IN THE HIGH COURT OF JUDICATURE AT MADRAS
P.T. ASHA, J.
Mr.P.Mahalingam Civil Engineering Contractor 21 Lakshmipuram Main road Velachery, Chennai - Appellant
Vs.
The Superintending Engineer Public Works Department Building (Control & Maintenance) Circle Chepauk, Chennai - Respondents
A.S.No.107 of 2015
Decided On : 29-09-2021
Code of Civil Procedure, 1908 - Section 79, Order XXVII Rule 5(A) - Plaintiff has filed this suit for recovery of a sum of Rs.23,44,879/- together with interest at 12% per annum from date of plaint till date of realization - It is case of plaintiff that he had been awarded contract for constructing a new emergency operation theater for ante natal ward at Government Women and Children Hospital (IOG) - Value of contract was a sum of Rs.1,57,24,982/- and contractor was given nine months time for completing work and handing over site - Agreement was entered into between parties encapsulating terms of agreement – Trial court also held that plaintiff had not proved that a sum of Rs.1,60,000/- was due towards final bill - With regard to refund of EMD and SD, learned Judge relied on case of defendant that defects had not been cleared and held that plaintiff was not entitled to any relief and dismissed suit – Whether plaintiff is entitled to escalation of cost and has proved same - Whether plaintiff was entitled to final bill and refund of EMD and SD – Held, coming to issue of refund of amounts under head of escalation, terms of agreement does not contemplate payment of escalation cost - That apart, plaintiff had categorically stated that he shall not claim any extra rate during time of extension period - Having done so, plaintiff cannot now turn around and claim said amount - Finding of Court below that plaintiff is not entitled to escalation cost appears to be just and does not require any reconsideration by this Court - Plaintiff has submitted that he has set right all defects and submitted his claim - Though defendants have pleaded that defects have not been rectified there is no detail given as to defects still remain unattended - Plaintiff had been called upon to rectify defects as early as in year 2006 and he has also rectified defects - Best evidence, namely, Mbook has been kept away from Court and an adverse inference has to be drawn for its non-production - First Appeal partly allowed.
JUDGEMENT :
The unsuccessful plaintiff is the appellant before this Court, challenging the Judgment and Decree passed by the III Additional City Civil Judge, Chennai in O.S.No.8999 of 2010. The parties for the ease of understanding are referred to in the same litigative status as before the Trial Court.
2. The facts in brief which are necessary for considering the dispute on hand is herein below extracted.
Plaintiff's Case:
3. The plaintiff has filed this suit for recovery of a sum of Rs.23,44,879/- together with the interest at 12% per annum from the date of the plaint till the date of realization. It is the case of the plaintiff that he had been awarded the contract for constructing a new emergency operation theater for the ante natal ward at the Government Women and Children Hospital (IOG) Egmore. The value of the contract was a sum of Rs.1,57,24,982/- and the contractor was given nine months time for completing the work and handing over the site. The agreement dated 27.01.2004 was entered into between the parties encapsulating the terms of the agreement. In compliance with the terms of the agreement, the plaintiff had deposited a sum of Rs.5,98,000/- towards the Earnest Money Deposit (EMD) and Security Deposit (SD). The site was handed over on 10.03.2004 and therefore as per the terms of the agreement the plaintiff was to complete the construction on or before 09.12.2004.
4. It is the case of the plaintiff that when he had tendered, the cost of steel was in the range of Rs.19,000/- per metric tonne and consequently, he had quoted for the tender. Thereafter, the price of steel had increased to a sum of Rs.28,000/- per metric tonne which further escalated to a sum of Rs.29,300/- which in effect increased the cost by 47%. He would submit that as per clause 5(3) of additional condition 1 and 14(vii) of the agreement where materials are supplied by the Department and price escalates then additional cost would be added. He would therefore submit that the reverse should be applied even in the case of the contractors.
5. It is his specific case that the demand for being compensated for the rise in price did not amount to an escalation of price but only a variation on account of the rising cost which was beyond the control of the plaintiff. The plaintiff would therefore submit that as per the agreement the quantity of steel that was to be supplied was 109 metric tonnes, which was concluded at the rate of Rs.19,000/- per metric tonne. The cost of steel fabrication was Rs.27,23,150/- for 109 metric tonnes. However, on account of the increase in price of steel to a sum of Rs.29,300/- per metric tonne, the differential cost (the increase) for 109 metric tonnes worked out to a sum of Rs.12,79,879/- and adding the cost of fabrication the differential value worked out to a sum of Rs.16,99,879/. This factor was brought to the notice of the defendants vide the plaintiff's letter dated 10.09.2004.
6. However, the defendants by their reply dated 01.10.2004 cited chapter IV of the Transparency of Tender Act, 2000, to state that the price escalation would apply only to the contract which exceeded a period of eighteen months. In the instant case, the period was only nine months. This prompted the plaintiff to issue a legal notice dated 19.05.2006 stating that the Act would not apply to the facts of the instant case as admittedly the price of the steel has increased and the terms could not have been incorporated into the original contract.
7. He would also submit that there was about a three month gap between the date of acceptance of the tender, its communication, the signing of the agreement and the handing over of the site. Therefore, he would contend that the defendants are liable to pay a sum of Rs.16,99,879/- towards the differential cost and they were also liable to refund a sum of Rs.5,85,000/- towards deposit and a sum of Rs.1,60,000/- towards the final bill together with the interest at 12% on the said amount. Since the payments were not made,
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.