2018 Supreme(Megh) 11
IN THE HIGH COURT OF MEGHALAYA AT SHILLONG
S.R. Sen, J.
M/s. Agarwala Rice Enterprises - Petitioner
Vs.
Union of India & Ors. - Respondents
WP(C) No. 121 & 122 of 2018
Decided On : 26-09-2018
Important Points
Subject
Public Procurement - Bid Rejection
Act Referred
PUBLIC PROCUREMENT POLICY FOR MICRO AND SMALL ENTERPRISES ORDER : O.6
Headnote
SSI Unit - Public Procurement Policy - Micro, Small & Medium Enterprises Development Act 2006, Section 11, Order 6 - Office Memorandum dated 9th February, 2017 - Clause 20(d), 20(L), 20(Q) - Mandatory procurement of 20% from Micro, Small & Medium Enterprises - Rejection of tender based on non-furnishing of past performance cert and details of running contract and tender participation in FY 2018-19 - Court emphasizes adherence to NIT terms and conditions, eligibility, and non-discrimination in bidder selection
Fact of the Case:
Petitioners, SSI units, participated in a tender for supply of rice but their bids were rejected for not furnishing past performance certificate and details of running contract and tender participation in FY 2018-19. The court heard arguments from both parties and reviewed the case records of both petitions.
Finding of the Court:
The court found that the rejection of the tenders was based on non-furnishing of specific documents as required by the NIT. However, the court emphasized the importance of adherence to NIT terms and conditions, eligibility, and non-discrimination in bidder selection.
Issues: Rejection of tenders based on non-furnishing of specific documents, adherence to NIT terms and conditions, eligibility, and non-discrimination in bidder selection.
Ratio Decidendi: The court held that while the lowest bidder should get the tender, it does not mean that the lowest bidder will supply the lowest quality of goods. The invitee of the tender must select the bidder without favor or disfavor, considering the eligibility of past experience and capacity to supply the quality of goods. The court also emphasized that new growing firms without past experience should not be rejected solely on that ground if they fulfill all the terms and conditions of the NIT.
Final Decision: The court left the matter with the respondents to decide the proper bidder in accordance with the court's observations and to take necessary steps. Both petitions were disposed of by the common judgment, and the interim order was vacated subject to following the court's observations.
Advocate Appeared:
For the Petitioner: Mr. G.N. Sahewalla, Mr. M. Sahewalla, Mr. S. Saraogi
For the Respondents: Ms. A. Paul
1. Both WP(C) No.121/2018 and WP(C) No.122/2018 came up for hearing on 11-09-2018 as both the cases are almost similarly situated.
2. The brief facts of WP(C). No. 121/2018 is as follows:
“That the petitioner is a partnership firm and is a SSI Unit duly registered in the office of General Manager, The District Industries and Commerce Centre, Nagaon. The respondent no.2 issued invitation for online bid being Request for Proposal (RFP) bearing no. Q-DRY/RICE/SCH-01(B) /2018-19 dated 13.03.2018 issued by the Director General Assam Rifles, Shillong for supply of Rice (super fine) under Schedule No-01(B) to be delivered at 1 Maintenance Group Assam Rifles, Silchar (Assam) and 3 Maintenance Group Assam Rifles, Jorhat (Assam) and Air Maintenance Det, Happy Valley Shillong for the financial year 2018-19.
In pursuance of the aforesaid Request for Proposal (RFP) bearing no. Q-DRY/RICE/SCH-01(B)/2018-19 dated 13.03.2018, seven parties including the petitioner submitted its bid. The petitioner being eligible submitted its bid and annexed all the requisite documents. The private respondent no.3 to 5 also participated in the tender process. Be it mentioned herein that the petitioner is the only SSI unit which participated in the bidding process. The said bid was submitted online on the 09.04.2018 before the stipulated time as mentioned in the corrigendum. Thereafter the tender was opened as stipulated time. The petitioner was eagerly awaiting the results of the technical bid as the petitioner had fulfilled all the criteria for qualifying the technical bid. The result of the opening of the technical bid was to be declared in the online. After much wait the results were declared on 16.05.2018 online. A technical evaluation report was uploaded on 16.05.2018 with the digital signature of Commandant and according to the said report, the bid of the petitioner was declared invalid showing the reason “Past performance cert not uploaded by the firm. Tender form not completely filled & signed, details of running contract and tender participation in FY 2018-19 not submitted”, i.e. not satisfying the mandates of Clause 20(d).
Now, the Ministry of Micro, Small & Medium Enterprises (MSME) vide policy circular no. 1(2)(1)/2016-MA dated 10.03.2016 had clarified that all the central ministries/departments/central public sector undertaking (CPSUs) may relax conditions of prior turnover and prior experience with respect of Micro, Small & Medium Enterprises in all public procurement subject to meeting of quality and technical specification. This policy was adopted vide Office Memorandum of the Ministry of Finance, Department of Expenditure, Procurement Policy Division dated 25.07.2016. Further in the year 2017, the Office of the Development Commissioner, Department of Micro, Small & Medium Enterprises (MA Division) had passed an office memorandum bearing no. F No.1(2)(1)/2016-MA dated 09.02.2017 whereby it was stated and reaffirmed that „Government has already decided that there is no condition of prior turn over and prior experience. Traders and agents should not be allowed to avail the benefits extended under the PP policy?. As such the respondent authorities ought not to have invalidated the bid of the petitioner on the ground of non furnishing the Past performance cert.
Technical Evaluation Committee while rejecting the technical bid of the petitioner stated a reason that the petitioner had not furnished information regarding tender participation in FY 2018-19. Be it mentioned herein that the bid time of the tender in the instant case started from 15.03.2018 and ended on 09.04.2018. The financial year 2018-19 started from 01.04.2018 and the petitioner submitted the bid on the last day of the bid submission date, i.e. 09.04.2018. And as such it was only 9 (nine) days from the beginning of the financial year till the date of submission of bid by the petitioners and during that period of nine days it is not possible for the petitioner to participate in a