SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

1972 Supreme(All) 236

Allahbad High Court
C.S.P.SINGH
Hindustan Aluminium Corporation. Ltd. - Appellant
Versus
The U.P. State Electricity Board - Respondent
Decided On : 09/27/1972

Advocates:
N.B. Singh, K.L. Misra. Devendra Swarup, Umesh Chandra, for Petitioner; R.N. Trivedi. Standing Counsel, for Respondent.

A licensee under the Electricity Act, 1948, cannot disconnect the supply of electricity to a consumer who has entered into an arbitration agreement with the licensee.

Headnote:

ELECTRICITY ACT, 1948 - SECTION 24 - ARBITRATION AGREEMENT - DISCONNECTION OF SUPPLY - NEGLECT TO PAY - WAIVER OF RIGHTS - WITHDRAWAL OF NOTICES - STATUTORY DUTY TO SUPPLY ELECTRICITY.

Fact of the Case:

The petitioner, an aluminium factory, entered into an agreement with the State Electricity Board for the supply of electricity. Disputes arose between the parties, and an arbitration agreement was entered into appointing a sole arbitrator. The arbitrator was unable to act, and the parties agreed to appoint another arbitrator. The Board sent a draft arbitration agreement to the petitioner, which the petitioner executed and returned. However, the Board refused to go ahead with the arbitration. The Board then issued a notice of disconnection of supply to the petitioner.

Finding of the Court:

The court held that the arbitration agreement was complete and binding on the parties. The court also held that the Board had waived its right to disconnect the supply under Section 24 of the Electricity Act, 1948, by entering into the arbitration agreement. The court further held that the Board was under a statutory duty to supply electricity to the petitioner and that the disconnection of supply would be a breach of that duty.

Issues: 1. Whether the arbitration agreement was complete and binding on the parties. 2. Whether the Board had waived its right to disconnect the supply under Section 24 of the Electricity Act, 1948. 3. Whether the Board was under a statutory duty to supply electricity to the petitioner.

Ratio Decidendi: 1. The court held that the arbitration agreement was complete and binding on the parties because: - The parties had agreed to appoint a sole arbitrator. - The arbitrator was unable to act, and the parties agreed to appoint another arbitrator. - The Board sent a draft arbitration agreement to the petitioner, which the petitioner executed and returned. 2. The court held that the Board had waived its right to disconnect the supply under Section 24 of the Electricity Act, 1948, by entering into the arbitration agreement because: - Section 24 of the Act is an enabling section, and the Board is under no obligation to resort to the mode of disconnection for the realisation of its dues. - The Board had agreed to treat the disconnection notices as withdrawn. 3. The court held that the Board was under a statutory duty to supply electricity to the petitioner because: - Section 18 of the Electricity (Supply) Act, 1948, imposes a duty on the Board to supply electricity to consumers.

Final Decision: The court allowed the petition and quashed the impugned notice of disconnection dated 8th December, 1971. The petitioner was awarded costs.

JUDGMENT :- The petitioner is a public limited company, and owns and runs an aluminium factory at Renukoot in the district of Mirzapur. The aluminium industry is a power based industry, in the sense that electrical energy is essential for the manufacture of aluminium. On the 29th of October, 1959, it entered into an agreement with the State of Uttar Pradesh for the supply of 55,000 K. W. of electricity from the Rihand Hydel Station (Annexure I to the petition). Clause 12 (b) of the agreement provided that in case the total generation of energy of the Rihand Hydroelectric generation station was reduced by causes beyond the Government's control, then the energy available would be rateably distributed amongst all consumers. Clause 13 (b) of the said agreement made it incumbent for the company to pay each bill within thirty days of the delivery thereof with five days of grace. In case the company disputed any item of the bill, it had to notify the Government in writing within thirty days of such dispute, but was not entitled to withhold payment. Clause 13 (d) provides for disconnection of the supply, In case the company neglected or refused to pay any amount payable under the bills. Clause 21 provides for arbitration of disputes arising out of the agreement. On the 6th November, 1965, another agreement was arrived at between the petitioner and the State Electricity Board which had stepped into the shoes of the State Government for additional supply of 45 million Watts of electricity. Two other supply agreements were also entered into in 1968 and 1970 but we are not concerned with them in the present petition.

It appears that the Chief Engineer of the Electricity Board on the 1st November, 1966, sent a letter to the petitioner purporting to be under Cl. 12 (b) (i) of the first agreement imposing a 30% cut on consumption on account of low reservoir level of the Rihand Dam. This was followed by a notification under Section 22-B of the Electricity Act on the 5th November, 1966, directing that all energy supplied to consumers by licensees, which in the present case happened to be the Electricity Board would be subject to a 30% cut. This order was to remain effective till 30th June, 1967. Thereafter, the Board issued an order on the 20th February 1967 under Section 49 of the Electricity (Supply) Act, 1948 imposing a surcharge of 5.5 Paise per unit for energy consumed in excess of 70% of the normal monthly consumption. In the year 1967-68, 1968-69 and 1969-70, cuts were again imposed by the Board. A notification under Section 22B was also issued Imposing cuts. The cuts in these years were imposed on the basis that the reservoir level of Rihand was not of the optimum level so as to ensure a full supply of energy to consumers. The Board thereafter raised demands against the petitioner for excess energy consumption, and also certain other demands which were disputed by the petitioner company. On the 28th January, 1970, the Board and the petitioner entered into an arbitration agreement appointing Sri K. N. Wanchoo, retired Chief Justice of India as the sole arbitrator to decide the dispute which had arisen between the parties. This arbitration agreement which has been filed as Annexure 'III' to the petition sets out three heads of dispute and covers the period upto 1969-70. Clause 4 of this agreement is important for the purposes of the present case and may be quoted:-

"That all disconnection notices given by the Board for non-payment of the claims pertaining to the matters mentioned in clause I above, shall stand withdrawn on the execution of this agreement."

It appears that Sri K. N. Wanchoo was not available for arbitrating in the dispute. The parties then approached Sri A. K. Sarkar, another retired Chief Justice of India, but he too expressed his inability to take up the matter. Thereafter the Board sent a letter on the 19th March, 1971 (Annexure VI to the petition) suggesting the name of Sri Hidayatullah, retired Chief Justice of India t






































Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top