon rains in October and November 2004 and October and November 2005, the delay in approval of the deletion proposal in August and September 2006 and the delay in issuing the Project Authority Certificate. Consequently, he submitted that the reasons for delay are not attributable to the Petitioner and that, therefore, the Petitioner was entitled to its escalation claim. He further submitted that the Petitioner had reported the deterioration in the road surface within a reasonable time as per Clause 31.5 of the Agreement.

3. As regards idling of men and machinery, the learned counsel submitted that the men and machinery of the Petitioner were kept idle from 09.04.2005 to 09.01.2006, which is the time taken for approval of the revised estimate by the first Respondent, and, therefore, the Petitioner is entitled to claim No.2 towards idling. In this connection, it was further submitted that the Arbitral Tribunal misconstrued Clause 28.5 of the Agreement so as to hold that the Petitioner had admitted that it would not make any claim for increase in costs. It was further submitted that the first Respondent delayed the issuance of the Project Authority Certificate for the purpose of enabling a waiver of excise duty and that the Petitioner incurred losses on that account. The learned counsel also submitted that the rejection of the claim of loss of profits and overheads is arbitrary and perverse and that the Arbitral Tribunal should have been adopted Hudson-s formula or any other accepted formula so as to determine the overheads and loss of profits claim. For all these reasons, the learned counsel submitted that the Arbitral Award is liable to be set aside.

4. In response and to the contrary, the learned counsel for the first Respondent submitted that the Agreement admittedly does not contain a price escalation clause. Instead, clause 47.2 stipulates that the prices included in the contract shall be deemed to include any increase or reduction in prices.

1
2
3
4
5
6
7
8
9
10
11