SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2022 Supreme(Tri) 138

HIGH COURT OF TRIPURA AGARTALA
T. Amarnath Goud, S.G. Chattopadhyay, JJ.
Pranjit Saikia - Appellant
Versus
Food Corporation of India & Ors. - Respondents
RFA No. 17 of 2016 & RFA No. 22 of 2017
Decided On : 11-08-2022

Advocates appeared:
Mr. D.K.Biswas, Sr. Adv, Mr. G.K.Nama, Advocate, for the Appellant; Mr. R.G.Chakraborty, Advocate, for the Respondent

The court affirmed the legality of contract termination due to imposed load restrictions, highlighting that contractual obligations must be fulfilled to claim damages.

Headnote:(A) Contract Law - Contract for Transportation - Clause X(c) - Imposition of load restriction and contract termination - Contract was terminated by the respondent for non-compliance, leading to claims for damages by the appellant for alleged losses - The court held that the restrictions imposed were legal and that the agreement was not frustrated without fault of the appellant. (Paras 18-19)

(B) Liability for Breach of Contract - Security deposit withholding due to contract breach - The appellant’s claims for loss and damages were denied as no breach by the respondents was established. (Para 19)

(C) Appeal - While the contract was not performed, the court allowed partial relief for the return of the security deposit. (Para 22)

Facts of the case:
The appellant was a contract-transporter selected to transport food grains but faced contract termination due to imposed load restrictions and failure to execute the contract. The appellant alleged loss of profits and claimed the termination was illegal.

Findings of Court:
The court dismissed the appellant’s claims, affirming that the termination and security forfeiture were legal and justified.

Issues: The primary issue was whether the contract termination and imposition of load restrictions were justified and if the appellant was entitled to damages.

Ratio Decidendi: The court found the restrictions legal under existing statutes, emphasizing that contractual obligations cannot be evaded, and damages cannot be claimed without fulfilling the contract terms.

Result: The appeal stands partly allowed, directing the return of the security deposit.

Table of Content
1. grounds for contract termination and loss of profit. (Para 2 , 3 , 4 , 5)
2. appellant's claims regarding contractual obligations. (Para 6 , 7 , 9)
3. respondent’s defence against appellant's claims. (Para 10 , 11)
4. judgment dismissal and upholding of contract terms. (Para 12 , 13)
5. limited relief for return of security deposit. (Para 21 , 22)

JUDGMENT

T. Amarnath Goud, J. - These appeals, being RFA 17 of 2016 and RFA 22 of 2017 challenging the judgment and decree dated 27.02.2016 in T.S.130 of 2012 and Judgment and decree dated 26.04.2017 in T.S.106 of 2012 passed by the Civil Judge(Sr.Div), West Tripura, Agartala respectively, have been clubbed together for disposal by a common judgment.

2. The appellant contract-transporter in RFA 17 of 2016 having been selected under tender dated 12.08.2009[Exbt.1] floated by the Food Corporation of India (FCI for short)[respondent herein] for transporting food grains on behalf of FCI for two years, started transportation of the same after depositing 50% of the total security deposit on condition of deducting remaining 50% from the admitted bills at 5% as per the tender provision, meanwhile after repeated communications by the Executive Director, FCI, since 01.06.2010, the appellant received letter on 07.06.2010 informing the appellant of possible termination of contract and imposing 'risk and cost terms' obligation under which the appellant would be allowed to carry the load prescribed by the respondent only which was reduced to half of the weight the appellant contractors would carry, as usual, on commencement of the contract work thereby causing huge loss of profit to the appellant. The appellant was compelled to stop transportation of goods in the face of unbearable loss to an unbearable extent.

3. Subsequently, the agreement between the appellant and the respondent was terminated on the face of failure of enforcement of load regulation and fresh tenders were invited on 12.07.2010 for the residual part of the terminated agreement applying the risk and cost condition under Clause X(a),(b) and (c) of the agreement. The appellant was entrusted for transportation of goods by three agreements/contracts on different routes as under:

1) Guwahati to Chandrapur [the work commencing on 01.07.2008]

2) Guwahati to Dharmanagar [the work commencing on 07.12.2009]

3) Guwahati to Aizwal [the work commencing on 20.01.2010]

4) Churaibari to CWC Hafania and Dharmanagar to Hafania.

4. For remaining major part of the works the respondents floated fresh tenders on 13.07.2010 showing new rate per ton at Rs.4,700/- which was 2,001/-(from Changsari to Agartala in the terminated contract) preventing the appellant from contesting in the fresh tender stating them as defaulters. According to the appellant, it was impossible to perform transportation under new rate causing huge loss of profit. It is pleaded that the appellant would have earned profit provided under Schedule-2, if that rate was allowed to the plaintiff for performing remaining major part of the works.

5. Invoking the provisions of clause X(c), the respondent, by issuing notice dated 24.11.2010[Exbt.27], also cautioned the appellant that in the event of non execution of the remaining part of the work entrusted, the appellant shall be liable to make good to the respondent and fresh tender dated 13.07.2010[Exbt.21] was floated for engaging new transport contractors for completing the remaining part of the work.

6. Besides withholding and forfeiting the security money as shown in Schedule-1 of the Annexure, the respondents also raised demand for a huge sum of money from the appellant to realize risk and cost by issuing notices dated 01.11.2011, 11.08.2011, 26.06.2011 and 26.08.2011 [Exbt. 26 series].

7. So far the addition of clause in the said contract regarding load restriction is concerned, the appellant submits that no such clause was found available in the earlier tender notice dated 12.08.2009. Due to the severe restrictions imposed by the

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
Judicial Analysis

AI

SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top