2005 Supreme(All) 1979

ALLAHABAD HIGH COURT
Yatindra Singh and R.K. Rastogi, JJ.
Northern Coalfield Limited, A Government of India Company incorporated
Versus
Chairman and Managing Director, U.P. Power Corporation Limited and Managing
First Appeal from Order 486 of 2005
Decided On : 18 October 2005
First Appeal from Order 486 Of 2005

Important Points

The main legal point established in the judgment is the interpretation of the Tariff Order 2000-01 and the determination of surcharge liability for HV-2 consumers getting power supply during restricted hours and on independent feeder emanating from 400/220/132 KV sub-station.

Subject

Interpretation of Statutes - Electricity Tariffs and Regulatory Commission

Act Referred

ELECTRICITY COMMISSION ACT : .
ELECTRICITY SUPPLY ACT : S.57(a), S.57, S.49, S.46
ELECTRICITY SUPPLY CODE : .
UTTAR PRADESH ELECTRICITY REFORMS ACT : S.24(3), S.26, S.26(2), S.27, S.27(2), S.24, S.48, S.36, S.15, S.2, S.13(3)
UTTAR PRADESH ELECTRICITY REGULATION OF SUPPLY, DISTRIBUTION, CONSUMPTION AND USE ORDER : .
UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION CONDUCT AND SERVICE REGULATIONS : Reg.138

Headnote

Tariff Order 2000-01 - Interpretation of HV-2 consumer surcharge - Section 24 of the 1999 Act, Electricity Commission Act, 1998, UP Electricity Reforms Act 1999, Electric Supply Act 2003 - The court discussed the interpretation of the tariff order 2000-01 and the notification dated 9. 8. 2000, focusing on the surcharge for getting power supply during restricted hours and on independent feeder emanating from 400/220/132 KV sub-station. The court analyzed the definitions of independent feeder, continuous process industry, and restricted/peak hours, and concluded that the NCL is liable to pay 30% surcharge for the NCL Bina connection and 15% surcharge for the IWSS connection for the period from 9. 8. 2000 to 5. 9. 2001.

Fact of the Case:

The case revolved around the interpretation of the Tariff Order 2000-01 related to the HV-2 consumer surcharge for getting power supply during restricted hours and on independent feeder emanating from 400/220/132 KV sub-station. The NCL filed an application before the Commission for clarification/review of the order dated 27. 7. 2000, which was dismissed, leading to the present appeal.

Finding of the Court:

The court found that the NCL is liable to pay 30% surcharge for the NCL Bina connection and 15% surcharge for the IWSS connection for the period from 9. 8. 2000 to 5. 9. 2001. The court also determined the maintainability of the NCL's application before the Commission, the status of the sub-station Bina, and the interpretation of restricted hours and peak hours.

Issues: The main issues were the maintainability of the NCL's application before the Commission, the status of the sub-station Bina, whether the NCL is getting power supply on independent feeder for its two connections, and the interpretation of restricted hours and peak hours.

Ratio Decidendi: The court's decision was based on the interpretation of the Tariff Order 2000-01, definitions of independent feeder and continuous process industry, and the distinction between restricted and peak hours. The court also considered the provisions of the Electricity Commission Act, 1998, UP Electricity Reforms Act 1999, and Electric Supply Act 2003.

Final Decision: The appeal was partly allowed, and the NCL was held liable to pay 30% surcharge for the NCL Bina connection and 15% surcharge for the IWSS connection for the period from 9. 8. 2000 to 5. 9. 2001. The parties were ordered to bear their own costs.

Advocates:
S.M.Dayal, SUDHIR AGRAWAL, V.B.UPADHYA, V.K.UPADHYA, W.H.KHAN,

YATINDRA SINGH, J.

( 1 ) THIS appeal revolves around interpretation of that part of Tariff order 2000-01, which relates to category HV-2 (Large and Heavy Power) consumer (the HV-2 consumer), who are getting power supply on independent feeder emanating from 400/220/132 KV Sub-station. Such a consumer is assured 500 hours of electric power supply in a month and in case of failure to fulfil this assurance, the consumer is also entitled to rebate. However for this benefit the consumer is liable to pay 15% surcharge on demand and energy charges. The main question in this appeal is, whether such a consumer is further liable to pay additional surcharge of 15%, if it is getting electric power during restricted hours. THE FACTS

( 2 ) M/s Northern Coalfield Ltd (the NCL) has coal fields in district Sonebhadra in UP and district sidhi in MP. It has taken two power connections from the UP Electricity Board (the Board ). The first was for 2850 KVA load and was taken on 12. 9. 1989 for integrated water supply scheme at khadia (IWSS Khadia connection ). The second one was for 20 MVA load and was taken on 20. 11. 1999 for coal mining purposes at Bina (NCL Bina connection ). These two connections are from 2 x 20 MVA sub-station at Bina (sub-station Bina) and are through different 33 KV Lines.

( 3 ) THE Board was constituted under the Electricity (Supply) Act 1948; it was looking after generation and supply of electricity in this State. The Board has been replaced by the UP Power corporation Ltd. (the Corporation) constituted under UP Electricity Reforms Act 1999 (the 1999 act ). The two connections taken by the NCL are now being managed by the Corporation.

( 4 ) THE UP Electricity Regulatory Commission (the Commission) was constituted under the electricity Commission Act, 1998 (the 1998 Act) enacted by the Parliament. However, our State enacted the 1999 Act for restructuring the electricity industry in this State. Under the 1999 Act, the rationalisation of generation, transmission, distribution, supply and tariff of the electricity is to be regulated by an independent electricity regulatory commission. The 1999 Act has adopted the Commission established under the 1998 Act. The 1999 Act is the State Act; the President has given his assent to it: it overrides the 1998 Act to the extent of repugnancy. At present, the parliament has enacted the Electric Supply Act 2003 (the 2003 Act), but the dispute is to be decided within the parameters of the 1999 Act (as it stood at the relevant time) rather than the 2003 Act.

( 5 ) THE Commission took up the question of revising the tariffs under section 24 of the 1999 Act and the tariff order 2000-01 was issued on 27. 7. 2000. The Corporation adopted the tariff by its notification on 9. 8. 2000 and these rates became applicable from that date. Tariff has been changed form 15. 9. 2001 for the subsequent period and the dispute in this writ petition is confined to the tariff from 9. 8. 2000 to 15. 9. 2001 for the HV-2 consumer. The relevant part of the tariff order dated 27. 7. 2000 and the notification dated 9. 8. 2000 are appended to this judgement as Appendix-I and Appendix-II respectively. The rates and the surcharge for the HV-2 consumers are indicated in a table in the tariff order 2000-01. This table is also reproduced in appendix-1. It has two columns and four rows. It is being referred to as the Table or the column or the rows as the case may be. The third row of the Table provides 15% surcharge for getting power supply during restricted hours. The fourth row of the Table provides 15% surcharge for getting power supply on independent feeder emanating from 400/220/132 KV sub-station. The interpretation of these two rows is involved in this appeal.

( 6 ) THE NCL filed an application before the Commission on 4. 7. 2004 for clarification/review of the order dated 27. 7. 2000. On this application, counter affidavit was filed by the Corporation. The judgement was reserved on 29. 11. 2004 however the Commissio