SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2015 Supreme(MP) 1053

IN THE HIGH COURT OF MADHYA PRADESH
N.K. GUPTA, J.
Mahinder Singh Bhasin - Appellant
Versus
Ssangyong Engineering and Construction Co. Ltd. - Respondent
M.Cr.C. No. 3547 of 2010
Decided On : 14-08-2015

Advocates Appeared:
For the Appellant : Bramhadatt Singh.
For the Respondents:Anoop Nair, Advocates.

The main legal point established is that cheques given for security purposes, and not as a legally enforceable debt or liability, do not fall within the purview of Section 138 of the NI Act.

Headnote:

NI Act - Cheque - Section 138 - 138 of NI Act

Fact of the Case:

The applicant issued a cheque to the respondent company, which was dishonoured. The respondent filed a complaint under Section 138 of the Negotiable Instruments Act (NI Act). The applicant sought to quash the proceedings, arguing that the cheque was given for security and not as a legally enforceable debt or liability.

Finding of the Court:

The court analyzed the terms and conditions of the agreement between the parties, the purpose of the cheques, and relevant legal provisions. It found that the cheques were given as security against mobilisation advance and were not legally enforceable debts or liabilities at the time of dishonour. The court invoked its inherent powers under Section 482 of the Cr.P.C. and quashed the criminal complaint against the applicant.

Issues: The main issue was whether the dishonoured cheques constituted a legally enforceable debt or liability under Section 138 of the NI Act.

Ratio Decidendi: The court relied on the terms of the agreement, the purpose of the cheques, and legal precedents to determine that the cheques were given for security and did not amount to a legally enforceable debt or liability at the time of dishonour.

Final Decision: The court allowed the petition under Section 482 of the Cr.P.C., quashed the proceedings of the criminal complaint case, and directed the trial court to drop the case against the applicant.

ORDER :

N.K. GUPTA, J.

1. This order shall govern the disposal of present matter as well as M.Cr.Cs.No. 2234/2010, 2235/2010, 3827/2010, 3828/2010, 3830/2010, 3842/2010, 3845/2010, 3853/2010, 3866/2010, 3870/2010, 3874/2010, 3876/2010, 3886/2010, 3995/2010, 6887/2010, 6888/2010, 6919/2010, 6920/2010, 6921/2010, 6922/2010, 12346/2010, 11785/2012, 11788/2012, 11789/2012, 11792/2012 and 11794/2012 because facts of such cases are same. However, in the present order facts of the present matter are mentioned.

2. The applicant has preferred the present petition under Section 482 of the Cr.P.C. to quash the proceedings of complaint case No. 2382/2009 pending before JMFC, Narsinghpur for offence under Section 138 of Negotiable Instruments Act (in short "NI Act").

3. The facts of the case, in short, are that, the applicant gave a cheque of Rs. 5 Lacs to the respondent company. Cheque was presented before the concerned bank on 15.6.2009 but, it was dishonoured because the applicant had given instructions to the concerned bank to stop the payment. A demand notice was given on 3.7.2009 and payment could not be received, thereafter, a criminal complaint was lodged before CJM, Narsinghpur, which was transferred to JMFC, Narsinghpur.

4. I have heard the learned counsel for the parties at length.

5. Learned counsel for the applicant submits that the amount of cheque was not recoverable because it was given for the purpose of security and therefore, no complaint under Section 138 of NI Act lies even if the applicant instructed the bank to stop the payment of the cheque. On the other hand, learned counsel for the respondent submits that the amount of cheque was due according to the terms of contract that took place between the parties.

6. If a work contract agreement executed by the parties is considered then, on its internal page No. 3, in para 9, terms and conditions for issuance of the cheque is mentioned, which is reproduced here-below for ready reference:-

"9. SSANGYONG will give Rupees 2 (Two) Crores as interest bearing Mobilisation Advance to the Sub Contractor for the costs of mobilization. The rate of interest being 10% per annum. Half of the amount shall be paid in advance and remaining half shall be paid directly to the suppliers on the behalf of the Sub Contractor, when sub Contractor has achieved 5% of financial progress. Sub Contractor have to submit post dated cheque/cheques of equivalent amount as a security against Mobilization Advance."

According to such condition, the respondent has given a mobilisation advance to the applicant. However, 50% of that amount was directly to be given to various suppliers from whom the applicant took the material and 50% of that amount was to be retained by the applicant to meet out other expenses of contract. However, the applicant was directed to submit post dated cheques equivalent to the amount as security against the mobilisation advance and consequently, he gave 25-26 cheques of various denominations to the respondent.

7. Also, according to the Para 12 of the aforesaid document, recoveries were to be made from monthly running bills of the applicant. It was also quoted in para 12 (C) that mobilisation advance recovery @ 12% from second R.A. bill onwards. Similarly, there was a termination clause of the contract also. In para 8 of that agreement, it was specifically mentioned that the post dated cheques given by the applicant were taken for equivalent amount against mobilisation advance as a security. Hence, such cheques could be encashed by the respondent if the contract is terminated and payment of various bills submitted by the applicant relating to work done by him should have been cleared. It is apparent that various proceedings for recovery of amount relating to work done in compliance to the aforesaid agreement are pending at various forums like Civil Court and Arbitration Tribunal. When various cheques were taken for security of the amount given as mobilisation advance then, the entire mobilisat
















Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
Judicial Analysis

AI

SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top