SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

1998 Supreme(MP) 937

MADHYA PRADESH HIGH COURT
Amarjeet Chaudhary, Dipak Misra, JJ.
SECRETARY OF STATE OF M.P., IRRIGATION DEPARTMENT, BHOPAL AND OTHERS - APPELLANTS
v.
JASWANT SINGH DHILLON - RESPONDENT
Civil Revision No. 54 of 1994 (J),
Decided on : November 24, 1998.

A statutory forum like the Tribunal was not established or brought into existence to give a new lease of life to already time-barred claims.

Headnote:

ARBITRATION - JURISDICTION - LIMITATION - TRIBUNAL - CLAIMS - BARRED BY LIMITATION - TRIBUNAL CANNOT ENTERTAIN - PURPOSE OF ESTABLISHMENT OF TRIBUNAL - NOT TO REVIVE TIME-BARRED CLAIMS.

Fact of the Case:

The claimant filed a reference before the Tribunal for recovery of Rs. 2,99,606.49 in relation to claims arising out of work contract No. 15/DL of 1980-81, dated 25-11-1980. The State Government assailed the award in Civil Revision No. 54/94 and the claimant-contractor questioned the pregnability of the same in Civil Revision No. 73/94.

Finding of the Court:

The Tribunal erred in law in holding that it had jurisdiction to deal with the claims of the claimants though it stood barred under Section 20(2) of the Adhiniyam. The Tribunal has grossly erred in rejecting the plea of limitation.

Issues: Whether the Tribunal had jurisdiction to deal with the claims of the claimants though it stood barred under Section 20(2) of the Adhiniyam. Whether the Tribunal erred in rejecting the plea of limitation.

Ratio Decidendi: The Tribunal was not brought into existence for revival of the time-barred claims. The purpose of the Adhiniyam was not to imbibe a life-spark to the dead claims and make them come alive like a phoenix. If the claims were barred by time under the Limitation Act, 1963 and the right to agitate those claims had been extinguished under the remedies which were in vogue before the Adhiniyam came into force, the same cannot be allowed to revive.

Final Decision: The revision is allowed and the award passed by the Tribunal is set aside.

ORDER

Dipak Misra, J. - As both the civil revisions arise from a common award dated 27-10-1993 passed in reference case No. 36/98 by the Madhya Pradesh Arbitration Tribunal in a reference under Section 7(i) of the M.P. Madhyastham Adhikaran Adhiniyam, 1983 (hereinafter referred to as 'the Adhiniyam'), they were heard analogously and are disposed of by this common order. The functionaries of the State have assailed the award in Civil Revision No. 54/94 and the claimant-contractor has questioned the pregnability of the same in Civil Revision No. 73/94.

2. The facts as have been unfurled are that the claimant filed the aforesaid reference before the Tribunal for recovery of Rs. 2,99,606.49 in relation to claims arising out of work contract No. 15/DL of 1980-81, dated 25-11-1980. The aforesaid agreement was executed for construction of 'Matia Moti Nallh Tank' for the earth work on the main bandh, from Chs. 16 to 22 in Mahanadi Godawari Basin, Raipur. The probable amount of contract was Rs. 10 lacs and the quoted rate of the respondent-petitioner therein was 2.76% and above UCSR. The stipulated period of contract was eight months and the work order was issued on 25-11-1980. Extension was granted to the claimant-respondent herein and the last extension was granted upto 31-5-1982 by reserving the right to impose penalty for delay in performance of contract. While the work was in progress the work of compaction and watering was withdrawn from the respondent-contractor for which he filed an application under Section 20 of the Indian Arbitration Act, 1940 (hereinafter referred to as 'the Act') in the Court of the learned. District Judge, Durg who appointed a Commissioner for recording the measurements and directed the State Government to appoint an Arbitrator under the agreement for settlement of disputes. But no action was taken by the State Government. The respondent, thereafter, filed an application for appointment of the Arbitrator by the Court under Section 8 of the Act. The learned District Judge vide order dated 19-7-1985 held that by virtue of Section 20 of the Adhiniyam the Civil Court had no jurisdiction and directed the respondent to approach the Tribunal. Thereafter, the claimants-respondents approached the Tribunal in the year 1988. The case of the respondents before the Tribunal was that the authorities of the State failed to supply the requisite designs, drawings and 'L' Section etc. It was also alleged that the carrying out of the work was not possible during the rainy season and the cut off trench excavated by the contractor-respondent was filled with water and slit. It was further alleged that there was no adequate arrangement for dewatering after rainy season. He resumed the work in cut-off trench but met with a peculiar type of strata and it was desired that the depth of cut off trench be determined afresh in consultation with Geologist. Accordingly the extra items of work, namely, construction of boulder toe and compaction and watering of earth were not within the scope of agreement, were included in the agreement by mutual consent of the parties. However, the work of compaction and watering later on was illegally and arbitrarily withdrawn by the authorities of the State Government. Owing to this illegal withdrawal the respondent could not complete the contract work within the stipulated time and the extended period. On the aforesaid grounds the imposition of penalty by the owner was assailed. It was also putforth before the Tribunal that the agreement quantities exceeded and the rates of extra items were revised by the owner but the same was not acceptable to the claimants. The final bill of Rs. 1,98,019/- was prepared. But it did not include the extra items of work and the payment for the work of compaction of watering etc. It was also illegal that final bill was also reduced to Rs. 42,742/- for no apparent reason. It was also setforth before the Tribunal that the State Administration allotted the balance work to





























Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top