MEGHALAYA HIGH COURT, SHILLONG
T. Nandakumar Singh, J.
Deng Bareh - Appellant
Versus
State of Meghalaya - Respondent
WP(C) No. 274/2011
Decided On : 20-03-2014
Land Acquisition - Land Acquisition Act, 1894 - The court directed the State respondents to take land acquisition proceeding under the Land Acquisition Act, 1894 for acquiring the land covered by the construction and erection of poles with electric wires passing through the land of the petitioner and pay adequate compensation to her. The Division Bench affirmed the directions for acquiring the land of the petitioner under the earlier order of the learned Single Judge. The court held that even for public purpose, the villagers or public cannot construct the road over the said land of the petitioner without necessary compensation. Forcibly taking over the land of a private individual without following due process of law, even for public purpose, is a violation of the constitutional right of the private individual under Article 300A of the Constitution of India.
Fact of the Case:
The petitioner sought a direction to complete the land acquisition proceeding for acquiring her land, which was used for construction of a village road and erection of electric poles with wires without compensation. The State respondents did not take up land acquisition proceeding despite previous court orders.
Finding of the Court:
The court found that the construction of the road and erection of electric poles without acquiring the land and without paying compensation was impermissible in law. The court directed the State respondents to take land acquisition proceeding under the Land Acquisition Act, 1894 and pay adequate compensation to the petitioner.
Issues: The issues involved the construction of a road and erection of electric poles on the petitioner's land without compensation, the failure of the State respondents to take land acquisition proceeding, and the contradictory pleas taken by the respondents.
Ratio Decidendi: The court held that even for public purpose, the villagers or public cannot construct the road over the said land of the petitioner without necessary compensation. Forcibly taking over the land of a private individual without following due process of law, even for public purpose, is a violation of the constitutional right of the private individual under Article 300A of the Constitution of India.
Final Decision: The court allowed the writ petition and directed the State respondents to complete the land acquisition proceeding under the Land Acquisition Act, 1894 within a specified period and pay the due land compensation along with interest. The court also observed that the petitioner may take actions for closing the road unless the concerned authorities pay the compensation, and if the petitioner takes recourse as per the court's observation, the authority concerned shall give necessary assistance and protection to the petitioner.
Judgment
T. Nandakumar Singh, J.Heard Mr. S.P. Mahanta, learned counsel for the petitioner and Mr. R. Gurung, learned GA appearing for the respondents No. 1, 2, 3 & 7. Also heard Mr. H. Kharmih, learned counsel for the respondents No. 4-6. This is the third round of litigation the petitioner had approached this Court for a direction to the respondents to complete the land acquisition proceeding for acquiring her land measuring 218 mtrs in length and 7 in mtrs breadth, which is, at present, used by the villagers as an approached road. It is stated in the writ petition, which is not denied by the respondents that the petitioner's land measuring 218 mtrs in length and 7 mtrs in breadth had been used for construction of the village road i.e. Twah-U-Sdiah Village. The petitioner had earlier approached this Court by filing a writ petition being WP(C) No. 252(SH)2003 against the present respondents and the said writ petition had been disposed of vide judgment and order dated 08.09.2008, by directing the State respondents to take up land acquisition proceeding under the Land Acquisition Act, 1894 for acquiring the said land of the petitioner which had already been used for construction of the road and erection of poles with electric wires. For convenience, the earlier order of this Court dated 08.09.2008 is quoted hereunder:-
8.9.2008
Heard Mr. S.P. Mahanta, learned counsel for the petitioner and Mr. S. Sen, learned counsel for respondent Nos. 1, 2, 3 and 6. Also heard Mr. H. Kharmih, learned counsel for the respondent Nos. 4 and 5.
The facts of the above case are very simple, not complicated. In pursuit of Local Area Development Fund of MLA, 7-War Jaiñtia Constituency, it is stated by the petitioner that the State PWD constructed a road upto Twah-U-Sdiah Village over the land of the petitioner measuring 218 mtrs length and 7 mtrs breadth, sometime, in the last part of 2002 during the subsistence of an interim order dated 22.11.2002 passed by this Court in WP(C) No. 422 (SH)2002 which was subsequently vacated on 19.05.2003.
The grievance of the petitioner is that the State PWD has encroached upon her land while constructing the road mentioned above and in addition to that, the MeSEB authorities have also erected electric poles with electric wires passing through the land of the petitioner without acquiring the land and without paying any form of rent and, as such, a direction is sought from this Court for appropriate order in accordance with law.
The respondents-the State Government, the State PWD and the MeSEB have not filed any counter affidavit disputing/controverting the averments made in the writ petition by the writ petitioner.
In the circumstances stated above, this Court is of the opinion that construction of road on the land of the petitioner and erection of electric poles with wires passing through the land of the petitioner without acquiring the land is not permissible in law and, accordingly, the respondents, particularly respondent Nos. 1, 2 and 3 are directed to take land acquisition proceeding under the Land Acquisition Act, 1894 for acquiring the land covered by the aforesaid construction and erection of poles with electric wires passing through the land of the petitioner and pay adequate compensation to her.
In view of the fact that the land belonging to the petitioner had been encroached upon in the matter stated above since 2002, it is made clear that the land acquisition proceeding shall be completed within a period of four months from the date of receipt of a copy of this order. In case the Collector is not above to complete the proceeding within the time stipulated by this Court, the Collector may approach this Court again for extension of time.
With the above, the writ petition stands disposed of.
2. The present respondents No. 4-6 preferred an appeal being Writ Appeal No. 44(SH)2008 before the Division Bench against the said judgment and order of the learned Single Judge dated 08.09.2008, which had been quoted above in e
The main legal point established in the judgment is the binding effect of the settlement between the parties, the waiver of the right to seek re-employment by the workmen, and the entitlement of the ....
A lockout is justified if it is declared in response to an illegal strike or a strike that is in breach of a settlement or award.
The combination of eyewitness testimonies, recovery of the weapon used, and forensic examination results can establish guilt in criminal cases, even based on circumstantial evidence.
The conviction of an accused person under Section 27(3) of the Arms Act is not permissible in law if the accused is also charged with committing murder under Section 302 of the Indian Penal Code.
The court can enhance compensation based on the deceased's income and family dependency, and adjust the multiplier used by the Tribunal if found unjustified.
A valid signature must be in the candidate's own handwriting, as emphasized by the General Clauses Act and relevant case law.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.