MADHYA PRADESH HIGH COURT AT JABALBUR BENCH
A.K. Shrivastava, J.
Dulari Bai, Rajesh, Sunil and Sanjay - Appellant
Versus
Rameshwar Dayal Shrivastava and Smt. Sangeeta - Respondent
First Appeal No. 358-1995
Decided On : 21-02-2013
Specific Performance - Contract - Specific Relief Act - [Specific Performance] - [Specific Performance of Contract] - [Section 20(1) of Specific Relief Act] - [Valuation of the house, Loan transaction, Discretionary relief, Unfair advantage, Conduct of the parties]
Fact of the Case:
The plaintiff filed a suit for specific performance of a contract for the purchase of a double-storeyed house. The defendant contended that the transaction was a loan and not a sale. The Trial Court decreed the suit, but the appeal was filed by the LRs of the original defendant.
Finding of the Court:
The Court found that the transaction between the parties was a loan and not a sale. It held that the valuation of the house was not Rs. 25,000 as mentioned in the agreement, but was at least Rs. 2 lac. The Court exercised its discretion under Section 20(1) of the Specific Relief Act and decided against granting specific performance of the contract. The plaintiff was only entitled to a refund of the advance amount with interest.
Issues: 1. Whether the transaction was a sale or a loan. 2. Valuation of the house at the time of the agreement. 3. Exercise of discretion under Section 20(1) of the Specific Relief Act.
Ratio Decidendi: The Court held that the transaction was a loan and not a sale, based on the evidence presented. It also found that the valuation of the house was not as stated in the agreement. The Court exercised its discretion under Section 20(1) of the Specific Relief Act and decided against granting specific performance of the contract.
Final Decision: The appeal was allowed in part, setting aside the judgment and decree of the Trial Court. The suit of the plaintiff was decreed only for the refund of the advance amount with interest. The application under Order XLI Rule 27 CPC was not decided, and the parties were directed to bear their own costs.
A.K. Shrivastava, J.
1. Feeling aggrieved by the judgment and decree dated 04.08.1995 passed by learned Second Additional District Judge, Hoshangabad in Civil Suit No. 19-A/1991 (Old No. 91-/1986) whereby the suit of plaintiff-respondent has been decreed, this appeal under Section 96 of the CPC has been filed by the defendants no. 1 to 4-appellants. In the Trial Court the suit has been filed by Rameshwar Dayal Shrivastava against Prem Narayan alias Rabude however during the pendency of the suit the defendant died and present appellants as well as respondent no. 2 Smt. Sangeeta were brought on record as defendants, however, the fifth defendant (respondent no. 2) Smt. Sangeeta was proceeded ex parte.
2. The facts in compendium are that a suit for specific performance of contract has been filed by the plaintiff-first respondent in respect to a double-storeyed house, the description whereof has been mentioned in the plaint and which is the subject matter of the suit. According to the plaintiff in order to contest the election the original defendant Prem Narayan was in need of money, as a result of which, he gave an offer to the plaintiff to purchase his house for a consideration of Rs. 25000/- which was readily accepted by the plaintiff-respondent. Thereafter, on 17.04.1980 a registered agreement of sale was executed between the parties in which it has been stated that today i.e. 17.04.1980 the original defendant has obtained a sum of Rs. 22,984/- towards advance money and balance amount of consideration Rs. 2016/- would be paid within three year latest by 17.04.1983 and thereafter the sale-deed can be executed and the possession would also be delivered at that time. It was also agreed between the parties that the possession of the house in question will be delivered to plaintiff after getting the tenant evicted from the suit shop. When the original defendant failed to get the sale-deed executed, on 28.05.1983 a notice was sent to him by the plaintiff to get it executed. But, the original defendant requested that because at present he is unable to get an alternative residential accommodation for him and his family members and hence requested on humanitarian ground to provide some more time to get the sale-deed executed. Thereafter on 05.07.1983 another agreement of sale was executed between the parties wherein it has been mentioned by defendant that since still he could not arrange an alternative residential accommodation, therefore, further period of one year more may be provided to execute the sale-deed. This agreement was notarized. When the original defendant did not execute the sale-deed, again an agreement was executed acknowledging the earlier execution of agreements of sale and this was also stated in the said document that although in the agreement dated 05.07.1983 the original defendant sought time to execute the sale-deed but because again alternative residential house was not found, therefore, again time of one year was sought to execute the sale-deed. In the agreement dated 23.06.1984 it has been mentioned that additional sum of Rs. 16/- has also been paid towards advance by the plaintiff which has been received by original defendant Prem Narayan and he is only required to obtain balance consideration of Rs. 2000/-. Thereafter another agreement was executed by said Prem Narayan on 11.10.1985 wherein it was agreed by the defendant to get the sale-deed executed of the disputed house in favour of plaintiff upto 17.04.1986. But when the defendant failed to perform his part of contract after sending a registered AD post notice to him on 12.04.1986 and also on 07.10.1986 the plaintiff has filed the present suit for specific performance of contract.
3. In the plaint it has been pleaded by the plaintiff that he was throughout ready and willing to perform his part of contract but every time under the pretext that defendant could not arrange alternative house for himself and his family members, therefore, the sale-deed wa
The main legal point established in the judgment is the binding effect of the settlement between the parties, the waiver of the right to seek re-employment by the workmen, and the entitlement of the ....
A lockout is justified if it is declared in response to an illegal strike or a strike that is in breach of a settlement or award.
The combination of eyewitness testimonies, recovery of the weapon used, and forensic examination results can establish guilt in criminal cases, even based on circumstantial evidence.
The conviction of an accused person under Section 27(3) of the Arms Act is not permissible in law if the accused is also charged with committing murder under Section 302 of the Indian Penal Code.
The court can enhance compensation based on the deceased's income and family dependency, and adjust the multiplier used by the Tribunal if found unjustified.
A valid signature must be in the candidate's own handwriting, as emphasized by the General Clauses Act and relevant case law.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.