SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2022 Supreme(Mad) 27

IN THE HIGH COURT OF JUDICATURE AT MADRAS
SENTHILKUMAR RAMAMOORTHY, J.
Pondicherry University, Puducherry - Appellant
Versus
Infoplus Technologies Pvt. Ltd., Chennai - Respondent
Arb. O.P. No. 332 of 2021 & A. No. 1699 of 2021
Decided On : 11-01-2022

Advocates Appeared:
For the Petitioner:P.H. Arvindh Pandian, M. Ravi, Advocates.
For the Respondent:Nellaiappan, Advocate.

Headnote:

Constitution of India, 1950 - Article 299 - Arbitration and Conciliation Act, 1996 - Section 34(2)(iv), 34 - Indian Contract Act, 1872 - Section 70 - Tender was floated by Petitioner for providing visual learning solutions for engineering graduates - Tender consisted of two parts, namely, a technical bid and financial bid. respondent was successful bidder and was awarded Firm Order - Whether Petitioner committed breach of Agreement - Whether Respondent is entitled to a sum towards same - Whether Respondent is entitled to other claims - Whether Respondent is entitled to interest - Whether such conclusion warrants interference, relevant clauses of Agreement should be noticed - Whether Respondent is entitled to amounts claimed in respect of 32 subjects which were delivered to Petitioner – Held, loss of profit claim is unlike other types of claim because it is a claim towards profit which aggrieved party could have earned but for breach committed by counter party - As a result of the nature of such claim, it cannot be proved by adducing evidence of actual loss - At best, a party making a claim for loss of profit could adduce evidence of profit margin which was reckoned while bidding for contract or profits earned from substantially similar contracts - However, even such evidence is of limited utility inasmuch as actual profit margin is impacted by several variables such as cost of inputs while contract is executed or even cost of human resources - Respondent also referred to several judgments of Hon'ble Supreme Court in cases to contend that loss of profit may be awarded even at 15 % of the value of un-executed work - Except said judgments were largely in context of construction contracts - Nonetheless, in view of nature of a claim for loss of profit, absence of evidence in respect thereof is not necessarily or always fatal to such claim - Considering following: Respondent had made a claim for undelivered but developed content for 85 subjects, which was rejected; Rs.13,34,000/- was deducted even towards two delivered subjects, which were held to be outside scope of Phase I; and Arbitral Tribunal only awarded 5% towards loss of profit on 120 subjects, court view that Award in this respect cannot be construed as patently illegal or contrary to public policy so as to justify interference under Section 34 of Arbitration Act – Original Petition dismissed.

JUDGMENT :

Prayer : This Petition has been filed under Section 34(2)(iv) of the Arbitration and Conciliation Act, 1996 praying to set aside the Award dated 16.06.2019 received on 17.06.2019 passed by the Arbitral Tribunal in the dispute arising out Contract Agreement dated 07.07.2015.

1. The respondent before the Arbitral Tribunal is the Petitioner herein. By this petition, the Petitioner assails the Arbitral Award dated June 17, 2019 (the Award) under Section 34 of the Arbitration and Conciliation Act, 1996 (the Arbitration Act).

2. A tender was floated by the Petitioner for providing visual elearning solutions for engineering graduates. The tender consisted of two parts, namely, a technical bid and financial bid. The respondent was the successful bidder and was awarded the Firm Order dated April 27, 2015. The Firm Order was to be implemented in two stages: the first stage involving design, development and delivery of e-learning solutions in DVD for 150 subjects at the rate of Rs.5.8 lakhs + taxes per subject; and the second stage involving implementation in the internet server of the Respondent at Rs.40/- + taxes per student per year and intranet servers installed at affiliated colleges at Rs.20/- + taxes per student per year.

3. Pursuant to the above mentioned Firm Order, after presentations were made by the Respondent before representatives of the Petitioner, an Agreement dated July 07, 2015 (the Agreement, Ex.C-4) was executed. The Agreement imposed an obligation on the Respondent to provide visual e-learning solutions for 150 subjects to students of the four year engineering degree programme. Shortly thereafter, the Respondent delivered visual e-learning solutions for 23 subjects in July 2015. Elearning solutions for a further 9 subjects were delivered in August 2015. In total, e-learning solutions for 32 subjects were delivered by the Respondent and received by the Petitioner. The Respondent also submitted an invoice dated August 12, 2015 for Rs.60,83,040/- (Ex.C-8) towards stage one of the delivery of 23 subjects at 40% of the total amount payable in such regard. Invoice dated December 21, 2015 was submitted a little later for a sum of Rs. 23,90,760/- (Ex.C-11) for the 9 subjects that were delivered in August 2015. Two further invoices, both dated March 24, 2017 for Rs.85,37,600/- and Rs.21,34,400/-(collectively Ex.C-11), respectively, were submitted towards the second installment of 40% and the third installment of 10%, respectively, for the above mentioned 32 subjects. All the above 4 invoices referenced Clause 6.2.1(d) of the Agreement. Thus, the Respondent submitted invoices for 90% of the price of e-learning solutions for 32 subjects.

4. Meanwhile, a meeting of the Committee for Development and Delivering of 3D Visual E-Learning Solutions For Undergraduate Engineering Programmes of the Affiliated Colleges of Pondicherry University (the Committee) was held on December 16, 2015. At such meeting, the Committee noted that the reports received for seven subjects indicated that “the materials had several defects and had scope for improvement.” As regards payment, the Committee recorded that it was informed that a recommendation had been made in the meeting of the principals held on June 25, 2015 to collect Rs.1000/- per student. At the next meeting of the Committee on December 29, 2015, the Committee reiterated that the report from the Coordinators indicated that the seven subjects, which were reviewed at the first level were not up to the acceptable level. As regards the other 16 subjects, it was recorded that the University has to identify subject experts. The Committee also decided to put on hold the request for receipt of materials for the second and fourth semester.

5. According to the Respondent, it developed e-learning solutions for a further 85 subjects at a price of Rs.4,93,00,000/-, which was computed and claimed in arbitration at the contractual price of Rs.5,80,000/- per subject. Thus, the Respondent asserted that

        Click Here to Read the rest of this document
        1
        2
        3
        4
        5
        6
        7
        8
        9
        10
        11
        SupremeToday Portrait Ad
        supreme today icon
        logo-black

        An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

        Please visit our Training & Support
        Center or Contact Us for assistance

        qr

        Scan Me!

        India’s Legal research and Law Firm App, Download now!

        For Daily Legal Updates, Join us on :

        whatsapp-icon Back to top