IN THE HIGH COURT OF PUNJAB AND HARYANA AT CHANDIGARH
Ravi Shanker Jha, Arun Palli, JJ.
Anand Nvh Products (p) Limited – Appellant
Versus
State Of Haryana & Ors. – Respondents
Civil Writ Petition No. 1878 of 2017 (O&M)
Decided On : 31-08-2022
Land Acquisition - Industrial Unit - Land Acquisition Act, 1894, Section 4, Section 6 - The judgment discusses the interpretation and application of Section 24(2) of the Act of 2013 in the context of the acquisition proceedings for an industrial unit. The court concludes that the acquisition proceedings have not lapsed under Section 24(2) as the requisite period of five years is not completed, physical possession of the land has been taken, and the obligation for payment of compensation stands discharged.
Fact of the Case:
The petitioner, an industrial unit, sought to quash the notification and award for the acquisition of its land for public purposes. The petitioner claimed that the acquisition proceedings had lapsed under Section 24(2) of Act of 2013 due to non-payment of compensation and possession of the land.
Finding of the Court:
The court found that the acquisition proceedings had not lapsed under Section 24(2) as the requisite period of five years was not completed, physical possession of the land had been taken, and the obligation for payment of compensation had been discharged. The court also noted that the land was necessary for the public purpose for which it was acquired.
Issues: The main issue was whether the acquisition proceedings had lapsed under Section 24(2) of Act of 2013 due to non-payment of compensation and possession of the land.
Ratio Decidendi: The court applied the principles laid down by the Supreme Court in the case of Indore Development Authority v. Manoharlal and others to interpret and apply Section 24(2) of the Act of 2013. The court concluded that the acquisition proceedings had not lapsed under Section 24(2) as the requisite period of five years was not completed, physical possession of the land had been taken, and the obligation for payment of compensation had been discharged.
Final Decision: The court dismissed the petition as the acquisition proceedings had not lapsed under Section 24(2) of Act of 2013. Pending applications were also dismissed.
JUDGMENT
Ravi Shanker Jha, C.J. - The petitioner has filed instant writ petition seeking issuance of writ in the nature of Certiorari for quashing the notification dated 15.11.2002 and 12.11.2003 issued under Section 4 and Section 6 of the Land Acquisition Act, 1894 and award dated 18.11.2005 for the public purpose namely, Development of Integrated Complex for Industrial, Institutional, Commercial and Recreational and other public utilities vide which the land of the petitioner was acquired and has further sought declaration to the effect that the acquisition proceedings have lapsed in view of Section 24(2) of Act of 2013.
2. As per the case set up by the petitioner, it is an industrial unit having manufacturing facility for automobile parts. The company is in possession of the land situated in Rect No. 14 Killa No. 11/1 (5-2), 12/2 (511), 13 (8-0), 18/1 (2-0), 19/1 (6-0) total measuring 26 Kanal 13 Marla in revenue estate of Village Begampur, Tehsil and District Gurugram. The company purchased the adjoining land measuring 26 Kanal 13 marla, the details of which is given in para no. 5 of the petition for expansion of the existing industrial unit. The said land along with other land came to be notified for acquisition by the State of Haryana through Department of Industries vide notifications dated 15.11.2002 and 12.11.2003 issued under Section 4 and 6 of the Land Acquisition Act, 1894. The notifications were challenged by the predecessor-in-interest of the petitioner by filing Civil Writ Petition No. 6180 of 2004, which was disposed of vide order dated 16.07.2005 based on the statement of the Advocate General, Haryana thereby offering to constitute a High-Powered Committee which would take decision after considering the grievances of the persons approaching the Court challenging the acquisition proceedings. In the meantime, the status quo was ordered to be maintained till the time decision is taken and same shall be maintained 15 days after the decision of the committee. Accordingly, the petitioner filed a representation date 07.09.2005 before the Director Industries Department Haryana for release of land and was called for personal hearing on 18.10.2005. The High-Powered Committee submitted its report dated 10.11.2005 that the site is lying vacant. This finding was contradictory to the show cause notice dated 28.09.2005 served upon the petitioner unit to show cause as to why the building has been erected without a valid CLU from the competent authority. During the pendency of the proceedings, award dated 18.11.2005 was announced.
3. The report of the High-Powered Committee was challenged by the petitioner in filing Civil Writ Petition No.19742 of 2005. This Court vide order dated 21.11.2008 directed the state to constitute a committee and to consider the case of the petitioner afresh. Accordingly, committee was constituted and as submitted by the petitioner, recommended to release that portion of land which was situated under the shed and all surrounding land was recommended to be acquired as it was lying vacant. The report was submitted before this Court and referring to the affidavit, learned Advocate General, Haryana stated that Government had accepted the report of the Committee with regards to release of land subject to the conditions imposed by the Committee. The writ petition was accordingly disposed of vide order dated 22.12.2009. The petitioner had given consent to the report of the committee, which now they state to have been given under trauma, as a result of which 6 Kanal land was released from acquisition. The petitioner thereafter filed an application for recall of order dated 22.12.2019, which was dismissed by this Court on 19.02.2010.
4. Now, the left-over land, which is under acquisition as per the petitioner, is under its possession and neither any compensation has been paid nor deposited in the Reference Court. Therefore, acquisition proceedings qua such land stands lapsed under Section 24(2) of Act of 2013.
5.
Indore Development Authority v. Manoharlal and others AIR 2020 SC 1496
The main legal point established in the judgment is that for the acquisition proceedings to lapse under Section 24(2) of Act of 2013, both the contingencies of non-possession and non-payment of compe....
The main legal point established in the judgment is that for lapsing of acquisition proceedings under Section 24(2) of the Act of 2013, both the conditions of physical possession and payment of compe....
The petition under Section 24(2) of the Act of 2013 must meet the gap period of five years, and the physical possession and compensation tender must be valid. The essentiality of the land for public ....
The physical possession of the land and the tendering of compensation are essential conditions for the lapse of acquisition proceedings under Section 24(2) of the Act of 2013.
The main legal point established is that under Section 24(2) of the Act of 2013, the lapse of acquisition proceedings is contingent upon the non-payment of compensation and non-possession of the land....
The physical possession of the land and tendering of compensation discharge the state's obligation, and the land essential for public purpose cannot be released from acquisition.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.