2015 Supreme(P&H) 1068

IN THE HIGH COURT OF PUNJAB AND HARYANA
Before
The Hon’ble Mr. Justice Rajesh Bindal
Civil Revision No. 4132 of 2012 (O&M)
Jagdev Singh
v.
Gursewak Singh
{Decided on 04/08/2015}

Subject

Civil Law - Amendment of Pleadings

Act Referred

CIVIL PROCEDURE CODE : O.6 R.17
SPECIFIC RELIEF ACT : S.16

Headnote

Amendment of Plaint--It should not be allowed where claim sought to be added is barred by limitation, if claim was to be filed independently.

       (A) Civil Procedure Code, 1908, O.6 R.17--Amendment of Plaint--It should not be allowed where claim sought to be added is barred by limitation, if claim was filed independently (Para 15)

       (B) Specific Relief Act, 1963, S.16--Agreement to Sell--Specific Performance--Limitation--For filing a suit for specific performance of agreement of sell, the limitation is 3 years from the date fixed for the performance and if no such date is fixed, when the plaintiff has notice that performance is refused. (Para 14)

       (C) Specific Relief Act, 1963, S.16--Amendment of Plaint--In a suit for recovery of earnest money, application for specific performance of agreement to sell was filed--Held; since application in itself was time barred, it was not to be allowed--Civil Procedure Code, 1908, O.6 R.17. (Para 15)

       

Judgement Key Points

Based on the provided legal document, the court has emphasized that a suit for recovery of possession by way of specific performance of an agreement to sell is subject to a limitation period of three years from the date fixed for performance. If the claim for specific performance is filed after this period, it is considered time-barred and not maintainable. In the case at hand, the application to amend the plaint to include a claim for specific performance was filed beyond the limitation period, rendering such a claim not maintainable.

Therefore, the recovery suit for possession by way of specific performance, as amended or sought to be amended in this context, is not maintainable.

Answer: No.


Advocates:
For the Petitioner:Mr. Arun Jindal, Advocate.
For the Respondent:Mr. Amar Vivek, Advocate.

JUDGMENT

Mr. Rajesh Bindal, J.:- Challenge in the present petition is to the order dated 1.6.2012, passed by the learned court below, whereby the application for amendment of the suit filed by the respondent-plaintiff, was allowed.

2. Brief facts, as are available on record, are that respondent No. 1-plaintiff filed a suit for recovery of Rs. 37,00,000/-, i.e., Rs. 18,50,000/- paid as earnest money and Rs. 18,50,000/- as damages in terms of the agreement to sell dated 28.5.2007, executed by the petitioner in favour of the respondent. Further prayer was made for permanent injunction restraining the petitioner from alienating the suit property. The suit was filed on 14.1.2008. In the aforesaid suit, the respondent-plaintiff filed application for amendment seeking to claim relief of possession by way of specific performance of agreement to sell. The amendment having been allowed by the court below, the order has been impugned in the present petition.

3. Learned counsel for the petitioner submitted that execution of the agreement to sell dated 28.5.2007 is not in dispute. In terms thereof, last date for execution of the sale deed was 30.11.2007. The respondent-plaintiff filed the suit for recovery of earnest money and damages and further for permanent injunction on 14.1.2008. No relief of possession by way of specific performance of agreement to sell was claimed. The application seeking amendment of the plaint was filed on 18.3.2011. The relief of possession by way of specific performance of agreement to sell was timebarred on that day, hence, the plaint could not be permitted to be amended for claiming a time-barred relief. The limitation to file a suit for possession by way of specific performance of agreement to sell expired on 29.11.2010. In support of his plea, reliance was placed upon K. Raheja Constructions Ltd. v. Alliance Ministries, AIR 1995 SC 1768; Van Vibhag Karamchari Griha Nirman Sahkari Sanstha Maryadit (Regd.) v. Ramesh Chander and others, [2010(6) Law Herald (SC) 4257] : (2010) 14 SCC 596; Smt. Krishna Rani v. Ram Kishan, 2002(4) RCR (Civil) 373 and Madan Lal v. S. L. Maloo and others, [2012(3) Law Herald (P&H) 2119] : 2012(3) PLR 221.

4. On the other hand, learned counsel for the respondent submitted that the base for claiming the relief either of recovery, injunction or specific performance of agreement to sell is the agreement dated 28.5.2007. In fact, the respondent herein is an illiterate person, who had entrusted the case to his counsel for claiming the relief of possession by way of specific performance of agreement to sell, however, he inadvertently filed a suit for refund of earnest money along with damages only. A litigant should not be made to suffer on account of fault of the counsel. No prejudice as such is going to be caused to the petitioner.

5. Heard learned counsel for the parties and perused the paper book.

6. An issue as to whether amendment of plaint should be allowed, where the claim sought to be added is barred by limitation, was considered by this court in Madan Lal’s case (supra), where law on the subject was considered. The relevant parts thereof are extracted below:

“9. In T. L. Muddukrishana v. Smt. Lalitha Ramchandra Rao, 1997(2) RCR (Civil) 154, while considering an issue as to whether a party should be permitted to amend pleadings to claim certain relief which is apparently timeCivil Revision No. 4132 of 2012 [3] barred, it was opined that in case the relief sought to be claimed is barred on the date the application is filed, the amendment should not be permitted. It was a case in which an agreement to sell was executed on 16.3.1989. The last date for execution of sale deed was fixed on 28.5.1989. Initially the vendee filed a suit for mandatory injunction on 21.4.1992 seeking a direction against the vendor to comply with the terms of agreement. During the pendency of the suit, an application was filed on 5.11.1992 seeking to amend the plaint praying for relief of specific performance