HIGH COURT OF JUDICATURE AT ALLAHABAD
Arindam Sinha, Prashant Kumar, JJ.
Bhullan Singh And Others – Petitioners
Versus
State Of U.P. And Others - Respondents
WRIT - C No. - 12447 of 2026
Decided On : 17-04-2026
| Table of Content |
|---|
| 1. historical factual background and procedural history of the compensation dispute. (Para 1 , 2 , 3 , 4 , 5 , 6 , 7 , 8 , 9) |
| 2. parties' contentions regarding the admissibility and applicability of government compensation guidelines. (Para 10 , 11 , 12 , 13 , 14 , 15 , 16 , 17) |
| 3. statutory framework and regulatory context for electricity infrastructure and land compensation. (Para 18 , 19 , 20 , 21 , 22 , 23 , 24 , 25 , 26 , 27 , 28 , 29 , 30 , 31) |
| 4. the state cannot selectively implement central government guidelines for determining land compensation. (Para 32 , 33 , 34 , 35) |
| 5. quashing of the impugned rejection order and mandating compensation disbursement. (Para 36 , 37 , 38) |
JUDGMENT :
Prashant Kumar, J.
Factual Matrix
1. The instant writ petition has been preferred by four petitioners who all are owners of a land situated in District Shamli where they have the crops and trees planted on the land. Over this land, the respondent Nos.2 and 3 are setting up a High Tension Electricity Transmission Line and because of which the petitioners suffer from the loss of crops, trees and devaluation of the land. As far as trees are concerned, certain compensation has been awarded but no compensation has been awarded for the corridor area over which the high tension wire passes through (known as Right of Way, 'RoW'). The Government of India through Ministry of Power had issued certain guidelines by means of a Government Order ( in short, 'G.O.') dated 15.10.2015 which provides for payment of compensation towards damages with regard to RoW for transmission lines as well as for the tower base area.
2. As per G.O. dated 15.10.2015, 85% of the land value has to be paid by the District Magistrate on the tower base area on which the heavy metallic tower is set up. Further, a compensation towards diminution of land value (in the width of RoW corridor due to laying of transmission line) was to be awarded which was subject to the maximum 15% of the land value as determined on circle rate/ guideline value/ Stamp Act rate.
3. The Government of India through Ministry of Power issued another guideline vide G.O. dated 14.06.2024 for payment with regard to RoW for transmission lines wherein the compensation for the tower base area was increased to 200 % and the land value for RoW corridor area was increased to 30% of the land value.
4. Again the Government of India through Ministry of Power issued another circular on 21.03.2025 providing a supplementary guideline for payment of compensation with regard to RoW for transmission line of inter-state high voltage electricity lines.
5. The respondent authorities while determining the compensation of trees and crops coming under the transmission line area failed to follow the guidelines and provided no compensation for the RoW of corridor area. The petitioners made several representations to the respondents but no heed was paid to it.
6. Aggrieved by this situation, the petitioners preferred a writ petition being Writ-C No.20077 of 2025 ( Pradeep Kumar and others vs. State of U.P. and others ) which was disposed of by a Division Bench of this Court vide order dated 04.11.2025 with the following directions:-
"5. Considering the facts and circumstances of the case and without going into the merits of the case, we dispose off the writ petition permitting each petitioners to file separate representation under Rule 3 (2) of the Works of Licensees Rules, 2006 ventilating their grievances before the respondent nos. 5-District Magistrate, Shamli & respondent no.6-District Magistrate, Saharanpur along with a certified copy of this order within a period of one month from today. In case any such representation is filed by the petitioners, concerned respondent authority shall pass separate orders on the representation of each petitioners strictly in accordance with law after giving due notice and opportunity of hearing to each petitioners within a period of two months thereafter."
7. As per the directions given by
Compensation under RFCTLARR Act is applicable only in cases of land acquisition, not for Right of Way, as clarified by the court.
(1) Damages suffered by erection of transmission lines and towers – For determining rights of various parties to receive compensation in case there is inter se dispute, certain amount of evidence wou....
The court established that under the Indian Telegraph Act, 1885, compensation for land damage must be based on surface damage rather than land value diminution.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.