SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

1953 Supreme(P&H) 29

PUNJAB & HARYANA HIGH COURT
Kapur and D.Falshaw JJ.
Watkins Mayor & Co.
Versus
Jullundur Electric Supply Co.Ltd.
Second Appeal No. 787 of 1948,
Decided On : MAY 21, 1953

A contractual provision for a minimum charge in an electricity supply agreement is valid and enforceable as a fair return on the company's capital expenditure, considering factors like load factor, power factor, and total consumption.

Headnote:

ELECTRICITY ACT - MINIMUM CHARGE - ENFORCEABILITY - INTERPRETATION OF SECTIONS 22, 23, AND SCHEDULE CLAUSES VI TO X - REASONABLE RETURN ON CAPITAL EXPENDITURE - CONTRACTUAL PROVISION FOR MINIMUM CHARGE - VALIDITY.

Fact of the Case:

An agreement between an electric supply company and consumers stipulated a minimum consumption of 1,20,000 units in two years, with a charge of Re. 0-1-3 per unit for energy consumed and Re. 0-1-0 per unit if consumption exceeded 3,00,000 units. The consumers failed to meet the minimum consumption, and the company sued for the cost of the unconsumed units at the stipulated rate.

Finding of the Court:

1. The transformer installed by the company was sufficient to meet the consumers' energy requirements. 2. The suit was not based on a breach of contract but sought to enforce the contractual provision for a minimum charge. 3. The minimum charge was a fair return on the company's capital expenditure, considering factors like load factor, power factor, and total consumption. 4. The contractual provision for a minimum charge was valid and enforceable.

Issues: 1. Whether the company breached the agreement by failing to provide sufficient energy. 2. Whether the suit was for damages or for the price of unconsumed energy. 3. Whether the company was entitled to a fair return on its capital expenditure. 4. Whether the contractual provision for a minimum charge was valid and enforceable.

Ratio Decidendi: 1. The evidence showed that the transformer installed by the company was sufficient to meet the consumers' energy requirements. 2. The claim in the plaint was based on the contractual provision for a minimum charge, not on a breach of contract. 3. The minimum charge was a fair return on the company's capital expenditure, considering factors like load factor, power factor, and total consumption. 4. The contractual provision for a minimum charge was valid and enforceable under the Indian Electricity Act and the agreement between the parties.

Final Decision: The appeal was dismissed, and the company was entitled to enforce the contractual provision for a minimum charge.

Judgment

Kapur, J.

1. This is a defendants appeal against an appellate decree of the Additional District Judge, Jullunder, dated 22-7-1948, varying the decree of the trial Court which had decreed the plaintiffs suit but had awarded damages of only Rs. 333/3/9 against the claim of the plaintiff of Rs. 2,921/7/9.

2. On 4-5-1940, an agreement was entered into between the plaintiff, the Jullundur Electric Supply Company Limited (hereinafter termed the Company), and the defendants, Messers. Watkins Mayor and Company, Jullundur (hereinafter called the consumers), for the supply of electric energy. The relevant conditions of this contract were that the consumers required a maximum load of 100 kilowatts and they guaranteed a minimum consumption of 1,20,000 units in two years and the Company was to charge in that case at the rate of Re. 0-1-3 per unit of energy consumed and if the consumption exceeded 3,00,000 units in two years, the rate was to be Re. 0-1-0 per unit subject to certain conditions. Clause 4 of the agreement was as follows:

"4. In case the consumer fails to consume the guaranteed 1,20,000 units as in Clause (3) in the period of two years from the date of agreement, he shall pay to the Company the cost of 1,20,000 (one lac and twenty thousand) units at the stipulated rate of Re. 0-1-3 per unit."

3. As the defendants did not consume the minimum amount of energy guaranteed by the agreement, the plaintiff brought a suit on 4-5-1945, claiming a sum of Rs. 2,921/7/9, alleging that there was a contract between the parties by which the consumers had given a guarantee to consume 1,20,000 units in two years and as they had only consumed 82,605 units, they were liable to pay for the balance of the units unconsumed out of the guaranteed units, i. e. 37,395 units. The defendants pleaded that the plaintiff Company did not put up a transformer of sufficient power, it being only of 88 Kilowatts although according to the con-tract, they had to erect a transformer of 100 Kilowatts or over, that they were unable to supply sufficient amount of energy as a result of which the pole fuses were constantly being burnt out and in spite of the complaint made they took no action, that the plaintiff could not therefore sue on the basis of the contract which was never acted upon and the minimum guarantee clause was therefore unenforceable. They also pleaded that they had deposited the money claimed by the plaintiff with the Electrical Inspector but he had returned the money to them on the ground that he had no jurisdiction to go into the matter of compensation. In their replication, the plaintiff Company denied the statements made by the defendants and stated that the transformer which they had put up was of sufficient power, that according to the contract they had only agreed to give the stipulated amount of energy, that there was no breach of contract on their part and that the burning out of the fuses was due to the unbalanced load which the defendants had put on the mains of the Company.

4. Mohan Lal, Chief Engineer of the plaintiff Company, was examined Before issues and he stat ed that the agreement was that the defendants were to take the maximum load of 100 kilowatts but there was no possibility of their taking this load at any time, that at no time could there be a diversity factor of more than 50 per cent, and even if 90 kilowatts load was taken, the fuses would not burn. out because there was an overload capacity of the transformer. Upon this the Court struck the fol lowing issues:

"1. What was the effect of the plaintiff Company fixing a transformer of 88 kilowatt on the agreement between the parties when the plaintiff Company had contracted to meet a maximum load of 100 kilowatt?

2. What was the effect of the giving of energy from the above transformer to others on the rights of the parties?

3. Could the defendants take advantage of the reduction of rates by the Punjab Government and how?

4. Relief.

5. Mr. Y. L. Taneja who tried the suit





































Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top