2006 Supreme(MP) 357
High Court Of Madhya Pradesh
DIPAK MISRA AND R. S. JHA, JJ.
KANHAIYALAL VISHWAMBHERDAYAL AGRAWAL - Appellant
Versus
MUKTILAL RAMESHWARDAS NAREDI - Respondents
F. A. 515 Of 2001
Decided On : 03/10/2006
Important Points
Subject
Civil Law - Partnership Dispute
Act Referred
LIMITATION ACT : S.3(2)(b), Art.5, Art.113
Headnote
Limitation Act - Dissolution of Partnership - Article 5, Article 26, Article 113 - The judgment and decree of the trial Court upheld as the counter-claim for accounts and a sum of Rs. 3,72,000/- were both found to be barred by limitation.
Fact of the Case:
The appellant questioned the legality of the judgment and decree passed by the First Additional District judge, East Nimar, Khandwa in Civil Suit no. 9b/2001, to the extent that the counterclaim for Rs. 3,72,000.00 filed by the appellant-defendant has been dismissed. The appellant and the respondent were partners in a firm, and the appellant retired from the firm with the respondent becoming the sole proprietor. The respondent filed a suit for accounts and recovery of a sum against the appellant and another party. The Court below dismissed both the suit and the counter-claim, leading to the present appeal.
Finding of the Court:
The Court found that the counter-claim for accounts and the sum of Rs. 3,72,000/- were both barred by limitation, upholding the judgment and decree of the trial Court.
Issues: The issues revolved around the legality of the judgment and decree, the applicability of different articles of the Limitation Act, and the timing of the filing of the counter-claim.
Ratio Decidendi: The counter-claim for accounts and the sum of Rs. 3,72,000/- were both found to be barred by limitation as per the provisions of the Limitation Act.
Final Decision: The appeal filed by the appellant was dismissed, and the parties were directed to bear their respective costs.
A.D.Deoras, AJAY OJHA, Ravish Agrawal, SANJAY SARVATE
( 1 ) THE appellant, in the present appeal, has questioned the legality of the judgment and decree dated 16-7-2001 passed by the First Additional District judge, East Nimar, Khandwa in Civil Suit no. 9b/2001, to the extent that the counterclaim for Rs. 3,72,000. 00 filed by the appellant-defendant has been dismissed.
( 2 ) THE facts of the case in brief are that the appellant and the respondent were both partners in a firm M/s. Naredi Goel Auto services, Civil Lines. Khandwa. By a deed of dissolution (Ex. P/7) dated 16-6-91 the appellant-defendant retired from the firm with effect from 31-3-1991 and the respondent-plaintiff became the sole proprietor of the firm from 1-4-1991. On 23-7-1991 (Ex. P/8)some of the amounts to be paid to the appellant as a result of the dissolution were settled in the presence of one Basant Kumar who also acted as a guarantor on behalf of the appellant-defendant. Thereafter, the respondent-plaintiff filed a suit for accounts and for recovery of a sum of Rs. 27,731. 71 with interest against the appellant-defendant and Basant Kumar Agrawal, who was impleaded as defendant No. 2.
( 3 ) THE appellant-defendant initially filed a counter-claim on 21-11-94 for accounts and for his share on dissolution and in addition prayed that the plaintiffs suit for a sum of Rs. 27,732. 71 be dismissed. However, subsequently the counter-claim was amended on 29-3-2000 and a relief of a decree of Rs. 3,72,000. 00 with interest at the rate of 24% from 1-4-91 was incorporated. It was alleged by the appellant-defendant in the counter-claim that subsequent to the dissolution of the firm vide the deed dated 16-6-91 and pending finalization of accounts, both the partners had agreed in the presence of Basant Kumar Agrawal on 23-7-91 that the respondent/plaintiff shall pay a sum of Rs. 1,50,000. 00 to the appellant/defendant against the book value of the pump, tanker and other stocks apart from the sum that would be found due to the appellant-defendant on finalization of accounts. It was also agreed that a sum of Rs. 75,000. 00 deposited in the name of rameshwar, father of the respondent-plaintiff, would also be paid to the appellant-defendant. It is alleged that admittedly the accounts of the firm were finalized as per the Chartered Accountant's Report dated 13-10-1991 in which a sum of Rs. 2,97,725. 24 was shown as due to the appellant-defendant. As the respondent-plaintiff did not pay this sum of Rs. 2,97,725. 24 as well as the agreed sum of Rs. 75,000. 00 standing in the name of Rameshwar to the appellant-defendant he was constrained to file the counterclaim.
( 4 ) THE Court below by the impugned judgment and decree dated 16-7-2001 has dismissed both the suit as well as the counter-claim. The respondent-plaintiff has not challenged the dismissal of his suit while the appellant -defendant has filed the present appeal against rejection of his counterclaim. The Court below by the impugned judgment has dismissed the counter-claim of the appellant-defendant only on the ground that the same was beyond the period of limitation prescribed by Article 5 of the Act as the counter-claim was filed on 21 -11 -94 while admittedly the firm was dissolved with effect from 31-3-91 i. e. beyond the period of three years from the date of dissolution of the partnership.
( 5 ) THE appellant-defendant has assailed the judgment and decree on the ground that the case of the appellant-defendant does not fall within the purview of Article 5 of the Act but in fact falls under Article 26 of the Limitation act. As the accounts had been settled between the parties by the interim agreement between them dated 23-7-91 Ex. P/8 according to which the respondent-plaintiff had admittedly agreed to pay the remaining amount till 30-4-1992, therefore the limitation of three years as prescribed under Article 26 of the Limitation Act would start running from 30-4-92 under Article 26 of the Act and not from the date of dissolution under Article 5 of the Act