SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

1996 Supreme(Ori) 144

High Court Of Orissa
P. C. NAIK
UNION OF INDIA - Appellant
Versus
STEEL AUTHORITY OF INDIA LIMITED - Respondent
MISC. APPEAL 172  Of  1993
Decided On : 09/17/1996

Advocates Appeared:
A.DEO, A.K.PARIDA, B.S.TRIPATHY, D.MISHRA, K.B.KAR, P.PANDEY, R.K.DAS, R.K.MOHAPATRA, R.N.NAIK, S.K.Nayak, S.K.SWAIN, U.K.Samal

A claim for refund of differential freight arising from a breach of contract of carriage by the Railway Administration is not a claim for refund of overcharge and does not require a notice under Section 78-B of the Indian Railways Act, 1890.

Headnote:

RAILWAY CLAIMS TRIBUNAL ACT - SECTION 23(1) - APPEAL - INDIAN RAILWAYS ACT, 1890 - SECTIONS 27-A, 28, 72, 76-A, 78-B - CONTRACT ACT, 1872 - SECTION 72 - LIMITATION ACT, 1963 - ARTICLES 55, 113 - RAILWAY ADMINISTRATION - RATIONALISATION SCHEME - CARRIAGE OF GOODS - FREIGHT CHARGES - DEVIATION OF ROUTE - REFUND OF DIFFERENTIAL FREIGHT - NOTICE UNDER SECTION 78-B - MISTAKE - LIMITATION - UNJUST ENRICHMENT - LAWYERS' FEE.

Fact of the Case:

The plaintiff, a steel plant, imported coal at Visakhapatnam Port for carriage to its plant at Rourkela. The shortest route was via Vijaynagaram-Titlagarh-Sambalpur-Jharsuguda-Rourkela covering a distance of 667 kilometers, but due to a rationalisation scheme, the coal had to be carried by the longer route via Vijaynagaram-Khurda Road-Kharagpur-Tatanagar-Chakradharpur-Rourkela covering a distance of 1082 kilometers. The plaintiff paid freight for the longer route, but later discovered that for a period of about nine months, the coal was actually carried by the shorter route. The plaintiff claimed a refund of the differential freight, but the Railway Administration denied liability.

Finding of the Court:

The Tribunal held that the claim could not be rejected for want of notice under Section 78-B as the provision was not attracted in view of the nature of the claim, that it was not necessary for the plaintiff to issue separate notice for each transaction, that the claim was within time, and that the Railway Administration was not entitled to retain the freight for the longer route while actually carrying the goods by a shorter route. The Tribunal directed the Railway Administration to refund the differential freight along with interest and costs.

Issues: 1. Whether the claim for refund of differential freight was maintainable without a notice under Section 78-B of the Indian Railways Act, 1890? 2. Whether the Railway Administration was liable to refund the differential freight despite the rationalisation scheme? 3. Whether the claim was barred by limitation? 4. Whether the award of lawyers' fee was justified?

Ratio Decidendi: 1. The claim for refund of differential freight was not a claim for refund of overcharge, and therefore, a notice under Section 78-B was not required. 2. The Railway Administration was liable to refund the differential freight as it had breached the contract of carriage by carrying the goods by a shorter route without any valid reason. 3. The claim was within time as it was filed within three years from the date of discovery of the mistake. 4. The award of lawyers' fee was justified considering the amount of the claim.

Final Decision: The appeal was dismissed with costs.

P. C. NAIK, J.


( 1 ) THIS is an appeal under S. 23 (1) of the Railway Claims Tribunal Act, 1987 filed by the Union of India and others against the judgment dated 18-1-1993 passed by the Railway Claims Tribunal, Bhubaneswar, in T. A. No. 289 of 1990

( 2 ) PLAINTIFF-RESPONDENT had filed Money Suit No. 115 of 1989 in the Court of the Subordinate Judge, Rourkela against the Union of India and others for refund of Rs. 1,32,87,749/-, which, according to the plaintiff, had been illegally realised from it by the Railway Administration.

( 3 ) THE facts giving rise to this appeal are that the plaintiff require imported coal for the Rourkela Steel Plant. The coal was unloaded at Visakhapatnam Port wherefrom it was required to be transported to Rourkela Steel Plant Exchange Yard at Bondamunda whew the wagons are placed for the purpose of unloading.

( 4 ) IT is the plaintiffs case that the shortest available route from Visakhapatnam to Rourkela is via Viajaynagaram-Titlagarhsambalpur-Jharsuguda-Rourkela covering a distance of 667 kilometres. The alternative, but longer and dearer route is via Vijaynagaram-Khurda Road-Kharagpur-Tatanagar-Chakradharpur-Rourkela covering a total distance of 1082 kilometres. However, in view of a notification issued under S. 27-A of the Indian Railways Act, 1890, the Central Government had notified certain routes called 'rationalised routes' over which particular traffic had to be booked and accordingly, in terms of a general order, the coal imported at Visakhapatnam Port for carriage to Rourkela Steel Plant was required to be booked and carried by the longer route covering 1082 kilometers instead of by the shorter route of 667 kilometres. According to the plaintiff, in view of the rationalisation scheme and the general order, it had no choice but to pay freight for the longer route, as booking could not be for carriage over the shorter route.

( 5 ) IT is the further case of the plaintiff that in or about April, 1987, an officer came to know that some of the rakes booking were despatched to Rourkela by the shorter route (covering a distance of 667 kilometres) though weight charges were recovered for carriage by the longer rationalised route (covering a distance of 1082 kilometres ). On further enquiry made at different junctions, it was gathered that during the period 15-4-1986 to 28-11-1986 and 5. 1. 1987 to 28. 2. 1987, a large quantity of imported coal booked from Visakhapatnam to Bondamunda had in fact been carried, not by the rationalised route but by the shorter route. On coming to know about the aforesaid fact, alleges the plaintiff, it lodged a demand for refund of the differential amount of Rs. 1,32,87,749/-, but the same was turned down. It is alleged by the plaintiff that though the notice of demand was styled as one under S. 78-B of the Indian Railways Act, 1890, in fact the demand cannot be said to be one under that section as the claim in question is not one which comes within the purview of the said section. On 9-6. 1989, notice under S. 80, C. P. C. was sent to the defendants and thereafter, the suit was filed in the court of the Subordinate Judge, Rourkela, Which was registered as Money Suit No. 119 of 1989. However, as in the meantime, the Railway Claims Tribunal Act was enacted and the Railway Claims Tribunal was established at Bhubaneswar, the suit was, in terms of S. 24 of the said Act, transferred to it and was re-numbered as T. A. No. 289 of 1990.

( 6 ) THE appellants-defendants resisted the claim and denied their liability, inter alia, on the ground that in terms of the rationalisation scheme, the goods had to be carried over the rationalised route and accordingly, freight was charged. It was pleaded that on some occasions due to operational constraints, out of 4900 wagons nearly 2900 wagons had to be carried via the shorter route and this was permissible in view of the decision of the Railway Board to the effect that in respect of the traffic booked by the rationalised route but oc






























Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top