1. Contempt petition for alleged wilful violation of interim injunction restraining construction on suit property. (Para 1 )
2026 Supreme(Telangana) 527
IN THE HIGH COURT FOR THE STATE OF TELANGANA AT HYDERABAD
N. Tukaramji, J.
Mohd Sadiq Alia (died) Mohd. Ameer Ali Amjad and others - Petitioners
Versus
Mohd. Ghouse Mohiuddin Quadri Shafri and others - Contemnors
Contempt Case No.371 of 2019
Decided On : 08-09-2026
Important Points
Subject
Civil Law - Contempt of Court
Act Referred
CIVIL PROCEDURE CODE : O.39 R.1, O.39 R.2, O.39 R.2(a)
Headnote
(B) Maintainability of Contempt Proceedings - Where an order is passed by the High Court in exercise of its jurisdiction under Article 227 of the Constitution of India, the availability of a remedy under Order XXXIX Rule 2-A of the CPC does not render the order incapable of enforcement through the Court's contempt jurisdiction (Para 20).
(C) Clerical Errors in Court Orders - A subsequent correction of an inadvertent clerical description in an order to accurately reflect the relief already granted does not introduce new relief or enlarge the scope of the injunction (Para 15).
Facts of the case:
Petitioners sought initiation of contempt proceedings against respondents for violating an interim injunction restraining them from raising construction on the suit schedule property. Due to a clerical error, the initial order mentioned restraint against alienation instead of construction; this was corrected via an order dated 01.03.2019. Despite service of the corrected order on 05.03.2019, construction continued until 28.03.2019. The respondent claimed bona fide misunderstanding and later stopped construction upon learning of the contempt proceedings.
Findings of Court:
The Court found that the corrected order merely rectified a clerical error and did not create a new restraint. Evidence established that the respondent had knowledge of the order through service on 05.03.2019. Continuing construction after such knowledge constitutes wilful and deliberate disobedience. The plea of bona fide misunderstanding was rejected as it did not account for the conduct following the service of the corrected order.
Issues: Whether the respondents, having knowledge of the interim order, wilfully and deliberately disobeyed the same by raising or continuing construction over the suit schedule property (Para 11), and whether the contempt case was maintainable given the alternative remedy under Order XXXIX Rule 2-A of the CPC (Para 4.3).
Ratio Decidendi: Wilful disobedience is established when a party has actual or legally sufficient knowledge of a court order and intentionally fails to comply. Clerical corrections to an order do not change the substantive relief granted. Subsequent compliance does not erase the act of contempt but may mitigate the quantum of punishment.
Result: Respondent No. 9 held guilty of wilful disobedience; fine of Rs. 2,000/- imposed.
Legal Category Hierarchy
-
contempt of court
-
civil contempt
- wilful disobedience (Para 1)
-
civil contempt
-
practice and procedure
-
injunctions
-
interim injunction
- restraining construction
-
violation of injunction
- remedy under order xxxix rule 2-a cpc
-
interim injunction
- correction of clerical errors
- service of notice
-
injunctions
Table of Contents
ORDER :
N. Tukaramji, J.
This petition has been filed under Sections 10 and 12 of the Contempt of Courts Act, 1971 (for short, “the Act”), seeking initiation of contempt proceedings against the respondents/contemnors for their alleged wilful violation of the order dated 31.12.2018 passed in I.A. No. 2 of 2018 in C.R.P. No. 7750 of 2018. The petitioners seek invocation of the contempt jurisdiction of this Court and appropriate action, including punishment of the respondents/contemnors in accordance with law, for the alleged disobedience of the said order.
2. Ms. Manjari S. Ganu, learned Counsel argued on behalf of Mr. Sunil B. Ganu, learned Counsel Senior for the petitioners and Mr. K. Durga Prasad, learned Counsel for the respondents.
3.1. The case of the petitioners, in brief, is that they have filed C.R.P. No. 7750 of 2018 challenging the order dated 13.12.2018 passed in I.A. No. 252 of 2018 in I.A. No. 1910 of 2017 in O.S. No. 1040 of 2017 on the file of the XXV Additional Chief Judge, City Civil Court, Hyderabad. Along with the revision petition, the petitioners filed I.A. No. 2 of 2018 seeking an interim injunction restraining the respondents from changing the nature of the suit schedule property by raising any construction thereon. On 31.12.2018, this Court granted the interim injunction as prayed for and issued notice before admission. The petitioners also filed C.R.P. No. 7748 of 2018 seeking an injunction restraining the respondents from alienating the suit schedule property or creating any third-party interests therein, wherein a similar interim injunction was granted on 31.12.2018. It is stated that, while preparing the order in C.R.P. No. 7750 of 2018, the Registry inadvertently mentioned the prayer relating to alienation instead of the prayer seeking to restrain the respondents from raising any construction over the suit schedule property. The said mistake was subsequently corrected and an order dated 01.03.2019 was passed, duly reflecting the actual relief granted by this Court on 31.12.2018. According to the petitioners, the corrected order was duly communicated to all the respondents and was also served upon their Counsel.
3.2. The petitioners contend that, despite having knowledge of the corrected order and the interim injunction granted by this Court, the respondents continued with the construction over the suit schedule property in disobedience of the order dated 31.12.2018. It is, therefore, their case that the respondents’ conduct amounts to wilful, deliberate and intentional disobedience of the interim order of this Court. According to the petitioners, such conduct not only defeats the purpose and efficacy of the order passed by this Court but also undermines the authority and dignity of the Court and obstructs the due administration of justice. On these grounds, the petitioners contend that the respondents are liable to be proceeded against and punished under the provisions of the Act. They accordingly seek appropriate directions to ensure strict compliance with the interim order, apart from such other orders as this Court may deem fit and proper in the circumstances of the case.
4.1. Respondent No. 9, who filed a counter-affidavit on behalf of himself and respondent Nos. 10 to 17, contends that they are bona fide purchasers of different portions of the property bearing Municipal Nos. 20-3-25 and 26, Doodh Bowli, Hyderabad. It is stated that they acquired their respective portions under registered sale deeds, pursuant to which their names were duly mutated in the municipal records. It is further stated that building permissions were obtained for carrying out construction on the respective portions of the property. The respondents contend that the order dated 31.12.2018 passed in C.R.P. No. 7750 of 2018, as originally reflected in the order communicated through the Registry, contained an injunction restraining alienation, creation of third-party rights or encumbrance over the property, but did not contain any r