SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Online)(AP) 20048

HIGH COURT OF ANDHRA PRADESH
R. Raghunandan Rao, T.C.D. Sekhar, JJ
National Project Construction Ltd. – Appellant
Versus
E Kondaiah Constructions – Respondent
Civil Miscellaneous Appeal No.46 of 2009



Advocates:
For the Appellants/Petitioners: C Prakash Reddy
For the Respondents: Vivek Chandra Sekhar S, G Rama Gopal, A Krishnam Raju

Under Section 31(7)(b) of the Arbitration and Conciliation Act, 1996, interest on the sum directed to be paid by an arbitral award (which includes principal and pre-award interest) is permissible and does not constitute impermissible interest on interest.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 31(7)(b) - Interest on interest - Power of arbitrator to award interest on the sum directed to be paid by the award - The arbitrator awarded compensation with interest @ 15% on principal amounts from the date of completion to the date of award, and further interest @ 18% p.a. from the date of award till realization - The appellant contended that this amounted to impermissible interest on interest. (Paras 5-6)

(B) Arbitration Act, 1940 - Distinguished from Arbitration and Conciliation Act, 1996 - The Supreme Court in M/s. D. Khosla and Company Vs. The Union of India [2024] 8 S.C.R. 113, referring to the Arbitration Act, 1940, held that neither the Act nor the Interest Act permits interest upon interest. However, the present case arises under the Arbitration and Conciliation Act, 1996, and the ratio in Hyder Consulting (UK) Ltd. V. State of Orissa (2015) 2 SCC 189 and UHL Power Company Limited Vs. State of Himachal Pradesh (2022) 4 SCC 116 applies, which permits interest on the sum directed to be paid. (Paras 10-11)

Facts of the case:
The appellants entered into an agreement on 28.12.1994 for works contracts related to the Visakhapatnam Steel Plant. Disputes arose regarding enhanced consideration and compensation, which were referred to arbitration. The arbitrator passed an award on 15.03.2002. The appellants challenged the award before the VI Additional District Judge, Visakhapatnam, in A.O.P.No.572 of 2002, which was dismissed on 21.10.2005. The appellants then filed the present appeal before the High Court.

Findings of Court:
The court dismissed the appeal, holding that the grant of interest @ 18% on the award amount was not in violation of any provision of law. The court relied on the judgments in Hyder Consulting (UK) Ltd. V. State of Orissa and UHL Power Company Limited Vs. State of Himachal Pradesh, which permit interest on the sum directed to be paid under the Arbitration and Conciliation Act, 1996.

Issues: Whether the arbitrator had the power to award interest on interest under the Arbitration and Conciliation Act, 1996.

Ratio Decidendi: Under Section 31(7)(b) of the Arbitration and Conciliation Act, 1996, interest is granted on the "sum directed to be paid by an arbitral award," which includes the principal amount and interest accrued up to the date of the award. This does not constitute interest on interest, and is permissible. Result : Civil Miscellaneous Appeal dismissed.

Table of Content
1. background facts of the contract, disputes, arbitration award, and lower court dismissal. (Para 1 , 2 , 3)
2. appellant's argument that interest on interest is impermissible and respondent's counter-argument. (Para 4 , 5 , 6 , 7)
3. court's analysis of supreme court precedents on interest on interest under the arbitration acts. (Para 8 , 9 , 10 , 11)
4. final order dismissing the appeal and closing pending applications. (Para 12)

The Court made the following Judgment: (per Hon‟ble Sri Justice R. Raghunandan Rao)

The appellants herein, had entered into an Agreement, dated 28.12.1994, for execution of certain works contracts, in relation to the Visakhapatnam Steel Plant. Certain disputes had arisen between the parties, in relation to payment of enhanced consideration and compensation. These disputes were referred to Arbitration and resulted in an Award being passed by a learned Arbitrator, on 15.03.2002.

2. Aggrieved by the said Award, the appellants herein had moved A.O.P.No.572 of 2002 before the learned VI Additional District Judge, Visakhapatnam. The said petition came to be dismissed, on 21.10.2005.

3. Aggrieved by the said Order of Dismissal, the present Writ Appeal came to be filed.

4. Sri C. Prakash Reddy, learned counsel appearing for the appellants, assails the Award, on the ground that, the learned Arbitrator had awarded interest on interest and the same is impermissible and the entire Award has to be set aside.

5. The case of the appellants is that, the learned Arbitrator had awarded compensation, in relation to claims 1 to 8 made by the respondents. Along with the Principal Award under these claims, the learned Arbitrator also awarded interest @ 15%, on the principal amounts from the date of completion of contract to the date of the award. The aforesaid compensation which included the principal amounts and the interest thereon, amounted to Rs.32,73,171.59 paise. The learned Arbitrator, after arriving at this figure, had further awarded interest @ 18% p.a. from the date of award till the date of realization.

6. Sri C. Prakash Reddy, learned counsel appearing for the appellants, would rely upon the judgment of the Hon’ble Supreme Court in the case of M/s. D. Khosla and Company V. The Union of India , [2024] 8 S.C.R. 113: 2024 INSC 587, to contend that the learned Arbitrator did not have any power or authority to award interest on interest and consequently, the Award would have to be set aside. The Hon’ble Supreme Court, after referring to the judgments of the Hon’ble Supreme Court in the case of Hyder Consulting (UK) Ltd. V. State of Orissa, (2015) 2 SCC 189 and the judgment of the Hon’ble Supreme Court in the case of UHL Power Company Limited Vs. State of Himachal Pradesh , (2022) 4 SCC 116, had held as follows:

“24. Neither the Act specifically empowers the Arbitrator or the court to award interest upon interest or compound interest nor there is any other provision which provides for grant of compound interest or interest upon interest. Even Section 34 CPC is silent in this regard whereas Sub-Section (3) of Section 3 of the Interest Act specifically prohibits the same.”

7. Sri G. Rama Gopal, learned counsel appearing for the respondents, on the other hand, sought to take us through the judgments of the Hon’ble Supreme Court in the cases of Hyder Consulting (UK) Ltd. V. State of Orissa and UHL Power Company Limited Vs. State of Himachal Pradesh , to contend that there could be award of interest on interest by a learned Arbitrator, in Arbitration conducted under the Arbitration and Conciliation Act, 1996.

8. A three-Judge Bench of the Hon’ble Supreme Court in the case of Hyder Consulting (UK) Ltd. V. State of Orissa, while overruling the earlier judgment of the Hon’ble Supreme Court in the case of State of Haryana Vs. S.L. Arora & Co.,, (2010) 3 SCC 690, had held as follows:

“5……

“21. In the result , I am of the view that S.L. Arora case is wrongly decided in that it holds that a sum directed to be paid by an Arb

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top