SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2021 Supreme(Mad) 1539

IN THE HIGH COURT OF MADRAS
R. SUBBIAH, C. SARAVANAN, JJ.
Transtonnelstroy-Afcons (JV) and Ors. – Appellants
Versus
Chennai Metro Rail Ltd. and Ors. – Respondents
Original Side Appeal Nos. 173, 174 of 2020, Cross Objection Nos. 36, 37 of 2020, Civil Miscellaneous Petition Nos. 8772, 8774, 8780 and 8782 of 2020
Decided On : 24-03-2021

Advocates:
Advocate Appeared:
For the Appellant :V. Raghavachari, G. Masilamani, Senior Counsel for D. Balaraman, Yashod Vardhan, Senior Counsel and P.H. Arvind Pandian, Senior Counsel/Addl. Advocate General assisted by S. Arjun Suresh
For the Respondents:Yashod Vardhan, Senior Counsel, P.H. Arvindh Pandiyan, Senior Counsel/Addl. Advocate General assisted by S. Arjun Suresh, V. Raghavachari, G. Masilamani, Senior Counsel for D. Balaraman and Srinath Sridevan

Headnote:

Arbitration and Conciliation Act 1966-Section 9(2),9(3),9,17-Invocation of Bank Guarantee should be strictly in accordance with the contract agreement. If it is not in consonance with the contract agreement, the invocation itself is bad. In this regard, the learned Senior Counsel invited the attention of this Court to Clause 5 of the Bank guarantee- the core or essence of the Bank gurantee is to indemnify the employer towards any liability or damages, resulting from any defect or shortcomings of the work undertaken by the contractor. Therefore, to "indemnify" is a condition to compensate or to make good the loss. While so, the employer must indicate a specific amount, either actual or estimated or expected loss/damages, as referred to in the Bank guarantee, which is one of the conditions precedent for invocation of the Bank Guarantees the validity of the BG must be for at least 28 days longer than the anticipated date of issue of the Taking Over Certificate- Core or essence of the BG is to indemnify the employer towards any liability or damages, resulting from any defect or shortcomings of the work undertaken by the contractor. Therefore, to "indemnify" is a condition to compensate or to make good the loss. While so, the employer must indicate a specific amount, either actual or estimated or expected loss/damages, as referred to in the BG, which is one of the conditions precedent for invocation of the Bank Guarantees- Held, Two underground tunneling contracts were awarded to the appellant(s) by the first respondent-CMRL. One relates to Corridor UAA-05 which pertains to construction of underground tunnelling the first respondent-CMRL sent a letter dated 06.07.2020 to the respective Banks to invoke the Bank Guarantees offered by the appellant(s). On coming to know about the attempt on the part of the first respondent-CMRL to invoke the Bank Guarantee, that too without specifying the amount corresponding to the proportionate alleged loss or damage, the appellant(s) filed O.A. Nos. 246 and 247 of 2020 before this Court. This Court granted an interim order. Even before the order passed by this Court was communicated, the Bank Guarantee was invoked in respect UAA-05. In respect of UAA-01, the amount was not paid to the first respondent-CMRL by the Bank from Anna Nagar East, Anna Nagar Tower and associated tunnels. The contract price is Rs. 1030,99,50,000/-. The other contract awarded to the appellant(s) for design and construction of underground stations are Washermanpet, Mannadi, High Court, Chennai Central and Egmore and associated tunnel work. The contract price was Rs. 1566,81,00,000/-. The award of the contracts are not disputed in these cases-As per Clause 4.2 of the GCC, the appellants have furnished performance Bank Guarantee, for 7.5% of the contract price in respect of UAE-05 performance BG for a sum of Rs. 77,36,250/- from Union Bank of India. In respect of UAA-01, the appellants have furnished performance Bank Guarantee of Rs. 117,51,07,500/- from IDBI Bank. In respect of UAA-05, after issuance of Taking Over Certificates, , as per Clause 4.2 of GCC read with CPA-7 and Clause 6 of BG, the first respondent reduced the BG to 2.5% from 7.5%. Thereafter, a revised performance BG dated 16.10.2018 for Rs. 25,77,48,750/- from Union Bank of India in favour of first respondent was issued with a validity was executed- So far as UAA-01 is concerned, the contract value was not reduced to 2.5% inspite of issuing Taking Over Certificate by the first respondent-CMRL-Now, both the projects covered under UAA-01 and UAA-05, have been put to public use. In other words, UAA-01 commenced commercial operations respectively and in respect of UAA-05, commercial operations commenced- The Bank Guarantees were invoked on the ground that several outstanding works left unattended and therefore, only a Partial Taking Over Certificate was issued in UAA-1 contract, with a list of balance works and snags. So far as UAA-05 contract is concerned, the Taking Over Certificate was issued, effective and on issuance of Taking Over Certificate, it was reduced from 7.5% to 2.5%, and the same is valid . But according to the appellant(s), the Bank Guarantees are not independent contracts and their invocation is subject to certain conditions. The invocation of Bank Guarantees depend on the underlying contract. Under such circumstances, as per Clause 4.2 of the GCC, the first respondent-CMRL ought to have notified the defects to the appellant(s) prior to invoking the Bank Guarantee, which has not been done in this case. But it is contended by the first respondent-CMRL that they have notified the defects through various correspondences-It is an independent contract, irrespective of the defects and shortcomings in execution of the work by the appellant(s), the first respondent-CMRL is entitled to invoke the Bank Guarantee. If it is not, the invocation of the Bank Guarantee depends upon the clauses contained in the underlying contract. But it should be borne in mind that the application was filed under Section 9 of the Arbitration and Conciliation Act, seeking interim protection pending the arbitration proceedings. In the instant case, the project was completed and it was put to public use. This is not a case as though the appellant(s) had abandoned the project or intended to rock the boat and made the first respondent-CMRL to complete the works left by the appellant by engaging another contractor. On the other hand, it is the case of the first respondent-CMRL that, though the appellant completed the work, there are some left over works and the same has to be completed by engaging a third party- Direct the parties to maintain "status-quo" as on date of this judgment, for a further period of 60 days from the date of receipt of a copy of this judgment, as far as the encashment of the respective Bank Guarantee(s) are concerned. The appellant(s) may therefore file appropriate application(s) before the Arbitral Tribunal under Section 17 of the Arbitration and Conciliation Act, 1996, for such interim measure as regards the invocation of the Bank Guarantee(s) is concerned. The amount which has already been transferred to the first respondent-CMRL by the Union Bank of India is concerned, we leave it to the parties to work out their remedies before the learned Arbitrator(s) in accordance with law- Court set aside’s the order and the Original Side Appeals are allowed to the extent indicated above. As a consequence of allowing of the Original Side Appeals, the Cross Objections are dismissed. No costs. Consequently, C.M.Ps. are closed- Appeal allowed.

JUDGMENT :

R. Subbiah, J.

1. Chennai Metro Rail has become one of the iconic symbols of the City of Chennai. It connects and/or transports people to various nerve-centres of the City. It is also considered as one of the important and convenient modes of transportation to ease traffic congestion in the City. It heralded a new mode of convenient transportation to the masses of City. Though it is operational for the past more than two years, the dispute between the contractor, who was awarded the contract for tunnelling, design and construction of Metro Railway Stations and Chennai Metro Rail, is yet to be settled. There were several arbitration proceedings pending between the contractor and Metro Rail. During the pendency of such arbitration proceedings, the present appeals and cross-objections are filed before us.

2. These Original Side Appeals have been filed as against the common order of dismissal, dated 14.08.2020 passed by the learned Single Judge in two separate applications filed by the appellants herein in O.A. Nos. 246 and 247 of 2020 under Section 9(ii)(d) of the Arbitration and Conciliation Act, for restraining the first respondent-M/s. Chennai Metro Rail Limited, from invoking and receiving the amounts from Bank Guarantee No. 49580IGL0074018, dated 16.10.2018 issued by the Union Bank of India for Rs. 25,77,48,750/- and Bank Guarantee No. 1000041BGP00943, dated 29.12.2010 issued by the IDBI Bank Limited, for Rs. 117,51,07,500/- or any part thereof, pending disposal of the Arbitration Proceedings under UAA-05 and UAA-01 Contracts, respectively.

3. The learned Single Judge, while dismissing O.A. Nos. 246 and 247 of 2020, had rejected the contention of the first respondent-Metro rail stating that the Original Applications filed by the appellants herein are not maintainable. As against such finding, Metro Rail Limited had filed Cross Objection Nos. 36 and 37 of 2020 respectively.

4. The brief facts which are necessary for disposal of the present appeals are as follows:

    (a) The appellant-M/s. Transtonnelstroy Afcons is a Joint Venture Company comprising M/s. Transtonnelstroy Limited, Moscow, Russia and M/s. Afcons Infrastructure Limited, Mumbai.

(b) The first respondent-M/s. Chennai Metro Rail Limited (hereinafter called as "CMRL"), awarded the work of design and construction of underground stations at Shenoy Nagar, Anna Nagar East, Anna Nagar Tower, Thirumangalam and associated tunnels-Contract No. UAE-05 to the appellant for a contract price of Rs. 1030,99,50,000/-. Pursuant to the same, a formal contract was entered into between the appellant and first respondent-CMRL on 31.01.2011 (hereinafter referred to UAA-05, for brevity), which relates to O.A. No. 246 of 2020, pertaining to O.S.A. No. 173 of 2020 had been filed.

(c) Similarly, the first respondent-CMRL awarded another work of Design and construction of underground station work at Washermenpet, Mannadi, High Court, Chennai Central and Egmore and Associated tunnels-Contract No. UAA-01, to the appellant for a contract price of Rs. 1566,81,00,000/- and pursuant to the same, a formal contract was entered into between the appellant and the first respondent-CMRL on 31.01.2011 (for short, "Contract No. UAA-01), which relates to O.A. No. 247 of 2020, pertaining to O.S.A. No. 174 of 2020 had been filed.

(d) As per Clause 4.2 of the General Conditions of Contract (GCC) read with Clause 7 of Conditions of Particular Application (CPA), the appellant-Company had furnished performance security by way of Bank Guarantee (BG). Insofar as Contract UAA-05 is concerned, the appellant-Company had furnished Bank Guarantee dated 30.12.2010 for Rs. 77,32,46,250/- (7.5% of underlying contract) from Union Bank of India, the second respondent in O.S.A. No. 173 of 2020. Similarly, insofar as Contract UAA-01 is concerned, the appellant-Company had furnished Bank Guarantee dated 29.12.2010 for Rs. 117,51,07,500/- (7.5% of underlying contract) from IDBI Bank Limited, the second respondent in O.S.A. No.

                          Click Here to Read the rest of this document
                          1
                          2
                          3
                          4
                          5
                          6
                          7
                          8
                          9
                          10
                          11
                          SupremeToday Portrait Ad
                          supreme today icon
                          logo-black

                          An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

                          Please visit our Training & Support
                          Center or Contact Us for assistance

                          qr

                          Scan Me!

                          India’s Legal research and Law Firm App, Download now!

                          For Daily Legal Updates, Join us on :

                          whatsapp-icon Back to top